1147 S AVERILL AVE 90732
Certificate Information: 1147 S AVERILL AVE 90732
- Application / Permit
- 16014-40000-00035
- Plan Check / Job No.
- B16SP00007
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and interior alteration to existing one story SFD.
- Permit Issued
- Issued on 5/22/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2016 | YAQUB MIRZA |
| Corrections Issued | 2/4/2016 | YAQUB MIRZA |
| Quality Review Completed | 2/11/2016 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/12/2016 | APPLICANT |
| Green Plans Picked Up | 2/12/2016 | APPLICANT |
| Applicant returned to address corrections | 3/20/2017 | YAQUB MIRZA |
| Applicant returned to address corrections | 3/23/2017 | YAQUB MIRZA |
| Plan Check Approved | 5/16/2017 | YAQUB MIRZA |
| Issued | 5/22/2017 | LADBS |
| CofO in Progress | 1/11/2024 | JAMES CHAVEZ |
| CofO Issued | 1/11/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/11/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/30/2017 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/30/2017 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/30/2017 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/30/2017 | SEVAK ISAKHAYAN |
| BHO/Hillside ordinance | Cleared | 3/30/2017 | SEVAK ISAKHAYAN |
| Hydrant and Access approval | Cleared | 3/30/2017 | JOHN CONNEALLY |
| Sewer availability | Cleared | 3/30/2017 | SEVAK ISAKHAYAN |
| Green Code | Cleared | 4/11/2017 | YAQUB MIRZA |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2017 | RAVIL MANAPOV |
| Grading Pre-Inspection | Cleared | 5/16/2017 | YAQUB MIRZA |
| Low Impact Development | Cleared | 5/16/2017 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 5/16/2017 | RAVIL MANAPOV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abarquez, Jose Munoz Iii; Lic. No.: C51994 | 18 EL CORZO RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/22/2020 | Partial Inspection | JOHN KLARIN |
| Deputy Drilled-In Anchors | 11/6/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Drilled-In Anchors | 12/3/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 12/8/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/24/2020 | Partial Approval | JOHN KLARIN |
| Sewer | 12/24/2020 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/12/2021 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 3/12/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/22/2022 | Partial Inspection | ANSON MAGLASANG |
| Green Building Rough | 7/22/2022 | Partial Inspection | ANSON MAGLASANG |
| Deputy Wood Construction | 7/26/2022 | Conditional Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 10/17/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 10/17/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/17/2022 | Approved | JOHN KLARIN |
| Insulation | 10/19/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 10/28/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 10/28/2022 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 12/14/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 2/1/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/17/2023 | Approved | ANSON MAGLASANG |
| Final | 4/17/2023 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 4/17/2023 | Approved | ANSON MAGLASANG |
| Green Building Final | 4/17/2023 | Approved | ANSON MAGLASANG |
| Green Building Rough | 4/17/2023 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 4/17/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 7/25/2023 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 7/25/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 7/26/2023 | Approved | JOHN KLARIN |
| Final | 12/22/2023 | OK to Issue CofO | JAMES CHAVEZ |