1180 N PIEDRA MORADA DR 90272

Certificate Information: 1180 N PIEDRA MORADA DR 90272

Application / Permit
16047-30000-00357
Plan Check / Job No.
B16WL01114
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
swimming pool
Permit Issued
Issued on 2/23/2017
Issuing Office
Metro
Current Status
CofO Issued on 2/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2016 APPLICANT
Assigned to Plan Check Engineer 3/10/2016 VLADIMIR ARUTYUNYAN
Corrections Issued 3/14/2016 VLADIMIR ARUTYUNYAN
Quality Review Completed 3/21/2016 GUANG MIN TUNG
Building Plans Picked Up 4/13/2016 APPLICANT
Green Plans Picked Up 4/13/2016 APPLICANT
Plan Check Approved 11/4/2016 VLADIMIR ARUTYUNYAN
Issued 2/23/2017 LADBS
CofO in Progress 12/2/2022 BRENDAN LOONEY
Permit Finaled 2/11/2023 DANIEL ORRANTE
CofO Issued 2/11/2023 DANIEL ORRANTE
Permit Finaled 2/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/18/2016 LUZ RABELO
Sewer availability Cleared 5/18/2016 LUZ RABELO
Coastal Zone Cleared 8/22/2016 CASSANDRA ZWEEP

Contact Information

Contractor Tso Construction Inc; Lic. No.: 911570-B P O BOX 6883      MALIBU, CA 90264

Inspector Information

MICHAEL ALLEN, (310) 914-3886 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 4/10/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Grading 4/11/2017 Conditional Approval VINCENT SCIPIONI
Deputy Grading 4/12/2017 Conditional Approval VINCENT SCIPIONI
Deputy Grading 4/13/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Grading 4/14/2017 Conditional Approval VINCENT SCIPIONI
Deputy Grading 4/17/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Grading 4/18/2017 Conditional Approval VINCENT SCIPIONI
Deputy Grading 4/19/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Grading 4/20/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Grading 4/21/2017 No Access for Inspection VINCENT SCIPIONI
Excavation/Setback/Form/Re-Bar 5/11/2017 Partial Approval VINCENT SCIPIONI
Piling/Pier/Caisson 5/11/2017 Partial Approval VINCENT SCIPIONI
Excavation/Setback/Form/Re-Bar 1/3/2019 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 9/25/2020 Partial Approval ANDREW NAVE
Deputy Shotcrete 9/29/2020 Conditional Approval ANDREW NAVE
Pre-Gunite 10/7/2020 Not Ready for Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/13/2020 Partial Approval ANDREW NAVE
Deputy Shotcrete 10/21/2020 Conditional Approval ANDREW NAVE
Rough-Plumbing 10/27/2020 Partial Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/29/2020 Partial Approval JOHNNY MIRANDA
Pool Piping 12/29/2020 Partial Approval JOHNNY MIRANDA
Pre-Gunite 12/29/2020 Not Ready for Inspection JOHNNY MIRANDA
Rough-Electrical 12/29/2020 Partial Approval JOHNNY MIRANDA
Rough-Plumbing 12/29/2020 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 1/13/2021 Not Ready for Inspection ANDREW NAVE
Pool Piping 1/13/2021 Not Ready for Inspection ANDREW NAVE
Pre-Gunite 1/13/2021 Not Ready for Inspection ANDREW NAVE
Pre-Gunite 2/2/2021 Approved ANDREW NAVE
Rough-Electrical 2/2/2021 Approved ANDREW NAVE
Rough-Plumbing 2/2/2021 Approved ANDREW NAVE
Deputy Shotcrete 3/1/2021 Approved ROBERT SHELLY
Deputy Shotcrete 3/2/2021 Conditional Approval ANDREW NAVE
Gunite 5/13/2021 Approved ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/21/2021 Approved ANDREW NAVE
Final 12/21/2021 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Approved ANDREW NAVE
Final 9/22/2022 Not Ready for Inspection ANDREW NAVE
Final 9/28/2022 Corrections Issued BRENDAN LOONEY
Final 10/5/2022 Corrections Issued BRENDAN LOONEY
Final 12/1/2022 OK to Issue CofO BRENDAN LOONEY