1025 N HIGHLAND AVE 90038
Certificate Information: 1025 N HIGHLAND AVE 90038
- Application / Permit
- 16016-10003-09780
- Plan Check / Job No.
- B19LA07237
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Supplemental to 16016-10000-09780 provide 2 hr rated mech room for equip on the 4th flr. provide 2 hr horz shaft for hvac equip between the (2) mech rooms, No work on 14th floor.
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/9/2023
Permit Application Status History
| Submitted | 4/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | TSE MING HUANG |
| Disabled Access Plans Picked Up | 5/3/2019 | APPLICANT |
| Corrections Issued | 5/8/2019 | TSE MING HUANG |
| Quality Review Completed | 5/9/2019 | TIEN JEN WANG |
| Green Plans Picked Up | 7/31/2020 | APPLICANT |
| Building Plans Picked Up | 12/23/2020 | APPLICANT |
| Plan Check Approved | 3/4/2021 | TSE MING HUANG |
| Issued | 3/10/2021 | APPLICANT |
| Permit Finaled | 6/8/2023 | JEROME BLACKWOOD |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/4/2020 | SHINE LIN |
| Green Code | Cleared | 12/3/2020 | NEGAR NEJAD |
| HPOZ | Cleared | 12/17/2020 | LAMBERT GIESSINGER |
| Fire Marshall Fire Life Safety | Cleared | 1/20/2021 | ANDREW KO |
Contact Information
| Contractor | Oltmans Construction Co; Lic. No.: 86393-B | 10005 MISSION MILL RD WHITTIER, CA 90601 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 3/24/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 12/14/2021 | Partial Approval | JONATHAN QUACH |
| Final | 3/8/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 3/8/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Smoke Detectors | 3/8/2023 | Approved | JEROME BLACKWOOD |
| Final | 4/13/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 4/13/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 4/17/2023 | Partial Inspection | JEROME BLACKWOOD |
| Green Building Final | 4/17/2023 | Partial Inspection | JEROME BLACKWOOD |
| Special/Order Compliance | 4/17/2023 | Approved | DAVID BURKHEAD |
| Final | 6/8/2023 | Permit Finaled | JEROME BLACKWOOD |
| Green Building Final | 6/8/2023 | Approved | JEROME BLACKWOOD |