1116 N CHANTILLY ROAD 90077

Certificate Information: 1116 N CHANTILLY ROAD 90077

Application / Permit
16047-10000-01796
Plan Check / Job No.
B15WL05302
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) Pool/spa
Permit Issued
Issued on 4/24/2018
Issuing Office
Valley
Current Status
CofO Issued on 6/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2015 APPLICANT
Green Plans Picked Up 10/27/2015 APPLICANT
Assigned to Plan Check Engineer 10/29/2015 VLADIMIR ARUTYUNYAN
Corrections Issued 11/3/2015 VLADIMIR ARUTYUNYAN
Quality Review Completed 11/6/2015 DOUGLAS NAKATANI
Building Plans Picked Up 11/10/2015 APPLICANT
Plan Check Approved 4/24/2018 VLADIMIR ARUTYUNYAN
Issued 4/24/2018 LADBS
CofO in Progress 6/14/2024 CHRISTOPHER WILSON
Permit Finaled 6/17/2024 DANIEL ORRANTE
CofO Issued 6/17/2024 DANIEL ORRANTE
Permit Finaled 6/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/19/2016 KELTON KIRBY
Sewer availability Cleared 10/19/2016 KELTON KIRBY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/26/2019 Partial Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/23/2021 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 3/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Gunite 3/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/30/2021 Approved CHRISTOPHER WILSON
Grounding or Bonding 3/30/2021 Partial Approval CHRISTOPHER WILSON
Pool Piping 3/30/2021 Approved CHRISTOPHER WILSON
Pre-Gunite 3/30/2021 Approved CHRISTOPHER WILSON
Rough-Electrical 3/30/2021 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 10/6/2022 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 10/13/2022 Approved CHRISTOPHER WILSON
Final 11/28/2023 Corrections Issued CHRISTOPHER WILSON
Final 5/23/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 6/12/2024 OK to Issue CofO CHRISTOPHER WILSON