7846 W GRANITO DR 90046
Certificate Information: 7846 W GRANITO DR 90046
- Application / Permit
- 16047-20000-02079
- Plan Check / Job No.
- B16VN16033
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 10'-0" X 33'-0" SWIMMING POOL AND 10'-0" X 5'-0" SPA WITHIN ON PILES PER ENGINEERING.
- Permit Issued
- Issued on 2/24/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2016 | JEROME MAGAT PALMA |
| Green Plans Picked Up | 12/8/2016 | APPLICANT |
| Corrections Issued | 12/12/2016 | JEROME MAGAT PALMA |
| Quality Review Completed | 12/15/2016 | MOURAD AZIZ |
| Building Plans Picked Up | 12/15/2016 | APPLICANT |
| Plan Check Approved | 2/22/2017 | JEROME MAGAT PALMA |
| Issued | 2/24/2017 | LADBS |
| CofO in Progress | 10/25/2022 | RAUL BARAJAS |
| Permit Finaled | 11/12/2022 | DEROLD HAUFF |
| CofO Issued | 11/12/2022 | DEROLD HAUFF |
| Permit Finaled | 11/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2017 | CELINA MORENO |
| Miscellaneous | Cleared | 1/17/2017 | CELINA MORENO |
| Sewer availability | Cleared | 1/17/2017 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 1/20/2017 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai, Luo B; Lic. No.: C80352 | 5244 HUCKLEBERRY OAK STREET SIMI VALLEY, CA 93063 |
| Engineer | Lau, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Geologist | Schick, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/28/2017 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/31/2017 | Partial Approval | CRAIG VAUGHAN |
| Deputy Other (see comments) | 8/7/2017 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/25/2017 | Approved | RAUL BARAJAS |
| Pool Piping | 9/18/2017 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Gunite | 9/18/2017 | Not Ready for Inspection | RAUL BARAJAS |
| Grounding or Bonding | 9/20/2017 | Approved | RAUL BARAJAS |
| Pool Piping | 9/20/2017 | Approved | RAUL BARAJAS |
| Pre-Gunite | 9/20/2017 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 12/11/2020 | No Access for Inspection | RAUL BARAJAS |
| Enclosure/Fence | 12/21/2020 | Corrections Issued | RAUL BARAJAS |
| Enclosure/Fence | 12/30/2020 | Corrections Issued | RAUL BARAJAS |
| Enclosure/Fence | 1/4/2021 | Approved | RAUL BARAJAS |
| Final | 1/4/2021 | Corrections Issued | RAUL BARAJAS |
| Final | 4/18/2022 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | RAUL BARAJAS |
| Final | 5/19/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 5/24/2022 | Partial Approval | RYAN SALAZAR |