1116 N CHANTILLY ROAD 90077
Certificate Information: 1116 N CHANTILLY ROAD 90077
- Application / Permit
- 16047-10000-01796
- Plan Check / Job No.
- B15WL05302
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) Pool/spa
- Permit Issued
- Issued on 4/24/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2015 | APPLICANT |
| Green Plans Picked Up | 10/27/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2015 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 11/3/2015 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 11/6/2015 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 11/10/2015 | APPLICANT |
| Plan Check Approved | 4/24/2018 | VLADIMIR ARUTYUNYAN |
| Issued | 4/24/2018 | LADBS |
| CofO in Progress | 6/14/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| CofO Issued | 6/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2016 | KELTON KIRBY |
| Sewer availability | Cleared | 10/19/2016 | KELTON KIRBY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/23/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Grounding or Bonding | 3/23/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Gunite | 3/23/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/30/2021 | Approved | CHRISTOPHER WILSON |
| Grounding or Bonding | 3/30/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 3/30/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 3/30/2021 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 3/30/2021 | Partial Approval | CHRISTOPHER WILSON |
| Enclosure/Fence | 10/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Enclosure/Fence | 10/13/2022 | Approved | CHRISTOPHER WILSON |
| Final | 11/28/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 5/23/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 6/12/2024 | OK to Issue CofO | CHRISTOPHER WILSON |