2175 W QUEENSBOROUGH LANE 90077

Certificate Information: 2175 W QUEENSBOROUGH LANE 90077

Application / Permit
16047-30000-00749
Plan Check / Job No.
B16WL02191
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
new pool & spa
Permit Issued
Issued on 10/23/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2016 APPLICANT
Assigned to Plan Check Engineer 5/26/2016 DIEGO BAUTISTA
Corrections Issued 5/29/2016 DIEGO BAUTISTA
Quality Review Completed 6/8/2016 GUANG MIN TUNG
Building Plans Picked Up 6/8/2016 APPLICANT
Green Plans Picked Up 6/10/2016 APPLICANT
Applicant returned to address corrections 8/9/2016 DIEGO BAUTISTA
Applicant returned to address corrections 8/23/2016 DIEGO BAUTISTA
Applicant returned to address corrections 8/31/2016 DIEGO BAUTISTA
Applicant returned to address corrections 9/19/2016 DIEGO BAUTISTA
Applicant returned to address corrections 12/12/2016 DIEGO BAUTISTA
Plan Check Approved 12/22/2016 DIEGO BAUTISTA
Issued 10/23/2017 LADBS
CofO in Progress 8/10/2023 CARLOS MATAMOROS
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2016 ERIK MUNOZ
Miscellaneous Cleared 6/14/2016 CASSANDRA ZWEEP
ZA Case Cleared 6/14/2016 CASSANDRA ZWEEP
Sewer availability Cleared 7/11/2016 AVALYN KAMACHI
Watercourse Cleared 12/5/2016 KEVIN AZARMAHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Cox, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/3/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/5/2021 Partial Approval CARLOS MATAMOROS
FLOOD-Elevation Certificate 2/5/2021 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 3/1/2021 Conditional Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 7/23/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/13/2021 Approved CARLOS MATAMOROS
Deputy Shotcrete 8/25/2021 Conditional Approval CARLOS MATAMOROS
FLOOD-Proofing Certificate 4/6/2023 Approved CARLOS MATAMOROS
Gunite 4/6/2023 Approved CARLOS MATAMOROS
Pre-Gunite 4/6/2023 Approved CARLOS MATAMOROS
Gunite 5/31/2023 Not Ready for Inspection CARLOS MATAMOROS
Enclosure/Fence 6/5/2023 Approved CARLOS MATAMOROS
Gunite 6/5/2023 Approved CARLOS MATAMOROS
Pool/Spa Cover 6/5/2023 Approved CARLOS MATAMOROS
Equipment Noise Level 6/6/2023 Not Ready for Inspection ZEYDI STEWART
Pool Equipment Noise Test 8/1/2023 Approved JUAN ESCOTO DELGADO
ELECTRICAL-Final 8/4/2023 Approved CARLOS MATAMOROS
Final 8/4/2023 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Approved CARLOS MATAMOROS