457-465 W 7TH ST 90731
Certificate Information: 457-465 W 7TH ST 90731
- Application / Permit
- 16016-10000-25950
- Plan Check / Job No.
- B16LA16832
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TI TO (E) TWO STORY RESTAURANT. CHANGE OF USE OF (E) TELEPHONE CENTER INTO RESTAURANT. MAKE TWO OPENING IN EXTERIOR WALLS TO COMBINE THE TWO BUILDINGS INTO ONE RESTAURANT AND BANQUET HALL USE. SEE COMMENTS.
- Permit Issued
- Issued on 6/11/2018
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 8/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2016 | MOHAMMAD FIROUZBAKHT |
| Corrections Issued | 11/7/2016 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 11/15/2016 | BILL STUTSMAN |
| Green Plans Picked Up | 1/3/2017 | APPLICANT |
| Plan Check Approved | 6/7/2018 | MOHAMMAD FIROUZBAKHT |
| Issued | 6/11/2018 | LADBS |
| CofO in Progress | 8/24/2021 | JOEY BUCHANAN |
| CofO Issued | 8/24/2021 | NICK LAROCCA |
| Permit Finaled | 8/24/2021 | NICK LAROCCA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2016 | PHILLIP WILSON |
| Highway dedication | Cleared | 12/6/2016 | PHILLIP WILSON |
| Sewer availability | Cleared | 12/6/2016 | PHILLIP WILSON |
| DAS Clearance | Cleared | 2/7/2017 | MOHAMMAD FIROUZBAKHT |
| Project located in CRA area | Cleared | 5/10/2017 | CRAIG BULLOCK |
| Fire Marshall Fire Life Safety | Cleared | 1/5/2018 | DAVE MYERS |
| Food Service Establishment | Cleared | 3/29/2018 | KENNETH BROWNE |
| Green Code | Cleared | 4/18/2018 | NEGAR NEJAD |
| Food establishment approval | Cleared | 5/11/2018 | LACDHS APPROVED |
| Supp. Use District POD/CDO/TDO | Cleared | 5/29/2018 | EDBER MACEDO |
| ZI | Cleared | 5/29/2018 | EDBER MACEDO |
Contact Information
| Architect | , ; Lic. No.: C34782 | 1570 WEST 9TH STREET SAN PEDRO, CA 90732 |
| Contractor | M A F Construction Inc; Lic. No.: 540983-B | 1000 N WESTERN AVENUE STE 201 SAN PEDRO, CA 90732 |
| Engineer | Galbreath, Sean Martin; Lic. No.: S5653 | 1443 E WASHINGTON BLVD 132 PASADENA, CA 91104 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 4/18/2019 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 4/19/2019 | Partial Approval | NICK LAROCCA |
| Deputy Drilled-In Anchors | 5/2/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 5/2/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/7/2019 | Approved | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 5/15/2019 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 5/20/2019 | Partial Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/3/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 7/11/2019 | Approved | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 8/30/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 9/9/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/16/2019 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/17/2019 | Partial Approval | NICK LAROCCA |
| Wood Frame | 9/27/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 10/1/2019 | Approved | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/16/2019 | Approved | RAFAEL ESPINOZA |
| Insulation | 10/28/2019 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 11/7/2019 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 11/8/2019 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 11/8/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/4/2019 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 12/4/2019 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 3/5/2020 | Approved | JOEY BUCHANAN |
| Final | 4/15/2021 | Corrections Issued | JOEY BUCHANAN |
| Green Building Final | 4/15/2021 | Approved | JOEY BUCHANAN |
| Green Building Rough | 4/15/2021 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 4/15/2021 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2021 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 4/15/2021 | Approved | JOEY BUCHANAN |
| Final | 6/28/2021 | Conditional Approval | JOEY BUCHANAN |