9231 W KINGLET DR 90069
Certificate Information: 9231 W KINGLET DR 90069
- Application / Permit
- 16047-30000-00697
- Plan Check / Job No.
- B16WL02041
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool/spa & water-feature
- Permit Issued
- Issued on 8/14/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2016 | CHON CHIO KUO |
| Corrections Issued | 5/10/2016 | CHON CHIO KUO |
| Quality Review Completed | 5/12/2016 | FELIX FIGUEROA |
| Building Plans Picked Up | 5/17/2016 | APPLICANT |
| Applicant returned to address corrections | 7/6/2016 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/19/2016 | CHON CHIO KUO |
| Green Plans Picked Up | 7/29/2016 | APPLICANT |
| Applicant returned to address corrections | 11/8/2016 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/11/2017 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/24/2017 | CHON CHIO KUO |
| Plan Check Approved | 7/13/2017 | CHON CHIO KUO |
| Issued | 8/14/2017 | LADBS |
| CofO in Progress | 8/20/2025 | RAUL BARAJAS |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
| CofO Issued | 8/23/2025 | DEROLD HAUFF |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2016 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 6/29/2016 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 6/29/2016 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 6/29/2016 | AVALYN KAMACHI |
| Permit | Cleared | 6/29/2016 | AVALYN KAMACHI |
| Sewer availability | Cleared | 6/29/2016 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 1/3/2017 | ZEMAMU GEBREWOLD |
| Hydrant and Access approval | Cleared | 1/17/2017 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/16/2017 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 3/16/2017 | ADRIAN SANCHEZ |
| Miscellaneous | Cleared | 6/20/2017 | TREVOR MARTIN |
| ZA Case | Cleared | 6/20/2017 | TREVOR MARTIN |
| BHO/Hillside ordinance | Cleared | 6/22/2017 | JACOB BIGLER |
| Excavation more than 5-ft deep | Cleared | 7/13/2017 | CALOSHA APPROVED |
| Private street | Cleared | 7/13/2017 | JOHN DACEY |
| ZA Case | Cleared | 7/13/2017 | JOHN DACEY |
Contact Information
| Architect | Scott, Utterstorm; Lic. No.: C34658 | 10315 JEFFERSON BL CULVER CITY, CA 90232 |
| Contractor | Dobkin Construction Inc; Lic. No.: 669554-B | 5401 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | Irvine, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD PASADENA, CA 91107 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Engineer | Obando, Gaspar Eduardo; Lic. No.: C71382 | 14000 TAHITI WY 303 MARINA DEL REY, CA 90292 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/17/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Electrical | 12/17/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Plumbing | 12/17/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 12/22/2021 | Partial Approval | RAUL BARAJAS |
| Final | 5/14/2025 | Not Ready for Inspection | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Not Ready | SCOTT FINNILA |
| Final | 6/18/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 6/27/2025 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | SCOTT FINNILA |
| Enclosure/Fence | 7/7/2025 | Approved | RAUL BARAJAS |
| Final | 8/12/2025 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Final | 8/14/2025 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | RAUL BARAJAS |
| Final | 8/20/2025 | OK to Issue CofO | RAUL BARAJAS |