600 PERUGIA WAY 90077

Certificate Information: 600 PERUGIA WAY 90077

Application / Permit
16047-30000-00395
Plan Check / Job No.
B16WL01276
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
new swimming pool and spa within.
Permit Issued
Issued on 9/13/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2016 APPLICANT
Assigned to Plan Check Engineer 3/17/2016 TARIK SAOUD
Corrections Issued 3/22/2016 TARIK SAOUD
Quality Review Completed 3/22/2016 GUANG MIN TUNG
Building Plans Picked Up 3/22/2016 APPLICANT
Applicant returned to address corrections 6/6/2016 TARIK SAOUD
Applicant returned to address corrections 9/7/2016 TARIK SAOUD
Plan Check Approved 9/8/2016 TARIK SAOUD
Issued 9/13/2016 LADBS
CofO in Progress 3/11/2020 CHRISTOPHER WILSON
Permit Finaled 1/3/2022 DANIEL ORRANTE
CofO Issued 1/3/2022 DANIEL ORRANTE
Permit Finaled 1/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/13/2016 BRIAN KELLY
Sewer availability Cleared 5/13/2016 BRIAN KELLY
Low Impact Development Cleared 5/16/2016 SAM NAVID
Grading Pre-Inspection Cleared 9/7/2016 TARIK SAOUD

Contact Information

Architect Glynn, Frank Christopher; Lic. No.: C19159 333 MAIN ST SUITE B      EL SEGUNDO, CA 90245
Contractor Greenbuild Construction Services Inc; Lic. No.: 937041-B 8200 WILSHIRE BLVD STE 200      BEVERLY HILLS, CA 90211
Engineer Parker, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025
Geologist Irvine, Jon A; Lic. No.: EG1691 1150 ENCANTO DR      ARCADIA, CA 91007

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/6/2016 Partial Approval ANTHONY ANDERSON
Deputy Pre-Stress Concrete 12/7/2016 Conditional Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 3/14/2017 Partial Approval ANTHONY ANDERSON
Deputy Other (see comments) 3/15/2017 Conditional Approval ANTHONY ANDERSON
Deputy Other (see comments) 3/16/2017 Conditional Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 3/24/2017 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 4/28/2017 Approved ANTHONY ANDERSON
Pool Piping 4/28/2017 Approved ANTHONY ANDERSON
Pre-Gunite 4/28/2017 Approved ANTHONY ANDERSON
Deputy Shotcrete 5/2/2017 Conditional Approval ANTHONY ANDERSON
Rough-Electrical 8/11/2017 Approved ANTHONY ANDERSON
Rough-Plumbing 8/11/2017 Approved ANTHONY ANDERSON
Rough-Plumbing 6/29/2018 No Access for Inspection MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 7/13/2018 Partial Approval MATT KELLERMAN
Grounding or Bonding 7/13/2018 Approved MATT KELLERMAN
Enclosure/Fence 3/8/2019 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 3/20/2019 Approved CHRISTOPHER WILSON
Final 12/6/2019 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/10/2019 Approved ROBERT SHELLY
Final 12/10/2019 Conditional Approval ROBERT SHELLY
SGSOV-Seismic Gas S/O Valve 12/10/2019 SGSOV Approved ROBERT SHELLY