6414 S MCKINLEY AVE 90001

Certificate Information: 6414 S MCKINLEY AVE 90001

Application / Permit
16016-10000-30189
Plan Check / Job No.
B16LA19929
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Alcohol Manufacturing
Work Description
CHANGE OF USE FROM MANUFACTURING TO DISTILLERY/STORAGE TO (e) 1-STORY URM BLDG. NO DEMOLITION. FULL COMPLIANCE WITH APPENDIX-CHAPTER A1 FOR BUILDING-#5.
Permit Issued
Issued on 11/8/2017
Issuing Office
Metro
Current Status
CofO Issued on 2/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2016 APPLICANT
Green Plans Picked Up 2/2/2017 APPLICANT
Disabled Access Plans Picked Up 2/3/2017 APPLICANT
Assigned to Plan Check Engineer 2/16/2017 YOUNG KIM
Corrections Issued 3/10/2017 YOUNG KIM
Quality Review Completed 3/23/2017 MINYE PAK
Building Plans Picked Up 3/29/2017 APPLICANT
Applicant returned to address corrections 7/12/2017 YOUNG KIM
Applicant returned to address corrections 8/17/2017 YOUNG KIM
Plan Check Approved 8/31/2017 YOUNG KIM
Issued 11/8/2017 LADBS
CofO in Progress 12/14/2021 KATY RAMIREZ
Permit Finaled 2/4/2022 TERRY HERR
CofO Issued 2/4/2022 TERRY HERR
Permit Finaled 2/4/2022 TERRY HERR

Permit Application Clearance Information

Sewer availability Cleared 7/5/2017 ADRIAN SANCHEZ
Specific Plan Cleared 7/5/2017 BRIAN CARR
Food Service Establishment Cleared 7/11/2017 KENNETH BROWNE
DAS Clearance Cleared 7/12/2017 WAI LAU
Eng Process Fee Ord 176,300 Cleared 7/12/2017 CELINA MORENO
Green Code Cleared 8/14/2017 MICKEY YAMASHITA
Food establishment approval Cleared 8/31/2017 LACDHS APPROVED

Contact Information

Contractor Huizar & Associates; Lic. No.: 404002-B 16110 S MENLO #11      GARDENA, CA 90247
Engineer Chan, Manuel; Lic. No.: S5682 885 CINNAMON LANE      DUARTE, CA 91010

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/15/2018 Approved JOEY BUCHANAN
Footing/Foundation/Slab 3/19/2018 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 6/18/2018 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 6/18/2018 Corrections Issued JOEY BUCHANAN
Deputy Drilled-In Anchors 8/16/2018 Approved JOEY BUCHANAN
Drywall Nailing 12/5/2018 Approved JOEY BUCHANAN
Final 12/5/2018 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 12/5/2018 Not Ready for Inspection JOEY BUCHANAN
Green Building Rough 12/5/2018 Approved JOEY BUCHANAN
Reinforced Masonry Frame 12/5/2018 No Access for Inspection JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 12/5/2018 SGSOV Not Ready JOEY BUCHANAN
Smoke Detectors 12/5/2018 Approved JOEY BUCHANAN
Wood Frame 12/6/2018 Corrections Issued JOEY BUCHANAN
Wood Frame 5/20/2019 Not Ready for Inspection JOEY BUCHANAN
Interior/Exterior Lathing 8/28/2019 Corrections Issued JOEY BUCHANAN
Interior/Exterior Lathing 9/3/2019 Partial Inspection RAFAEL ESPINOZA
Green Building Final 11/4/2021 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 11/4/2021 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Not Ready KATY RAMIREZ
Pre-Inspection 11/5/2021 Approved KATY RAMIREZ
Final 11/12/2021 Partial Inspection KATY RAMIREZ
Green Building Final 11/12/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 11/12/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/12/2021 SGSOV No Gas KATY RAMIREZ
Final 11/24/2021 Partial Inspection KATY RAMIREZ
Final 12/14/2021 OK to Issue CofO KATY RAMIREZ