3666 W VALLEYBRINK ROAD 90039

Certificate Information: 3666 W VALLEYBRINK ROAD 90039

Application / Permit
16016-10000-15514
Plan Check / Job No.
B16LA10044
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New detached 2 -car garage (20' x 20')and attched recreation room (8'-11" x 19')
Permit Issued
Issued on 11/9/2016
Issuing Office
Metro
Current Status
Issued on 11/9/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/6/2016 APPLICANT
Assigned to Plan Check Engineer 7/6/2016 SALVADOR QUINTANILLA
Corrections Issued 7/6/2016 SALVADOR QUINTANILLA
Applicant returned to address corrections 9/22/2016 JOHNNY WU
Plan Check Approved 9/22/2016 CATHERINE CHEN
Issued 11/9/2016 LADBS

Permit Application Clearance Information

Sewer availability Cleared 7/13/2016 AVALYN KAMACHI
Eng Process Fee Ord 176,300 Cleared 8/11/2016 VALENTINO PUEBLOS
Low Impact Development Cleared 9/15/2016 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/22/2016 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Vega, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2017 Corrections Issued LUIS ALVAREZ
Footing/Foundation/Slab 3/29/2017 Not Ready for Inspection LUIS ALVAREZ
PLUMBING-Rough 3/29/2017 Corrections Issued LUIS ALVAREZ
Pre-Inspection 3/29/2017 Approved DOMINIC DANERI
Sewer 3/29/2017 Approved LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 4/3/2017 Approved LUIS ALVAREZ
Footing/Foundation/Slab 4/6/2017 Approved LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2017 Approved LUIS ALVAREZ
ELECTRICAL-Rough 5/4/2017 Approved LUIS ALVAREZ
HVAC-Rough 5/4/2017 Approved LUIS ALVAREZ
PLUMBING-Rough 5/4/2017 Approved LUIS ALVAREZ
BUILDING-Rough-Frame 5/5/2017 Approved LUIS ALVAREZ
Green Building Rough 5/5/2017 Approved LUIS ALVAREZ
Insulation 5/5/2017 Approved LUIS ALVAREZ
Interior/Exterior Lathing 5/5/2017 Approved LUIS ALVAREZ
Drywall Nailing 5/11/2017 Approved LUIS ALVAREZ
Final 6/26/2017 Partial Approval LUIS ALVAREZ
Green Building Final 6/26/2017 Approved LUIS ALVAREZ
SGSOV-Seismic Gas S/O Valve 6/26/2017 SGSOV Approved LUIS ALVAREZ
Service/Power Release 6/26/2017 Not Ready for Inspection LUIS ALVAREZ
Smoke Detectors 6/26/2017 Approved LUIS ALVAREZ
Final 6/30/2017 Conditional Approval LUIS ALVAREZ
ELECTRICAL-Final 9/27/2017 Approved DOMINIC DANERI
Insulation 9/27/2017 Approved DOMINIC DANERI
PLUMBING-Final 9/27/2017 Approved DOMINIC DANERI
Final 8/14/2023 Partial Inspection HAMIK HARTOUNIAN