3949 N GLENALBYN DR 90065
Certificate Information: 3949 N GLENALBYN DR 90065
- Application / Permit
- 16020-10000-04076
- Plan Check / Job No.
- B16LA20698
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- Site retaining wall 12' max height, 83.5' total length at rear of lot
- Permit Issued
- Issued on 4/3/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/5/2023
Permit Application Status History
| Submitted | 12/29/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2017 | VU NGUYEN |
| Corrections Issued | 3/9/2017 | KRIKOR MANOUKIAN |
| Quality Review Completed | 3/17/2017 | BINH PHAN |
| Building Plans Picked Up | 4/12/2017 | APPLICANT |
| Green Plans Picked Up | 4/12/2017 | APPLICANT |
| Applicant returned to address corrections | 6/28/2018 | KRIKOR MANOUKIAN |
| Plan Check Approved | 3/22/2019 | VU NGUYEN |
| Issued | 4/3/2020 | LADBS |
| Permit Finaled | 6/5/2023 | ROBERT HUGHES |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 6/14/2018 | BRIAN CARR |
| Specific Plan | Cleared | 6/14/2018 | BRIAN CARR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tan, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 1/8/2021 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 1/13/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Piling/Pier/Caisson | 1/13/2021 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Piling/Pier/Caisson | 2/9/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 2/10/2021 | Approved | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 2/10/2021 | Partial Approval | ROBERT HUGHES |
| Piling/Pier/Caisson | 2/10/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 2/22/2021 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 3/5/2021 | Corrections Issued | ALEXANDER HELFER |
| Piling/Pier/Caisson | 3/5/2021 | Partial Inspection | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 3/18/2021 | Partial Approval | ROBERT HUGHES |
| Piling/Pier/Caisson | 3/18/2021 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 5/3/2021 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 2/18/2022 | Partial Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Partial Approval | ROBERT HUGHES |
| Final | 6/5/2023 | Permit Finaled | ROBERT HUGHES |