1006 N DOUGLAS ST 90026

Certificate Information: 1006 N DOUGLAS ST 90026

Application / Permit
17010-10000-00322
Plan Check / Job No.
B17LA01322
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SFD ABOVE 4- CAR GARAGE. (BUILDING 3)
Permit Issued
Issued on 11/15/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2017 APPLICANT
Green Plans Picked Up 2/22/2017 APPLICANT
Assigned to Plan Check Engineer 3/2/2017 ERIC CABRERA
Corrections Issued 3/7/2017 ERIC CABRERA
Quality Review Completed 3/8/2017 DAVID CHANG
Building Plans Picked Up 3/9/2017 APPLICANT
Plan Check Approved 5/2/2019 YAQUB MIRZA
Issued 11/15/2019 LADBS
CofO in Progress 6/16/2023 THOMAS LOGRASSO
No Progress 7/17/2023 THOMAS LOGRASSO
CofO in Progress 7/21/2023 THOMAS LOGRASSO
Permit Finaled 7/25/2023 DEROLD HAUFF
CofO Issued 7/25/2023 DEROLD HAUFF
Permit Finaled 7/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/27/2018 JEANETTE VONG
Address approval Cleared 12/27/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/27/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/27/2018 JEANETTE VONG
Highway dedication Cleared 12/27/2018 JEANETTE VONG
Highway dedication Cleared 12/27/2018 JEANETTE VONG
Permit Cleared 12/27/2018 JEANETTE VONG
Permit Cleared 12/27/2018 JEANETTE VONG
Sewer availability Cleared 12/27/2018 JEANETTE VONG
Sewer availability Cleared 12/27/2018 JEANETTE VONG
Hydrant and Access approval Cleared 1/16/2019 JOHN CONNEALLY
City Hist. Cultural Monument Cleared 4/5/2019 CHRISTINA PARK
HPOZ Cleared 4/5/2019 CHRISTINA PARK
Historic monument Cleared 4/5/2019 CHRISTINA PARK
Low Impact Development Cleared 4/5/2019 IDA MEISAMI-FARD
HPOZ Cleared 4/8/2019 CHRISTINA PARK
Historic monument Cleared 4/8/2019 CHRISTINA PARK
Roof/Waste drainage to street Cleared 4/12/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 4/12/2019 JEANETTE VONG
Green Code Cleared 4/19/2019 DONALD CRICHLOW
GPI Written Notices Cleared 5/2/2019 ERIC CABRERA
Grading Pre-Inspection Cleared 5/2/2019 ERIC CABRERA

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 345 W LORAINE ST #3      GLENDALE, CA 91202

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2020 No Access for Inspection SCOTT FINNILA
Underground Mechanical 1/27/2020 No Access for Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 1/30/2020 Corrections Issued AJA COLLAY
Underground Mechanical 1/30/2020 Not Ready for Inspection AJA COLLAY
Excavation/Setback/Form/Re-Bar 2/19/2020 Corrections Issued AJA COLLAY
Excavation/Setback/Form/Re-Bar 2/25/2020 Corrections Issued AJA COLLAY
Footing/Foundation/Slab 2/25/2020 Not Ready for Inspection AJA COLLAY
METHANE-Barrier 2/25/2020 Approved AJA COLLAY
METHANE-Subgrade 2/25/2020 Approved AJA COLLAY
Underground Mechanical 2/25/2020 Approved AJA COLLAY
Excavation/Setback/Form/Re-Bar 2/27/2020 Approved AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval STUART CHAPMAN
PLUMBING-Rough 6/22/2020 Approved OSVALDO PARAMO
HVAC-Rough 8/3/2020 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Approved ENRIQUE MIRELES
Special/Order Compliance 8/13/2020 Approved DAVID MATSON
ELECTRICAL-Rough 8/21/2020 Approved OSVALDO PARAMO
HVAC-Rough 9/16/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/9/2020 Partial Approval DONALD CRICHLOW
Insulation 10/16/2020 Conditional Approval SCOTT FINNILA
Shower Pan 10/16/2020 Approved SCOTT FINNILA
Insulation 11/20/2020 Conditional Approval DAVID CHAN
BUILDING-Rough-Frame 12/1/2020 Approved STUART CHAPMAN
Green Building Rough 12/1/2020 Approved STUART CHAPMAN
Insulation 12/1/2020 Approved STUART CHAPMAN
METHANE-Rough 12/1/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 12/1/2020 Approved STUART CHAPMAN
Drywall Nailing 12/11/2020 Approved RICHARD STEINBACH
Interior/Exterior Lathing 12/17/2020 Partial Approval RICHARD STEINBACH
Sewer 7/8/2021 Approved SCOTT FINNILA
Underground Mechanical 9/27/2021 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 10/7/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 10/15/2021 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 10/15/2021 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 10/19/2021 Partial Approval THOMAS LOGRASSO
PLUMBING-Final 9/2/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 9/14/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 9/26/2022 Not Ready for Inspection THOMAS LOGRASSO
Gas Test 9/26/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 9/26/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 10/5/2022 Approved THOMAS LOGRASSO
Gas Test 10/5/2022 Approved THOMAS LOGRASSO
PLUMBING-Final 10/5/2022 Approved THOMAS LOGRASSO
HVAC-Final 10/21/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 5/16/2023 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 5/16/2023 Approved THOMAS LOGRASSO
Green Building Final 5/16/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 5/16/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 5/16/2023 Approved THOMAS LOGRASSO
Final 5/25/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 6/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 6/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 6/16/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 6/16/2023 Approved THOMAS LOGRASSO
Service/Power Release 6/16/2023 Approved THOMAS LOGRASSO
Special/Order Compliance 7/11/2023 Corrections Issued THOMAS LOGRASSO