4452-4452 1/2 E TURQUOISE ST 90032
Certificate Information: 4452-4452 1/2 E TURQUOISE ST 90032
- Application / Permit
- 17010-10000-00281
- Plan Check / Job No.
- B17LA01137
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 3 STORY DUPLEXW/ATTACHED 4 CAR GARAGE
- Permit Issued
- Issued on 10/30/2017
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2017 | NEGAR NEJAD |
| Corrections Issued | 2/27/2017 | NEGAR NEJAD |
| Quality Review Completed | 2/28/2017 | DAVID CHANG |
| Building Plans Picked Up | 4/11/2017 | APPLICANT |
| Green Plans Picked Up | 5/18/2017 | APPLICANT |
| Applicant returned to address corrections | 7/3/2017 | NEGAR NEJAD |
| Plan Check Approved | 9/12/2017 | LAMAR DAVIS |
| No Progress | 9/13/2017 | LAMAR DAVIS |
| Plan Check Approved | 9/13/2017 | LAMAR DAVIS |
| Issued | 10/30/2017 | LADBS |
| CofO in Progress | 2/26/2020 | RUBEN SALAS |
| CofO in Progress | 2/26/2020 | RUBEN SALAS |
| Permit Finaled | 2/27/2020 | DEROLD HAUFF |
| CofO Issued | 2/27/2020 | DEROLD HAUFF |
| Permit Finaled | 2/27/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2017 | CELINA MORENO |
| Permit | Cleared | 4/21/2017 | CELINA MORENO |
| CPC | Cleared | 5/10/2017 | JESSE RAMOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2017 | ROCHELLE DUNGCA |
| Sewer availability | Cleared | 5/10/2017 | ROCHELLE DUNGCA |
| Specific Plan | Cleared | 5/10/2017 | JESSE RAMOS |
| Hydrant and Access approval | Cleared | 5/23/2017 | ROBERT DUFF |
| Opn space landscape/Water mgmt | Cleared | 6/15/2017 | EDBER MACEDO |
| Low Impact Development | Cleared | 6/29/2017 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 6/29/2017 | RAVIL MANAPOV |
| Green Code | Cleared | 7/3/2017 | NEGAR NEJAD |
| GPI Written Notices | Cleared | 9/12/2017 | NEGAR NEJAD |
| Grading Pre-Inspection | Cleared | 9/12/2017 | NEGAR NEJAD |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2018 | Partial Inspection | OSVALDO PARAMO |
| Pre-Inspection | 4/18/2018 | Partial Inspection | DOMINIC DANERI |
| Footing/Foundation/Slab | 4/20/2018 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/8/2018 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2018 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 9/4/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 9/4/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2018 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2019 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2019 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/5/2019 | Partial Approval | OSVALDO PARAMO |
| Green Building Final | 5/6/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 5/10/2019 | Approved | AJA COLLAY |
| Wood Frame | 5/10/2019 | Conditional Approval | AJA COLLAY |
| Insulation | 5/20/2019 | Approved | AJA COLLAY |
| Drywall Nailing | 5/24/2019 | Approved | RUBEN SALAS |
| Verify Sprinkler Sign Off | 6/6/2019 | Approved | OSVALDO PARAMO |
| Wood Frame | 6/6/2019 | Approved | OSVALDO PARAMO |
| Final | 11/8/2019 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 11/8/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2019 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 11/8/2019 | Approved | OSVALDO PARAMO |
| Final | 11/21/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 11/21/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 11/21/2019 | Partial Inspection | RUBEN SALAS |
| Final | 12/6/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 12/6/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 12/10/2019 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 12/10/2019 | Approved | OSVALDO PARAMO |
| Final | 2/26/2020 | OK to Issue CofO | RUBEN SALAS |