2042 E SACRAMENTO ST 90021
Certificate Information: 2042 E SACRAMENTO ST 90021
- Application / Permit
- 16016-10003-25667
- Plan Check / Job No.
- B23LA16505
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Nursery plant
- Work Description
- SUPPLEMENTAL PERMIT TO 16016-10000-25667 TO REPAIR EXISTING 1ST FLOOR INDOOR NURSERY DUE TO FIRE DAMAGE.
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Metro
- Current Status
- Issued on 4/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | ARMEN JIVALAGIAN |
| Corrections Issued | 9/12/2023 | ARMEN JIVALAGIAN |
| Quality Review Completed | 9/14/2023 | PETER KIM |
| Building Plans Picked Up | 10/5/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 10/31/2023 | APPLICANT |
| Applicant returned to address corrections | 11/8/2023 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 11/22/2023 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 11/22/2023 | APPLICANT |
| Applicant returned to address corrections | 2/13/2024 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/22/2024 | ARMEN JIVALAGIAN |
| Plan Check Approved | 4/2/2024 | ARMEN JIVALAGIAN |
| Issued | 4/2/2024 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 11/29/2023 | YINGSHI HUANG |
| Historic Resource Verification | Cleared | 12/21/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 1/17/2024 | ELIZABETH GALLARDO |
| DAS Clearance | Cleared | 2/1/2024 | ARMEN JIVALAGIAN |
| Green Code | Cleared | 2/2/2024 | ARMEN JIVALAGIAN |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Fico Construction; Lic. No.: 757096-B | 2330 WESTWOOD BLVD SUITE #102 LOS ANGELES, CA 90064 |
| Engineer | Soleymani,, Habib; Lic. No.: S2575 | 1917 PARNELL AVE LOS ANGELES, CA 90025 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2024 | Approved | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 7/23/2024 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | RONALD JIMENEZ |
| Insulation | 8/7/2024 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 8/7/2024 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 8/7/2024 | Corrections Issued | RONALD JIMENEZ |
| Drywall Nailing | 8/23/2024 | Partial Approval | RONALD JIMENEZ |