340 N PATTON ST 90026
Certificate Information: 340 N PATTON ST 90026
- Application / Permit
- 16020-30000-00952
- Plan Check / Job No.
- B16WL01770
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Permanent)
- Work Description
- temporary shoring fo apartment building
- Permit Issued
- Issued on 5/31/2018
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 2/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2016 | TARIK SAOUD |
| Corrections Issued | 5/23/2016 | TARIK SAOUD |
| Quality Review Completed | 5/27/2016 | GUANG MIN TUNG |
| Building Plans Picked Up | 5/31/2016 | APPLICANT |
| Green Plans Picked Up | 5/31/2016 | APPLICANT |
| Applicant returned to address corrections | 12/13/2016 | TARIK SAOUD |
| Applicant returned to address corrections | 5/25/2017 | TARIK SAOUD |
| Plan Check Approved | 4/11/2018 | TARIK SAOUD |
| Issued | 5/31/2018 | LADBS |
| Permit Finaled | 2/26/2021 | JAMES POWERS |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 12/20/2017 | CALOSHA APPROVED |
Contact Information
| Contractor | S H Z Development Inc; Lic. No.: 899219-B | 11516 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Engineer | Dejban, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
| Engineer | Sahebi, Mo; Lic. No.: C33508 | 1330 OLYMPIC BL SANTA MONICA, CA 90404 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/4/2018 | Partial Inspection | WINSTON DUNNING |
| Deputy Grading | 6/27/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 6/28/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 6/29/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/5/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/6/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/9/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/10/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/11/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/12/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/13/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/16/2018 | Conditional Approval | WINSTON DUNNING |
| Piling/Pier/Caisson | 7/16/2018 | Partial Inspection | WINSTON DUNNING |
| Deputy Grading | 7/17/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/18/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/19/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/20/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Drilled-In Anchors | 7/23/2018 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Drilled-In Anchors | 7/24/2018 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Drilled-In Anchors | 7/25/2018 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Drilled-In Anchors | 7/26/2018 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Drilled-In Anchors | 7/27/2018 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 7/30/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 7/31/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/1/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/2/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/3/2018 | Conditional Approval | WINSTON DUNNING |
| Piling/Pier/Caisson | 8/3/2018 | Partial Inspection | WINSTON DUNNING |
| Deputy Grading | 8/14/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/15/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/16/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/17/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/24/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/27/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/28/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/29/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/30/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/31/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/4/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/5/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/6/2018 | Conditional Approval | WINSTON DUNNING |
| Piling/Pier/Caisson | 9/6/2018 | Partial Inspection | WINSTON DUNNING |
| Deputy Grading | 9/7/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/10/2018 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 9/11/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/12/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/13/2018 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/14/2018 | Conditional Approval | WINSTON DUNNING |
| Wood Frame | 8/8/2019 | Partial Inspection | LESLIE TRUJILLO |
| Drywall Nailing | 8/14/2019 | Partial Approval | LESLIE TRUJILLO |
| Wood Frame | 8/14/2019 | Partial Approval | LESLIE TRUJILLO |
| Pre-Inspection | 6/23/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 6/26/2020 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 7/17/2020 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 7/17/2020 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 7/28/2020 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 8/7/2020 | Partial Approval | NICK DANERI |
| Special/Order Compliance | 8/18/2020 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/4/2020 | Partial Approval | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 9/25/2020 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 10/28/2020 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 11/16/2020 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 1/25/2021 | Partial Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 2/5/2021 | Partial Approval | RAFAEL ESPINOZA |
| Reinforced Concrete Frame | 2/5/2021 | Partial Approval | RAFAEL ESPINOZA |
| Final | 2/26/2021 | Permit Finaled | JAMES POWERS |