10104 W ANGELO VIEW DR 90210
Certificate Information: 10104 W ANGELO VIEW DR 90210
- Application / Permit
- 16047-20000-02303
- Plan Check / Job No.
- B16VN17833
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW ELEVATED POOL/ SPA ON PILES/ GRADE BEAMS.
- Permit Issued
- Issued on 5/22/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2017 | GUANG MIN TUNG |
| Corrections Issued | 1/20/2017 | GUANG MIN TUNG |
| Quality Review Completed | 1/20/2017 | TIEN JEN WANG |
| Building Plans Picked Up | 1/23/2017 | APPLICANT |
| Plan Check Approved | 4/26/2017 | GUANG MIN TUNG |
| Issued | 5/22/2017 | LADBS |
| Permit Expired-Status Void | 6/11/2020 | MATT KELLERMAN |
| Re-Activate Permit | 11/21/2020 | MATT KELLERMAN |
| Permit Expired-Status Void | 11/24/2020 | ANTHONY MCDOWALL |
| Re-Activate Permit | 12/31/2020 | ANTHONY MCDOWALL |
| CofO in Progress | 9/21/2022 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 11/22/2022 | DANIEL ORRANTE |
| CofO Issued | 11/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2017 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 2/21/2017 | JOHN LIN |
| Sewer availability | Cleared | 2/21/2017 | JOHN LIN |
| ZA Case | Cleared | 3/17/2017 | EDBER MACEDO |
| ZA Case | Cleared | 3/17/2017 | EDBER MACEDO |
| Grading Pre-Inspection | Cleared | 3/29/2017 | GUANG MIN TUNG |
Contact Information
| Engineer | Nasser, Andrew Richard; Lic. No.: S1453 | 479 S MARENGO AVE PASADENA, CA 91101 |
| Geologist | Robertson, Hugh Schuyler Iii; Lic. No.: EG1001 | 2500 TOWNSGATE ROAD, SUITE E WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/17/2017 | Partial Approval | JOEL LAUNCHBAUGH |
| Excavation/Setback/Form/Re-Bar | 3/15/2018 | Partial Approval | JOEL LAUNCHBAUGH |
| Deputy Other (see comments) | 3/16/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Excavation/Setback/Form/Re-Bar | 8/22/2018 | Approved | CARLOS MATAMOROS |
| Deputy Other (see comments) | 8/24/2018 | Conditional Approval | CARLOS MATAMOROS |
| Pre-Inspection | 12/13/2018 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 1/2/2019 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/1/2019 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/8/2019 | Partial Approval | CARLOS MATAMOROS |
| Pre-Gunite | 7/2/2019 | Corrections Issued | CARLOS MATAMOROS |
| Grounding or Bonding | 7/17/2019 | Approved | CARLOS MATAMOROS |
| Pool Piping | 7/17/2019 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 7/17/2019 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 7/17/2019 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 7/23/2019 | Conditional Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 10/23/2019 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 6/11/2020 | Permit Expired-Status Void | MATT KELLERMAN |
| Enclosure/Fence | 11/24/2020 | Permit Expired-Status Void | ANTHONY MCDOWALL |
| Enclosure/Fence | 1/5/2021 | Approved | ANTHONY MCDOWALL |
| Grounding or Bonding | 4/12/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Grounding or Bonding | 4/15/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Grounding or Bonding | 4/16/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 6/3/2021 | Approved | ANTHONY MCDOWALL |
| Final | 6/3/2021 | Corrections Issued | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 6/3/2021 | SGSOV Not Ready | ANTHONY MCDOWALL |
| Final | 6/15/2021 | Partial Approval | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Approved | ANTHONY MCDOWALL |
| Final | 9/15/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/21/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |