827 S 3RD AVE 90005
Certificate Information: 827 S 3RD AVE 90005
- Application / Permit
- 16016-10001-21988
- Plan Check / Job No.
- B18LA12175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO 16016-20000-21988 TO REVISE PLAN TO INCLUDE ADDITION AND REMODELING AND CONVERT ATTIC TO STORY PER REVISED DIR-2017-5334-COA
- Permit Issued
- Issued on 9/5/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2018 | APPLICANT |
| Green Plans Picked Up | 6/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | SAM CHANG |
| Corrections Issued | 7/17/2018 | SAM CHANG |
| Quality Review Completed | 7/19/2018 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 7/20/2018 | APPLICANT |
| Plan Check Approved | 9/5/2018 | SAM CHANG |
| Issued | 9/5/2018 | LADBS |
| CofO in Progress | 11/4/2024 | ENRIQUE MIRELES |
| No Progress | 11/10/2024 | DEROLD HAUFF |
| CofO in Progress | 11/10/2024 | DEROLD HAUFF |
| No Progress | 12/5/2024 | DEROLD HAUFF |
| CofO in Progress | 12/5/2024 | DEROLD HAUFF |
| Permit Finaled | 12/19/2024 | DEROLD HAUFF |
| CofO Issued | 12/19/2024 | DEROLD HAUFF |
| Permit Finaled | 12/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 8/31/2018 | BRADLEY FURUYA |
| CPC | Cleared | 8/31/2018 | BRADLEY FURUYA |
| CPC | Cleared | 8/31/2018 | BRADLEY FURUYA |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 8/31/2018 | COLIN LOREDO |
| HPOZ | Cleared | 8/31/2018 | BRADLEY FURUYA |
| Low Impact Development | Cleared | 8/31/2018 | MITESH PATEL |
| Miscellaneous | Cleared | 8/31/2018 | BRADLEY FURUYA |
| Roof/Waste drainage to street | Cleared | 8/31/2018 | NAZILA NOORIFAR |
| ZI | Cleared | 8/31/2018 | BRADLEY FURUYA |
Contact Information
| Contractor | Espana Builders; Lic. No.: 1002026-B | 23137 BALTAR STREET WEST HILLS, CA 91304 |
| Engineer | Roberts, Jeffrey Allan; Lic. No.: C56881 | 9925 COMMERCE AVENUE SUITE B TUJUNGA, CA 91042 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/14/2018 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/14/2018 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/24/2018 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2019 | Partial Approval | DANIEL GONZALEZ |
| HVAC-Rough | 1/10/2019 | Corrections Issued | DANIEL GONZALEZ |
| PLUMBING-Rough | 1/10/2019 | Approved | DANIEL GONZALEZ |
| HVAC-Rough | 2/6/2019 | Partial Approval | LUIS BARRALES |
| Deputy Wood Construction | 3/1/2019 | Approved | LUIS BARRALES |
| ELECTRICAL-Rough | 3/26/2019 | Approved | LUIS BARRALES |
| BUILDING-Rough-Frame | 4/24/2019 | Approved | LUIS BARRALES |
| Green Building Rough | 4/24/2019 | Approved | LUIS BARRALES |
| Insulation | 5/3/2019 | Corrections Issued | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 5/3/2019 | Partial Approval | DANIEL GONZALEZ |
| Insulation | 6/3/2019 | Approved | LUIS BARRALES |
| Drywall Nailing | 6/18/2019 | Approved | LUIS BARRALES |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2019 | Not Ready for Inspection | LUIS BARRALES |
| Interior/Exterior Lathing | 9/6/2019 | Not Ready for Inspection | LUIS BARRALES |
| Interior/Exterior Lathing | 10/11/2019 | Not Ready for Inspection | LUIS BARRALES |
| Service/Power Release | 10/11/2019 | Not Ready for Inspection | LUIS BARRALES |
| Service/Power Release | 3/2/2020 | Not Ready for Inspection | MICHAEL FAUNCE |
| ELECTRICAL-Final | 6/19/2020 | Approved | ARTHUR SARGSYAN |
| Gas Test | 8/31/2020 | Approved | ARTHUR SARGSYAN |
| Service/Power Release | 9/25/2020 | Not Required | JOSEPH MCGARRY |
| ELECTRICAL-Final | 1/19/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 1/19/2021 | Approved | JOSEPH MCGARRY |
| Final | 5/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 10/18/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 10/18/2024 | Approved | JEFFREY MEAD |
| Final | 10/29/2024 | OK to Issue CofO | ENRIQUE MIRELES |
| Special/Order Compliance | 11/19/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 12/4/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Special/Order Compliance | 12/14/2024 | Corrections Issued | JOAQUIN GREENOUGH |