3949 N GLENALBYN DR 90065
Certificate Information: 3949 N GLENALBYN DR 90065
- Application / Permit
- 16030-10000-09642
- Plan Check / Job No.
- B16LA20698
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Site grading for excavation of basement and retaining walls; 770 c.y. cut & export
- Permit Issued
- Issued on 4/3/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/5/2023
Permit Application Status History
| Submitted | 12/29/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2017 | VU NGUYEN |
| Corrections Issued | 3/9/2017 | KRIKOR MANOUKIAN |
| Quality Review Completed | 3/17/2017 | BINH PHAN |
| Building Plans Picked Up | 4/12/2017 | APPLICANT |
| Green Plans Picked Up | 4/12/2017 | APPLICANT |
| Applicant returned to address corrections | 6/28/2018 | KRIKOR MANOUKIAN |
| Plan Check Approved | 3/22/2019 | VU NGUYEN |
| Issued | 4/3/2020 | LADBS |
| Permit Finaled | 6/5/2023 | ROBERT HUGHES |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/9/2018 | EDBER MACEDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tan, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/3/2020 | Corrections Issued | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 12/29/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Special/Order Compliance | 1/8/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Deputy Grading | 3/19/2021 | Approved | ROBERT HUGHES |
| Sub-Drain | 5/3/2021 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 5/18/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 5/18/2021 | Partial Approval | ROBERT HUGHES |
| Excavation | 3/24/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 4/15/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 4/15/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Approved Compaction Report | 2/15/2023 | Approved | KIRK LINKLATER |
| Bottom/Toe | 4/27/2023 | Approved | ROBERT HUGHES |
| Final | 4/27/2023 | Corrections Issued | ROBERT HUGHES |
| Rough | 4/27/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Final | 6/5/2023 | Permit Finaled | ROBERT HUGHES |
| Rough | 6/5/2023 | Approved | ROBERT HUGHES |