1432 N TANAGER WAY 90069

Certificate Information: 1432 N TANAGER WAY 90069

Application / Permit
16047-30000-00772
Plan Check / Job No.
B16WL02252
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool and spa
Permit Issued
Issued on 8/4/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2016 APPLICANT
Assigned to Plan Check Engineer 5/26/2016 MANUEL GARCIA
Corrections Issued 6/2/2016 MANUEL GARCIA
Quality Review Completed 6/9/2016 GUANG MIN TUNG
Building Plans Picked Up 6/9/2016 APPLICANT
Green Plans Picked Up 6/10/2016 APPLICANT
Applicant returned to address corrections 6/27/2016 MANUEL GARCIA
Applicant returned to address corrections 7/7/2016 MANUEL GARCIA
Applicant returned to address corrections 7/12/2016 MANUEL GARCIA
Applicant returned to address corrections 8/22/2016 MANUEL GARCIA
Applicant returned to address corrections 9/29/2016 MANUEL GARCIA
Plan Check Approved 3/15/2017 MANUEL GARCIA
Issued 8/4/2017 LADBS
CofO in Progress 6/8/2023 RAUL BARAJAS
Permit Finaled 7/30/2023 DEROLD HAUFF
CofO Issued 7/30/2023 DEROLD HAUFF
Permit Finaled 7/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2016 ROBERT SAMONTE
Sewer availability Cleared 6/10/2016 ROBERT SAMONTE
Grading Pre-Inspection Cleared 12/13/2016 MANUEL GARCIA

Contact Information

Contractor Oh'S Design & Development; Lic. No.: 989612-B 500 SOUTH SHATTO PLACE #411      LOS ANGELES, CA 90020
Engineer Barajas, Jorge Luis; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Cox, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Peck, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2018 Partial Inspection DANIEL GONZALEZ
Pre-Inspection 12/18/2019 Not Ready for Inspection RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 11/19/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/26/2021 Approved RAUL BARAJAS
Grounding or Bonding 2/26/2021 Approved RAUL BARAJAS
Rough-Plumbing 2/26/2021 Approved RAUL BARAJAS
Deputy Shotcrete 3/1/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/1/2021 Approved RAUL BARAJAS
Grounding or Bonding 3/1/2021 Approved RAUL BARAJAS
Rough-Plumbing 3/1/2021 Approved RAUL BARAJAS
Pool Piping 5/14/2021 Partial Approval RUBEN SALAS
Rough-Electrical 5/14/2021 Partial Approval RUBEN SALAS
Rough-Plumbing 5/14/2021 Not Ready for Inspection RUBEN SALAS
Pool Piping 5/27/2021 Approved RAUL BARAJAS
Rough-Electrical 5/27/2021 Partial Approval RAUL BARAJAS
Rough-Plumbing 5/27/2021 Approved RAUL BARAJAS
Deck 5/24/2023 Approved RAUL BARAJAS
Enclosure/Fence 5/24/2023 Approved RAUL BARAJAS
Final 5/24/2023 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Approved RAUL BARAJAS
Final 6/8/2023 OK to Issue CofO RAUL BARAJAS