618 S VAN NESS AVE 1-6 90005

Certificate Information: 618 S VAN NESS AVE 1-6 90005

Application / Permit
17010-10000-00277
Plan Check / Job No.
B16LA18355
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4 Story, 6 unit appartment building (127' x 6 3/4") (Building 1)
Permit Issued
Issued on 12/6/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2016 APPLICANT
Assigned to Plan Check Engineer 12/23/2016 SALVADOR QUINTANILLA
Green Plans Picked Up 1/17/2017 APPLICANT
Corrections Issued 1/25/2017 SALVADOR QUINTANILLA
Plans on Hold 1/31/2017 MINYE PAK
Hold Released 7/6/2017 MINYE PAK
Quality Review Completed 7/13/2017 WING SUEN
Building Plans Picked Up 7/13/2017 APPLICANT
Disabled Access Plans Picked Up 8/3/2017 APPLICANT
Plan Check Approved 12/1/2017 SALVADOR QUINTANILLA
No Progress 12/1/2017 SALVADOR QUINTANILLA
Plan Check Approved 12/6/2017 SALVADOR QUINTANILLA
Issued 12/6/2017 LADBS
CofO in Progress 4/21/2021 EDWIN GREGORYONA
Permit Finaled 4/30/2021 ERNESTO CORRAL
CofO Issued 4/30/2021 ERNESTO CORRAL
Permit Finaled 4/30/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/7/2017 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 8/7/2017 RAVIL MANAPOV
Highway dedication Cleared 8/7/2017 RAVIL MANAPOV
Permit Cleared 8/7/2017 RAVIL MANAPOV
Sewer availability Cleared 8/22/2017 FATIMA GUERRA
Fire Marshall Fire Life Safety Cleared 9/5/2017 VIDAL GARCIA
Hydrant and Access approval Cleared 9/5/2017 ROBERT DUFF
DAS Clearance Cleared 9/7/2017 WAI LAU
Building over 3-story or 36-ft Cleared 9/13/2017 CALOSHA APPROVED
Green Code Cleared 9/13/2017 SALVADOR QUINTANILLA
Zoning Information File Cleared 9/13/2017 WING SUEN
Hold Cleared 10/10/2017 WING SUEN
Miscellaneous Cleared 10/24/2017 SALVADOR QUINTANILLA
Low Impact Development Cleared 11/17/2017 SAM NAVID
Roof/Waste drainage to street Cleared 11/17/2017 RAVIL MANAPOV
Frnt yard landscape/Water mgmt Cleared 11/29/2017 NOAH MCCOY
Miscellaneous Cleared 11/29/2017 NOAH MCCOY
Opn space landscape/Water mgmt Cleared 11/29/2017 NOAH MCCOY
Specific Plan Cleared 11/29/2017 NOAH MCCOY
Density Bonus 12.22.A.25 Cleared 12/1/2017 LOUIE MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/19/2018 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 2/8/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/9/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 2/9/2018 Not Ready for Inspection GREGORY POMISH
Deputy Steel/Welding 2/12/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/13/2018 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 2/13/2018 Partial Approval GREGORY POMISH
Deputy Steel/Welding 2/14/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/15/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/20/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/22/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 2/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 3/13/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/15/2018 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/16/2018 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 5/11/2018 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/5/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 6/5/2018 Corrections Issued LARRY ARNICK
Deputy Reinf. Concrete 6/13/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 6/14/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 6/20/2018 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 6/21/2018 Not Ready for Inspection LARRY ARNICK
T-Bar Ceiling 6/21/2018 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 6/22/2018 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 6/22/2018 Partial Approval LARRY ARNICK
Green Building Rough 6/22/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/22/2018 Not Ready for Inspection LARRY ARNICK
Wood Frame 6/22/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 7/3/2018 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 7/10/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/12/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 7/13/2018 Conditional Approval LARRY ARNICK
Reinforced Concrete Frame 7/13/2018 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 7/16/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/17/2018 Not Ready for Inspection LARRY ARNICK
Green Building Rough 7/18/2018 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 7/18/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 7/18/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 7/19/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/19/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 7/20/2018 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/20/2018 Partial Approval LARRY ARNICK
Green Building Rough 7/20/2018 Not Ready for Inspection LARRY ARNICK
Green Building Rough 7/20/2018 Off-Hour Fees Due
Verify Sprinkler Sign Off 7/20/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 7/20/2018 Off-Hour Fees Due
Wood Frame 7/20/2018 Off-Hour Fees Due
Footing/Foundation/Slab 7/25/2018 Partial Approval LARRY ARNICK
Deputy Drilled-In Anchors 7/26/2018 Conditional Approval LARRY ARNICK
Deputy Steel/Welding 8/24/2018 Conditional Approval LARRY ARNICK
Green Building Rough 1/17/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 1/27/2021 Not Ready for Inspection LARRY ARNICK
Final 1/27/2021 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/27/2021 Approved LARRY ARNICK
Green Building Final 1/27/2021 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/27/2021 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 1/27/2021 Approved LARRY ARNICK
Structural Steel Frame 1/27/2021 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/27/2021 Not Ready for Inspection LARRY ARNICK
Wood Frame 1/27/2021 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 2/9/2021 Not Ready for Inspection DAVID BURKHEAD
Final 2/9/2021 Partial Inspection DAVID BURKHEAD
Green Building Final 2/9/2021 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 2/9/2021 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 2/9/2021 SGSOV Approved DAVID BURKHEAD
Structural Steel Frame 2/9/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/9/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/9/2021 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 4/16/2021 Approved EDWIN GREGORYONA
Final 4/16/2021 Conditional Approval EDWIN GREGORYONA
Green Building Final 4/16/2021 Approved EDWIN GREGORYONA
Structural Steel Frame 4/16/2021 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/16/2021 Approved EDWIN GREGORYONA
Wood Frame 4/16/2021 Approved EDWIN GREGORYONA
Final 4/21/2021 Conditional Approval EDWIN GREGORYONA