3699 N ALTA MESA DR 91604

Certificate Information: 3699 N ALTA MESA DR 91604

Application / Permit
17010-10000-00418
Plan Check / Job No.
B17LA01610
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story single family dwelling with attached garage, carport and deck.
Permit Issued
Issued on 1/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2017 APPLICANT
Assigned to Plan Check Engineer 3/2/2017 RODOLFO ARIAS
Corrections Issued 3/6/2017 RODOLFO ARIAS
Quality Review Completed 3/10/2017 JOHN FRANCIA
Building Plans Picked Up 5/29/2018 APPLICANT
Applicant returned to address corrections 7/6/2018 RODOLFO ARIAS
Green Plans Picked Up 8/28/2018 APPLICANT
Applicant returned to address corrections 10/4/2018 RODOLFO ARIAS
Applicant returned to address corrections 10/23/2018 RODOLFO ARIAS
Applicant returned to address corrections 11/19/2018 RODOLFO ARIAS
Applicant returned to address corrections 12/3/2018 RODOLFO ARIAS
Applicant returned to address corrections 12/12/2018 RODOLFO ARIAS
Applicant returned to address corrections 4/26/2019 RODOLFO ARIAS
Applicant returned to address corrections 5/6/2019 RODOLFO ARIAS
Applicant returned to address corrections 5/16/2019 RODOLFO ARIAS
Applicant returned to address corrections 5/30/2019 RODOLFO ARIAS
Applicant returned to address corrections 7/24/2019 RODOLFO ARIAS
Applicant returned to address corrections 1/17/2020 RODOLFO ARIAS
Applicant returned to address corrections 1/22/2020 RODOLFO ARIAS
Plan Check Approved 1/28/2020 RODOLFO ARIAS
Issued 1/30/2020 LADBS
CofO in Progress 7/15/2025 CHRISTOPHE COCHRAN
Permit Finaled 7/21/2025 RUBEN SALAS
CofO Issued 7/21/2025 RUBEN SALAS
Permit Finaled 7/21/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2019 MARKOS PEREZ-BRAN
Miscellaneous Cleared 4/25/2019 DAISY BENICIA
ZA Case Cleared 4/25/2019 DAISY BENICIA
ZA Case Cleared 4/25/2019 DAISY BENICIA
ZA Case Cleared 4/25/2019 DAISY BENICIA
Excavation more than 5-ft deep Cleared 4/30/2019 CALOSHA APPROVED
Construction within easement Cleared 5/14/2019 RIDWAN HARDY
Construction near power lines Cleared 5/23/2019 RIDWAN HARDY
BHO/Hillside ordinance Cleared 8/21/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 8/21/2019 APEKSHYA BAJRACHARYA
Frnt yard landscape/Water mgmt Cleared 8/21/2019 RINA LARA
Miscellaneous Cleared 8/21/2019 RINA LARA
Miscellaneous Cleared 8/21/2019 RINA LARA
Miscellaneous Cleared 8/21/2019 RINA LARA
Sewer availability Cleared 8/21/2019 APEKSHYA BAJRACHARYA
Specific Plan Cleared 8/21/2019 RINA LARA
ZA Case Cleared 8/21/2019 RINA LARA
ZA Case Cleared 8/21/2019 RINA LARA
Green Code Cleared 9/3/2019 SEAN DANG
Hydrant and Access approval Cleared 9/3/2019 ROBERT DUFF
Low Impact Development Cleared 9/3/2019 ORVAL HERNANDEZ-MARCI
Miscellaneous Cleared 9/4/2019 LEE GUILBEAUX
Trees in Parkway Cleared 9/15/2019 ADRIAN SANCHEZ
Construction within easement Cleared 9/20/2019 OSCAR CASTRO
Disturb/Remove Protected Trees Cleared 9/20/2019 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 10/7/2019 LEE GUILBEAUX
Disturb/Remove Protected Trees Cleared 10/7/2019 ADRIAN SANCHEZ
Encroachment in public way Cleared 10/7/2019 LEE GUILBEAUX
Permit Cleared 10/7/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/7/2019 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 1/3/2020 LEE GUILBEAUX

Contact Information

Architect Mahmoodi,, Arshia; Lic. No.: C34875 6543 FRANKLIN AVENUE # 306      LOS ANGELES, CA 90028
Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2020 Approved ARAM AVEDISIAN
Pre-Inspection 4/21/2022 No Access for Inspection ARAM AVEDISIAN
Deputy Grading 7/12/2022 Approved BRIAN MILLER
Deputy Grading 7/13/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Grading 7/14/2022 Conditional Approval MATT KELLERMAN
Deputy Grading 7/15/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 9/7/2022 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 9/7/2022 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 9/7/2022 Approved CHRISTOPHE COCHRAN
Piling/Pier/Caisson 9/8/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 9/9/2022 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 10/11/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/12/2022 Conditional Approval MICHAEL SMITH
Deputy Reinf. Concrete 10/13/2022 Conditional Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 10/14/2022 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/17/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/24/2022 Approved CHRISTOPHE COCHRAN
Piling/Pier/Caisson 10/24/2022 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/26/2022 Conditional Approval MICHAEL SMITH
Deputy Reinf. Concrete 10/27/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/28/2022 Conditional Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 11/1/2022 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 11/2/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 12/28/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 2/8/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 2/14/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 2/22/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/22/2023 Approved WILLIAM WREN
Excavation/Setback/Form/Re-Bar 2/22/2023 Off-Hour Fees Due
Deputy Reinf. Concrete 2/23/2023 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/23/2023 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 3/15/2023 Not Ready for Inspection JOHN COLEMAN
Deputy Drilled-In Anchors 3/17/2023 Conditional Approval MICHAEL SMITH
Deputy Drilled-In Anchors 3/20/2023 Conditional Approval JUAN VALENZUELA
Underground Mechanical 3/20/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 3/24/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/4/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Steel/Welding 4/5/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 4/6/2023 Conditional Approval JUAN VALENZUELA
Deputy Shotcrete 4/10/2023 Conditional Approval DAVID MATSON
Deputy Steel/Welding 4/10/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 4/10/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 4/10/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Structural Steel Frame 4/10/2023 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 4/10/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/11/2023 Conditional Approval JUAN VALENZUELA
Deputy Shotcrete 4/11/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/12/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/12/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 4/12/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Structural Steel Frame 4/12/2023 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 4/12/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/13/2023 Conditional Approval JUAN VALENZUELA
Deputy Shotcrete 4/13/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/18/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/18/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/19/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 5/4/2023 Conditional Approval JUAN VALENZUELA
Deck 5/8/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/8/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 5/8/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/8/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 5/8/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Structural Steel Frame 5/8/2023 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 5/8/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Steel/Welding 5/9/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/19/2023 Conditional Approval JUAN VALENZUELA
Deputy Shotcrete 5/19/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/22/2023 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/22/2023 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/23/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/26/2023 Conditional Approval MICHAEL SMITH
Deputy Steel/Welding 5/26/2023 Conditional Approval MICHAEL SMITH
Deputy Steel/Welding 5/30/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 5/31/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/1/2023 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/1/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 6/1/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Grounding or Bonding 6/1/2023 Partial Approval CHRISTOPHE COCHRAN
Structural Steel Frame 6/1/2023 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 6/1/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/2/2023 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 6/9/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 6/22/2023 Conditional Approval MICHAEL SMITH
Deputy Reinf. Concrete 8/14/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 8/28/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 9/6/2023 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 10/13/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 10/13/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/16/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/16/2023 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 10/16/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 10/16/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/17/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 10/18/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/30/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 10/30/2023 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 10/31/2023 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 11/2/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 11/2/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Wood Construction 11/6/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 11/9/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 11/9/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 11/9/2023 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 11/15/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 11/15/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/17/2023 Partial Approval JOSE AVILA
Interior/Exterior Lathing 11/17/2023 Approved JOSE AVILA
Deputy Steel/Welding 11/20/2023 Conditional Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/21/2023 Approved CHRISTOPHE COCHRAN
Insulation 11/21/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/21/2023 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 12/4/2023 Approved CHRISTOPHE COCHRAN
Insulation 12/4/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/19/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 12/19/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/26/2023 Approved CHRISTOPHE COCHRAN
Special/Order Compliance 1/30/2024 Approved CHRISTOPHE COCHRAN
Deputy Grading 3/18/2024 Approved MANUEL TEJADA
Deputy Reinf. Concrete 3/20/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 3/21/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/3/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/4/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Final 4/24/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Service/Power Release 4/24/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/4/2024 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 6/4/2024 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 6/7/2024 Approved SALVADOR MARTINEZ
HVAC-Final 6/17/2024 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 6/24/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/1/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/8/2024 Approved JENNIFER RABUCHIN
HVAC-Final 7/8/2024 Approved JENNIFER RABUCHIN
Final 7/31/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/31/2024 Approved CHRISTOPHE COCHRAN
Green Building Final 7/31/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Reinforced Concrete Frame 7/31/2024 Approved CHRISTOPHE COCHRAN
Reinforced Masonry Frame 7/31/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 7/31/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 7/31/2024 Approved CHRISTOPHE COCHRAN
Structural Steel Frame 7/31/2024 Approved CHRISTOPHE COCHRAN
Sewer 4/4/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 4/9/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Sewer 4/11/2025 Approved CHRISTOPHE COCHRAN
Final 7/3/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 7/3/2025 Approved CHRISTOPHE COCHRAN
Service/Power Release 7/3/2025 Approved CHRISTOPHE COCHRAN