Underground Mechanical
|
11/3/2017
|
Not Ready for Inspection
|
DAVID CHAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/24/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
1/24/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
2/13/2018
|
Approved
|
SCOTT FINNILA
|
|
Masonry Wall/Backfill
|
3/6/2018
|
Approved
|
CHARLENE BUSTAMANTE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/28/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/3/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/9/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
4/26/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Green Building Rough
|
4/26/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Verify Sprinkler Sign Off
|
4/26/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Drywall Nailing
|
4/30/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Steel/Welding
|
5/10/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
5/11/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/11/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Green Building Rough
|
5/11/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Verify Sprinkler Sign Off
|
5/11/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Deputy Wood Construction
|
5/15/2018
|
Conditional Approval
|
DOMINIC DANERI
|
|
Wood Frame
|
5/23/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Wood Construction
|
6/4/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/8/2018
|
Partial Inspection
|
DOMINIC DANERI
|
|
Wood Frame
|
6/8/2018
|
Partial Inspection
|
DOMINIC DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/11/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Structural Steel Frame
|
6/11/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Deputy Wood Construction
|
6/12/2018
|
Order to Comply Issued
|
SCOTT FINNILA
|
|
Deputy Steel/Welding
|
6/13/2018
|
Conditional Approval
|
DOMINIC DANERI
|
|
Drywall Nailing
|
6/13/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/13/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Structural Steel Frame
|
6/13/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/21/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Deputy Wood Construction
|
6/22/2018
|
Approved
|
MICHAEL FAUNCE
|
|
Deputy Steel/Welding
|
7/9/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Steel/Welding
|
7/10/2018
|
Conditional Approval
|
MICHAEL FAUNCE
|
|
BUILDING-Rough-Frame
|
8/2/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Verify Sprinkler Sign Off
|
8/2/2018
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Deputy Wood Construction
|
8/6/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
8/20/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
8/20/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Deputy Other (see comments)
|
9/17/2018
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
11/5/2018
|
Corrections Issued
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/5/2018
|
Partial Approval
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
1/2/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
1/2/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
1/2/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Rough-Elec/Plmb/HVAC
|
1/2/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
1/2/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Special/Order Compliance
|
1/3/2019
|
Approved
|
MATTHEW NUCKOLLS
|
|
BUILDING-Rough-Frame
|
1/11/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Insulation
|
1/11/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
1/15/2019
|
Corrections Issued
|
SCOTT FINNILA
|
|
Green Building Rough
|
1/15/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
1/15/2019
|
Approved
|
SCOTT FINNILA
|
|
Verify Sprinkler Sign Off
|
1/15/2019
|
Approved
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
3/8/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Gas Test
|
3/8/2019
|
Approved
|
SCOTT FINNILA
|
|
Green Building Rough
|
3/8/2019
|
Approved
|
SCOTT FINNILA
|
|
PLUMBING-Final
|
3/8/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
3/8/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
3/26/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Insulation
|
3/26/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
3/26/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Insulation
|
4/5/2019
|
Approved
|
SCOTT FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
4/5/2019
|
Approved
|
SCOTT FINNILA
|
|
Drywall Nailing
|
4/25/2019
|
Approved
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
5/31/2019
|
Approved
|
MICHAEL FAUNCE
|
|
Shower Pan
|
12/23/2019
|
Corrections Issued
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
1/9/2020
|
Partial Approval
|
SCOTT FINNILA
|
|
Shower Pan
|
1/13/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
1/14/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Sewer
|
2/4/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Sewer
|
2/11/2020
|
Corrections Issued
|
SCOTT FINNILA
|
|
Sewer
|
2/19/2020
|
Corrections Issued
|
SCOTT FINNILA
|
|
Sewer
|
2/25/2020
|
Corrections Issued
|
SCOTT FINNILA
|
|
Masonry Wall/Backfill
|
4/15/2020
|
Partial Inspection
|
SCOTT FINNILA
|
|
Underground Mechanical
|
5/20/2020
|
Partial Approval
|
SCOTT FINNILA
|
|
Underground Mechanical
|
6/10/2020
|
Partial Approval
|
SCOTT FINNILA
|
|
Underground Mechanical
|
6/17/2020
|
Corrections Issued
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
3/8/2021
|
Approved
|
SCOTT FINNILA
|
|
ELECTRICAL-Final
|
3/8/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Final
|
3/8/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Green Building Final
|
3/8/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
HVAC-Final
|
3/8/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
METHANE-Rough
|
3/8/2021
|
Approved
|
SCOTT FINNILA
|
|
PLUMBING-Final
|
3/8/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
SGSOV-Seismic Gas S/O Valve
|
3/8/2021
|
SGSOV Not Ready
|
SCOTT FINNILA
|
|
Service/Power Release
|
3/8/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Smoke Detectors
|
3/8/2021
|
Approved
|
SCOTT FINNILA
|
|
Final
|
5/25/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
HVAC-Final
|
5/25/2021
|
Approved
|
SCOTT FINNILA
|
|
PLUMBING-Final
|
5/25/2021
|
Approved
|
SCOTT FINNILA
|
|
SGSOV-Seismic Gas S/O Valve
|
5/25/2021
|
SGSOV Approved
|
SCOTT FINNILA
|
|
Final
|
6/17/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Gas Test
|
6/17/2021
|
Approved
|
SCOTT FINNILA
|
|
Green Building Final
|
6/17/2021
|
Approved
|
SCOTT FINNILA
|
|
Service/Power Release
|
6/17/2021
|
Approved
|
SCOTT FINNILA
|
|
Final
|
6/22/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
ELECTRICAL-Final
|
7/19/2021
|
Approved
|
SCOTT FINNILA
|
|
Final
|
7/19/2021
|
OK to Issue CofO
|
SCOTT FINNILA
|