445 N SURFVIEW DR 90272
Certificate Information: 445 N SURFVIEW DR 90272
- Application / Permit
- 16016-20000-00817
- Plan Check / Job No.
- B16VN00467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove existing roof, reframe with steel framing, add ordinary steel moment frame at garage entrance and extend eaves projection of 12' x 15' at rear. Reconfigure interior with new bedroom, bathrooms and structurally reinforce some walls per plan.
- Permit Issued
- Issued on 10/14/2016
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2016 | ALDOUS CHIC |
| Corrections Issued | 1/25/2016 | ALDOUS CHIC |
| Quality Review Completed | 1/26/2016 | STEVEN KIM |
| Building Plans Picked Up | 1/27/2016 | APPLICANT |
| Applicant returned to address corrections | 4/19/2016 | ALDOUS CHIC |
| Plan Check Approved | 5/5/2016 | ALDOUS CHIC |
| Issued | 10/14/2016 | LADBS |
| Permit Finaled | 8/17/2024 | RICHARD STEINBACH |
| CofO Issued | 8/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/28/2015 | ALDOUS CHIC |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2016 | RICHARD SOUTHERLAND |
| Roof/Waste drainage to street | Cleared | 1/28/2016 | RICHARD SOUTHERLAND |
| Coastal Zone | Cleared | 2/4/2016 | MAIDEL LUEVANO |
Contact Information
| Architect | Kerr, Robert E; Lic. No.: C28038 | 2551 S BUNDY DRIVE LOS ANGELES, CA 90064 |
| Contractor | Tso Construction Inc; Lic. No.: 911570-B | P O BOX 6883 MALIBU, CA 90264 |
| Engineer | Barr, Joseph Daniel Iii; Lic. No.: C70708 | 1910 20TH AVE DRIVE NE #109 HICKORY, NC 28601 |
| Engineer | Vidal, Juan Alonso; Lic. No.: GE861 | 15331 DOGWOOD ST WESTMINSTER, CA 92683 |
| Geologist | Miller, Jonathan Steven; Lic. No.: EG2391 | 2800 NEILSON WAY #210 SANTA MONICA, CA 90405 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2018 | Approved | JOHN LUMB |
| Pre-Inspection | 9/27/2018 | Partial Inspection | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 10/15/2018 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/15/2018 | Partial Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 10/16/2018 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 10/23/2018 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/23/2018 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 10/23/2018 | Partial Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 10/26/2018 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 11/26/2018 | Conditional Approval | ANDREW NAVE |
| Underground Mechanical | 11/26/2018 | Conditional Approval | ANDREW NAVE |
| Gas Test | 11/27/2018 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/10/2018 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/10/2018 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 12/14/2018 | Not Ready for Inspection | ANDREW NAVE |
| Pre-Inspection | 12/14/2018 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 12/18/2018 | Partial Inspection | ANDREW NAVE |
| Deputy Steel/Welding | 1/25/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 1/28/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 1/30/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 2/6/2019 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 2/13/2019 | Not Ready for Inspection | ANDREW NAVE |
| Structural Steel Frame | 2/13/2019 | Partial Inspection | ANDREW NAVE |
| Deputy Steel/Welding | 2/27/2019 | Conditional Approval | ANDREW NAVE |
| Pre-Inspection | 3/4/2019 | Approved | ANDREW NAVE |
| Deputy Steel/Welding | 4/15/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 4/19/2019 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2019 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/3/2019 | Conditional Approval | ANDREW NAVE |
| Structural Steel Frame | 6/17/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2019 | Approved | ANDREW NAVE |
| Green Building Rough | 8/29/2019 | Not Ready for Inspection | ANDREW NAVE |
| Wood Frame | 8/29/2019 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 10/16/2019 | Corrections Issued | ANDREW NAVE |
| Underground Mechanical | 10/16/2019 | Partial Inspection | ANDREW NAVE |
| Sewer | 12/16/2019 | Approved | ANDREW NAVE |
| Sewer | 1/8/2020 | Approved | ANDREW NAVE |
| HVAC-Rough | 1/27/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 1/30/2020 | Partial Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 2/11/2020 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 3/2/2020 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 5/4/2020 | Partial Inspection | ANDREW NAVE |
| Green Building Rough | 5/4/2020 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/18/2020 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 5/18/2020 | Conditional Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 6/3/2020 | Partial Approval | ANDREW NAVE |
| Insulation | 6/9/2020 | Partial Approval | ANDREW NAVE |
| Insulation | 6/15/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 7/9/2020 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 7/9/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/9/2020 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 7/15/2020 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 8/10/2020 | Partial Approval | ROBERT SHELLY |
| Interior/Exterior Lathing | 8/10/2020 | Partial Approval | ROBERT SHELLY |
| Interior/Exterior Lathing | 9/15/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 10/15/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 10/15/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 10/28/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 12/24/2020 | Partial Approval | EVAN COOPER |
| Special/Order Compliance | 12/24/2020 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 1/15/2021 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 1/15/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 2/11/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/5/2021 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 8/5/2021 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 8/5/2021 | Approved | ANDREW NAVE |
| Shower Pan | 8/5/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/18/2021 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Not Ready for Inspection | ANDREW NAVE |
| Grounding or Bonding | 8/18/2021 | Not Ready for Inspection | ANDREW NAVE |
| Masonry Wall/Backfill | 9/21/2021 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 10/25/2021 | Partial Approval | ANDREW NAVE |
| Service/Power Release | 1/13/2022 | Corrections Issued | ANDREW NAVE |
| Service/Power Release | 1/19/2022 | Approved | ANDREW NAVE |
| Gas Test | 6/22/2022 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 6/22/2022 | Corrections Issued | ANDREW NAVE |
| Gas Test | 6/30/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 6/30/2022 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 7/8/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 7/26/2022 | Approved | ANDREW NAVE |
| HVAC-Final | 8/3/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 9/20/2022 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/17/2022 | Approved | BRENDAN LOONEY |
| Final | 11/17/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/17/2022 | Approved | BRENDAN LOONEY |
| Green Building Final | 11/17/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 11/17/2022 | Approved | BRENDAN LOONEY |
| Structural Steel Frame | 11/17/2022 | Approved | BRENDAN LOONEY |
| Final | 11/29/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 12/22/2022 | Conditional Approval | BRENDAN LOONEY |