8145 W WILLOW GLEN ROAD 90046

Certificate Information: 8145 W WILLOW GLEN ROAD 90046

Application / Permit
16047-20000-01721
Plan Check / Job No.
B16VN13436
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL & SPA
Permit Issued
Issued on 2/3/2017
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2016 APPLICANT
Assigned to Plan Check Engineer 10/20/2016 DOUGLAS NAKATANI
Corrections Issued 10/24/2016 DOUGLAS NAKATANI
Green Plans Picked Up 10/26/2016 APPLICANT
Quality Review Completed 10/27/2016 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/1/2016 APPLICANT
Applicant returned to address corrections 12/6/2016 DOUGLAS NAKATANI
Applicant returned to address corrections 1/20/2017 DOUGLAS NAKATANI
Applicant returned to address corrections 1/24/2017 DOUGLAS NAKATANI
Plan Check Approved 2/2/2017 DOUGLAS NAKATANI
Issued 2/3/2017 LADBS
CofO in Progress 12/18/2020 BRAD BESCOS
Permit Finaled 12/18/2020 DEROLD HAUFF
CofO Issued 12/18/2020 DEROLD HAUFF
Permit Finaled 12/18/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/14/2016 ROCHELLE DUNGCA
Roof/Waste drainage to street Cleared 11/14/2016 ROCHELLE DUNGCA
Sewer availability Cleared 11/14/2016 ROCHELLE DUNGCA
Miscellaneous Cleared 11/17/2016 TREVOR MARTIN
Miscellaneous Cleared 11/17/2016 TREVOR MARTIN
Miscellaneous Cleared 11/17/2016 TREVOR MARTIN
Specific Plan Cleared 11/17/2016 TREVOR MARTIN
ZA Case Cleared 11/17/2016 TREVOR MARTIN

Contact Information

Contractor Bykoff Construction Company; Lic. No.: 775986-B 1642 SIERRA BONITA      LOS ANGELES, CA 90046
Engineer Azizisefat, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/21/2017 Approved RAUL BARAJAS
Grading Pre-Inspection 8/21/2017 Not Ready for Inspection RAUL BARAJAS
Grounding or Bonding 8/30/2017 Partial Approval RAUL BARAJAS
Gunite 8/30/2017 Partial Approval RAUL BARAJAS
Pool Piping 8/30/2017 Partial Approval RAUL BARAJAS
Pre-Gunite 8/30/2017 Conditional Approval RAUL BARAJAS
Rough-Electrical 8/30/2017 Partial Approval RAUL BARAJAS
Rough-Plumbing 8/30/2017 Partial Approval RAUL BARAJAS
Final 6/9/2020 Not Ready for Inspection RAUL BARAJAS
Pre-Gunite 6/9/2020 Conditional Approval RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/9/2020 SGSOV Not Ready RAUL BARAJAS
Final 10/6/2020 Corrections Issued RAUL BARAJAS
Pre-Gunite 10/6/2020 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Approved RAUL BARAJAS
Final 12/1/2020 Not Ready for Inspection BRAD BESCOS
Final 12/18/2020 Conditional Approval BRAD BESCOS