1944 S TUDOR LANE 90034
Certificate Information: 1944 S TUDOR LANE 90034
- Application / Permit
- 16047-20000-01355
- Plan Check / Job No.
- B16VN10485
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- BUILD 16' X 31' IRREGULAR SHAPE POOL WITH 8' DIAMETER ATTACHED SPA PER STD. PLAN #242
- Permit Issued
- Issued on 8/4/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2016 | ALDOUS CHIC |
| Corrections Issued | 8/3/2016 | ALDOUS CHIC |
| Plan Check Approved | 8/4/2016 | ALDOUS CHIC |
| Issued | 8/4/2016 | LADBS |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/3/2016 | TREVOR MARTIN |
| ZA Case | Cleared | 8/3/2016 | TREVOR MARTIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2016 | RICHARD SOUTHERLAND |
| Sewer availability | Cleared | 8/4/2016 | RICHARD SOUTHERLAND |
Contact Information
| Contractor | Pdq Construction; Lic. No.: 706088-B | 10846 LOUISE AVE GRANADA HILLS, CA 91344 |
| Engineer | Shniderman, Jason Bernard; Lic. No.: C20524 | 16000 SHERMAN WAY #234 VAN NUYS, CA 91607 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/22/2016 | Not Ready for Inspection | CRAIG DAVIS |
| Pre-Gunite | 9/6/2016 | Not Ready for Inspection | CRAIG DAVIS |
| Pre-Gunite | 9/15/2016 | Not Ready for Inspection | CRAIG DAVIS |
| Deck | 10/18/2016 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 3/8/2017 | Not Ready for Inspection | CRAIG DAVIS |
| Enclosure/Fence | 3/8/2017 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 3/8/2017 | Approved | CRAIG DAVIS |
| Final | 3/8/2017 | Not Ready for Inspection | CRAIG DAVIS |
| Gunite | 3/8/2017 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 3/8/2017 | Not Ready for Inspection | CRAIG DAVIS |
| Pool Piping | 3/8/2017 | Approved | CRAIG DAVIS |
| Pool/Spa Cover | 3/8/2017 | Not Ready for Inspection | CRAIG DAVIS |
| Pre-Gunite | 3/8/2017 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2017 | SGSOV Not Ready | CRAIG DAVIS |
| Enclosure/Fence | 4/17/2017 | Corrections Issued | LUIS ALVAREZ |
| Enclosure/Fence | 4/19/2017 | Approved | MATTHEW NUCKOLLS |
| ELECTRICAL-Final | 1/19/2018 | Approved | SCOTT FINNILA |
| Final | 1/19/2018 | Partial Approval | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/19/2018 | SGSOV Approved | SCOTT FINNILA |
| Special/Order Compliance | 10/7/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 10/9/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 11/6/2025 | Conditional Approval | BRENDAN MORELLI |