2451 N ARBUTUS DR 90049

Certificate Information: 2451 N ARBUTUS DR 90049

Application / Permit
16047-30000-02082
Plan Check / Job No.
B16WL06089
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
new pool and spa.
Permit Issued
Issued on 6/5/2018
Issuing Office
West Los Angeles
Current Status
Issued on 6/5/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2016 APPLICANT
Assigned to Plan Check Engineer 12/15/2016 DIEGO BAUTISTA
Corrections Issued 12/19/2016 DIEGO BAUTISTA
Green Plans Picked Up 12/20/2016 APPLICANT
Quality Review Completed 12/22/2016 STEVEN KIM
Building Plans Picked Up 12/22/2016 APPLICANT
Applicant returned to address corrections 6/21/2017 DIEGO BAUTISTA
Applicant returned to address corrections 3/5/2018 ERWIN PASCUA
Applicant returned to address corrections 5/16/2018 ERWIN PASCUA
Plan Check Approved 6/5/2018 ERWIN PASCUA
Plan Check Approved 6/5/2018 ERWIN PASCUA
Issued 6/5/2018 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/28/2018 LEE GUILBEAUX
Sewer availability Cleared 3/28/2018 LEE GUILBEAUX
Watercourse Cleared 5/22/2018 DENNIS BRAGIN

Contact Information

Architect , ; Lic. No.: C29604 3451 BUTLER AVENUE      LOS ANGELES, CA 90066
Architect , ; Lic. No.: C82109    18765 STRATTON LANE    HUNTINGTON BEACH, CA 92648
Contractor Houck Construction Inc; Lic. No.: 768547-B 1531 PONTIUS AVENUE      LOS ANGELES, CA 90025
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Tran, Quang Tai; Lic. No.: C70929 3889 FOUNTAIN ST      CAMARILLO, CA 93012
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/29/2020 Not Ready for Inspection TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 2/24/2022 Partial Approval JUAN VALENZUELA
FLOOD-Elevation Certificate 2/24/2022 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/21/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/2/2022 Partial Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Approval JUAN VALENZUELA
Rough-Plumbing 9/27/2022 Partial Approval JUAN VALENZUELA
Deputy Other (see comments) 9/28/2022 Conditional Approval JUAN VALENZUELA
Pre-Gunite 11/16/2022 Partial Approval JUAN VALENZUELA
Rough-Plumbing 11/16/2022 Partial Approval JUAN VALENZUELA
Deputy Shotcrete 11/28/2022 Conditional Approval KENNETH NAGLE
Grounding or Bonding 3/24/2023 Approved KEVIN SARGSYAN
Pool Piping 3/24/2023 Approved KEVIN SARGSYAN
Gas Piping or Gas Test 4/17/2023 Approved KEVIN SARGSYAN
Deck 9/1/2023 Approved KEVIN SARGSYAN
Deputy Shotcrete 12/11/2023 Conditional Approval KEVIN SARGSYAN
Enclosure/Fence 6/5/2026 Approved KEVIN SARGSYAN