1555 N AMALFI DR 90272
Certificate Information: 1555 N AMALFI DR 90272
- Application / Permit
- 16047-30000-02202
- Plan Check / Job No.
- B16WL06434
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool/spa
- Permit Issued
- Issued on 10/11/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2016 | DIEGO BAUTISTA |
| Corrections Issued | 12/19/2016 | DIEGO BAUTISTA |
| Quality Review Completed | 12/20/2016 | STEVEN KIM |
| Applicant returned to address corrections | 3/28/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 4/18/2017 | DIEGO BAUTISTA |
| Plan Check Approved | 6/15/2017 | DIEGO BAUTISTA |
| Issued | 10/11/2017 | LADBS |
| CofO in Progress | 8/16/2022 | JUAN VALENZUELA |
| Permit Finaled | 8/17/2022 | DANIEL ORRANTE |
| CofO Issued | 8/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2017 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/18/2017 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Boswell Construction Inc; Lic. No.: 934480-B | 17071 VENTURA BLVD STE 201 ENCINO, CA 91316 |
| Engineer | Daneshfar, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
| Engineer | Minas, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 4/14/2021 | Partial Approval | JOHN KIDWELL |
| Pool Piping | 4/14/2021 | Approved | JOHN KIDWELL |
| Pre-Gunite | 4/14/2021 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 5/12/2022 | Corrections Issued | JOHN KIDWELL |
| Enclosure/Fence | 5/17/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Enclosure/Fence | 5/20/2022 | Approved | JUAN VALENZUELA |
| Pool Equipment Noise Test | 6/8/2022 | Approved | AGUSTIN ALVAREZMORALES |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Approved | JUAN VALENZUELA |
| Final | 8/8/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Approved | JUAN VALENZUELA |
| Final | 8/16/2022 | OK to Issue CofO | JUAN VALENZUELA |