1111 S BROADWAY 90015

Certificate Information: 1111 S BROADWAY 90015

Application / Permit
16016-10000-19257
Plan Check / Job No.
B16LA12506
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Rehabilitation of Historic 5- Story Herald Examiner building. Shell and core construction only. Change of use for partial ground and second floor from printing shop/office to restaurants. All other floors to remain office use. Structural upgrade to the building to comply with city non-ductile ordinance.
Permit Issued
Issued on 12/12/2017
Issuing Office
Metro
Current Status
CofO Issued on 11/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2016 APPLICANT
Assigned to Plan Check Engineer 9/29/2016 LARRY LEE
Corrections Issued 10/25/2016 LARRY LEE
Quality Review Completed 10/25/2016 PETER KIM
Building Plans Picked Up 10/28/2016 APPLICANT
Applicant returned to address corrections 11/4/2016 LARRY LEE
Applicant returned to address corrections 3/6/2017 LARRY LEE
Applicant returned to address corrections 10/31/2017 LARRY LEE
Plan Check Approved 11/13/2017 LARRY LEE
No Progress 11/13/2017 LARRY LEE
Plan Check Approved 11/13/2017 LARRY LEE
Issued 12/12/2017 LADBS
TCO Issued (Expire Date: 05-23-2021) 11/24/2020 ERNESTO CORRAL
TCO Issued (Expire Date: 11-15-2021) 5/19/2021 DAVID TSAU
CofO in Progress 11/12/2021 ERNESTO CORRAL
Permit Finaled 11/12/2021 ERNESTO CORRAL
CofO Issued 11/12/2021 ERNESTO CORRAL
Permit Finaled 11/12/2021 ERNESTO CORRAL

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 10/12/2017 LAMBERT GIESSINGER
Historic monument Cleared 10/12/2017 LAMBERT GIESSINGER
Historical monument Cleared 10/17/2017 JIM URQUHART
Project located in CRA area Cleared 10/17/2017 JIM URQUHART
Food Service Establishment Cleared 10/24/2017 SAM NAVID
Low Impact Development Cleared 10/26/2017 IDA MEISAMI-FARD
Fire Marshall Fire Life Safety Cleared 11/7/2017 MENOA AGHAJANI
DAS Clearance Cleared 11/8/2017 LARRY LEE
Green Code Cleared 11/8/2017 SEAN DANG
CPC Cleared 11/13/2017 MARITZA PRZEKOP
ZA Case Cleared 11/13/2017 MARITZA PRZEKOP
ZA Case Cleared 11/13/2017 MARITZA PRZEKOP

Contact Information

Architect Sommerhalder, Olivier R; Lic. No.: C32170 844 GRANT #C      SANTA MONICA, CA 90405
Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670
Engineer Davis, Richard Hays; Lic. No.: C48082 2015 CANTATA DR      LOS ANGELES, CA 90068
Engineer Wilkerson, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/27/2019 Partial Inspection NICK DANERI
Reinforced Concrete Frame 3/27/2019 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/18/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/23/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 4/26/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/14/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/16/2019 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 5/16/2019 Partial Approval KATY RAMIREZ
METHANE-Barrier 5/16/2019 Partial Inspection KATY RAMIREZ
METHANE-Subgrade 5/16/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 5/17/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/22/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/29/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/29/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 5/31/2019 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 5/31/2019 Partial Approval DANIEL COLLINS
METHANE-Barrier 5/31/2019 Conditional Approval DANIEL COLLINS
METHANE-Subgrade 5/31/2019 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 6/12/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2019 Conditional Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 6/20/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/25/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/26/2019 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 6/26/2019 Partial Approval JAMES POWERS
METHANE-Barrier 6/26/2019 Not Ready for Inspection KATY RAMIREZ
METHANE-Subgrade 6/26/2019 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 6/27/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/28/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 7/1/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 7/22/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/22/2019 Partial Approval JAMES POWERS
METHANE-Barrier 7/22/2019 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 7/22/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/23/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/29/2019 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 8/1/2019 Partial Approval JAMES POWERS
Deputy Shotcrete 8/1/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/1/2019 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 8/2/2019 Conditional Approval DAVID TSAU
Reinforced Concrete Frame 8/2/2019 Partial Approval HAMID PISHEHVAR
Deputy Shotcrete 8/27/2019 Approved JOEY BUCHANAN
Reinforced Concrete Frame 8/27/2019 Not Ready for Inspection JOEY BUCHANAN
Deputy Shotcrete 8/28/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/28/2019 Off-Hour Fees Due
Reinforced Concrete Frame 8/28/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2019 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 8/29/2019 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 8/30/2019 Conditional Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 8/30/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Shotcrete 9/3/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 9/3/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/4/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/20/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/20/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/23/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/23/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/24/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/24/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/25/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/25/2019 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 9/25/2019 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 9/25/2019 Partial Approval KATY RAMIREZ
METHANE-Barrier 9/25/2019 Not Ready for Inspection KATY RAMIREZ
METHANE-Subgrade 9/25/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 9/26/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/26/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 9/27/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/30/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 9/30/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/30/2019 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 10/3/2019 Not Ready for Inspection KATY RAMIREZ
METHANE-Barrier 10/3/2019 Not Ready for Inspection KATY RAMIREZ
METHANE-Subgrade 10/3/2019 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 10/4/2019 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 10/7/2019 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 10/9/2019 Partial Approval JAMES POWERS
METHANE-Barrier 10/9/2019 Partial Approval JONATHAN QUACH
METHANE-Subgrade 10/9/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/11/2019 Partial Approval JAMES POWERS
METHANE-Subgrade 10/11/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 10/18/2019 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 10/18/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 10/18/2019 Partial Inspection KATY RAMIREZ
Deputy Shotcrete 10/22/2019 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 10/22/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 10/22/2019 Not Ready for Inspection KATY RAMIREZ
Structural Steel Frame 10/22/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/23/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 10/23/2019 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/30/2019 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 10/30/2019 Partial Inspection KATY RAMIREZ
Structural Steel Frame 10/30/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/31/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/7/2019 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 11/7/2019 Partial Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/8/2019 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 11/8/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/13/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/13/2019 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 11/15/2019 Partial Approval KATY RAMIREZ
METHANE-Barrier 11/15/2019 Not Ready for Inspection KATY RAMIREZ
METHANE-Subgrade 11/15/2019 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/19/2019 Conditional Approval RONALD PACHECO
Deputy Shotcrete 11/19/2019 Conditional Approval RONALD PACHECO
Deputy Steel/Welding 11/19/2019 Conditional Approval RONALD PACHECO
Reinforced Concrete Frame 11/19/2019 Partial Approval RONALD PACHECO
Reinforced Concrete Frame 11/21/2019 Not Ready for Inspection KATY RAMIREZ
Structural Steel Frame 11/21/2019 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/22/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 11/22/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/26/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Masonry 11/26/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 11/26/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 11/26/2019 Conditional Approval KATY RAMIREZ
Masonry Wall/Backfill 11/26/2019 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 11/26/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/27/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/27/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Masonry 11/27/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 11/27/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 11/27/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/4/2019 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 12/4/2019 No Access for Inspection KATY RAMIREZ
Reinforced Concrete Frame 12/5/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/6/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 12/9/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/12/2019 Conditional Approval DANIEL COLLINS
Masonry Wall/Backfill 12/12/2019 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 12/12/2019 Partial Approval KATY RAMIREZ
Masonry Wall/Backfill 12/16/2019 Partial Approval RONALD PACHECO
Deputy Shotcrete 12/20/2019 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 12/20/2019 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 1/7/2020 Partial Approval KATY RAMIREZ
METHANE-Barrier 1/7/2020 Not Ready for Inspection KATY RAMIREZ
METHANE-Subgrade 1/7/2020 Partial Inspection KATY RAMIREZ
Reinforced Concrete Frame 1/15/2020 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 1/16/2020 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 1/22/2020 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 1/22/2020 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 1/29/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 2/5/2020 Partial Inspection KATY RAMIREZ
Reinforced Concrete Frame 2/5/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/12/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 2/20/2020 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 2/20/2020 Partial Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 2/21/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/21/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/21/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 2/24/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/24/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/24/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 2/25/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/25/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/25/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 2/26/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/26/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/26/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 2/27/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/27/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/27/2020 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 2/27/2020 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 2/27/2020 Not Ready for Inspection KATY RAMIREZ
Deputy Methane Barrier 2/28/2020 Conditional Approval KATY RAMIREZ
Deputy Other (see comments) 2/28/2020 Conditional Approval KATY RAMIREZ
Deputy Methane Barrier 3/2/2020 Conditional Approval JONATHAN QUACH
Deputy Other (see comments) 3/2/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 3/3/2020 Conditional Approval DANIEL COLLINS
Deputy Methane Barrier 3/4/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 3/4/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/4/2020 Partial Approval DANIEL COLLINS
Deputy Methane Barrier 3/5/2020 Conditional Approval DANIEL COLLINS
Deputy Methane Barrier 3/6/2020 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 3/6/2020 Partial Approval DANIEL COLLINS
METHANE-Barrier 3/6/2020 Approved DANIEL COLLINS
METHANE-Subgrade 3/6/2020 Approved DANIEL COLLINS
Light Gage Steel Frame 3/16/2020 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 3/31/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/31/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/16/2020 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/20/2020 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 4/20/2020 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 4/20/2020 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/23/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/23/2020 Conditional Approval KATY RAMIREZ
Drywall Nailing 4/23/2020 Partial Approval KATY RAMIREZ
Insulation 4/23/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 4/28/2020 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 5/6/2020 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 5/7/2020 Conditional Approval JONATHAN QUACH
Drywall Nailing 5/7/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 5/7/2020 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 5/14/2020 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 5/22/2020 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 6/4/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 6/11/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 6/17/2020 Partial Approval KATY RAMIREZ
Special/Order Compliance 7/21/2020 Approved KATY RAMIREZ
Final 8/5/2020 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 8/5/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Final 8/5/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Rough 8/5/2020 Approved KATY RAMIREZ
METHANE-Final 8/5/2020 Not Ready for Inspection KATY RAMIREZ
METHANE-Rough 8/5/2020 Approved KATY RAMIREZ
Reinforced Masonry Frame 8/5/2020 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/5/2020 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 8/5/2020 Not Ready for Inspection KATY RAMIREZ
Final 8/21/2020 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 8/21/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Final 8/21/2020 Not Ready for Inspection KATY RAMIREZ
METHANE-Final 8/21/2020 Not Ready for Inspection KATY RAMIREZ
METHANE-Rough 8/21/2020 Approved KATY RAMIREZ
Reinforced Masonry Frame 8/21/2020 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 8/21/2020 Not Ready for Inspection KATY RAMIREZ
Pre-Inspection 9/21/2020 Not Ready for Inspection KATY RAMIREZ
Pre-Inspection 9/22/2020 No Access for Inspection KATY RAMIREZ
Pre-Inspection 9/23/2020 Not Ready for Inspection KATY RAMIREZ
Final 9/25/2020 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 9/25/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Final 9/25/2020 Not Ready for Inspection KATY RAMIREZ
METHANE-Final 9/25/2020 Approved KATY RAMIREZ
METHANE-Rough 9/25/2020 Approved KATY RAMIREZ
Pre-Inspection 9/25/2020 Approved KATY RAMIREZ
Reinforced Masonry Frame 9/25/2020 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 9/25/2020 Not Ready for Inspection KATY RAMIREZ
Pre-Inspection 9/28/2020 Partial Inspection KATY RAMIREZ
Pre-Inspection 9/29/2020 Approved KATY RAMIREZ
Pre-Inspection 10/1/2020 Partial Inspection KATY RAMIREZ
Special/Order Compliance 11/16/2020 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Not Ready RONALD PACHECO
Final 11/24/2020 OK for TCO DANIEL COLLINS
Footing/Foundation/Slab 11/24/2020 Approved DANIEL COLLINS
Green Building Final 11/24/2020 Approved DANIEL COLLINS
Reinforced Masonry Frame 11/24/2020 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved DANIEL COLLINS
Smoke Detectors 11/24/2020 Approved DANIEL COLLINS
Deputy Drilled-In Anchors 12/11/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/23/2020 Conditional Approval KATY RAMIREZ
Special/Order Compliance 4/28/2021 Partial Inspection KATY RAMIREZ
Deputy Steel/Welding 5/10/2021 Conditional Approval KATY RAMIREZ
Deputy Methane Barrier 7/9/2021 Conditional Approval DANIEL COLLINS
Final 9/8/2021 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 10/20/2021 Partial Inspection KATY RAMIREZ
Final 10/28/2021 Not Ready for Inspection KATY RAMIREZ
Final 11/3/2021 Not Ready for Inspection KATY RAMIREZ