549 N MUSKINGUM AVE 90272

Certificate Information: 549 N MUSKINGUM AVE 90272

Application / Permit
16014-30009-03976
Plan Check / Job No.
B18WL07050
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO PCIS # 16014-30000-03976 TO REVISE DESIGN PER CDP, ADD ROOF DECK, 3 RD FLOOR ELEVATOR & INCREASE ADDITION
Permit Issued
Issued on 1/23/2019
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2018 APPLICANT
Green Plans Picked Up 11/16/2018 APPLICANT
Assigned to Plan Check Engineer 11/21/2018 ALFREDO JARA
Corrections Issued 11/28/2018 ALFREDO JARA
Quality Review Completed 12/7/2018 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/15/2019 ALFREDO JARA
Issued 1/23/2019 LADBS
Permit Finaled 3/18/2021 ANDREW NAVE

Permit Application Clearance Information

Green Code Cleared 11/29/2018 DONALD CRICHLOW
BHO/Hillside ordinance Cleared 12/13/2018 TAO YANG
BHO/Hillside ordinance Cleared 12/13/2018 TAO YANG
BHO/Hillside ordinance Cleared 12/13/2018 TAO YANG
Eng Process Fee Ord 176,300 Cleared 12/13/2018 TAO YANG
Permit Cleared 12/13/2018 TAO YANG
Roof/Waste drainage to street Cleared 12/13/2018 TAO YANG
Hydrant and Access approval Cleared 12/28/2018 JOHN CONNEALLY
Low Impact Development Cleared 12/28/2018 MARTIN FRAGOSO
Coastal Zone Cleared 1/2/2019 TREVOR MARTIN
Miscellaneous Cleared 1/2/2019 TREVOR MARTIN
Miscellaneous Cleared 1/2/2019 TREVOR MARTIN
Trees in Parkway Cleared 1/7/2019 JOHN KIM
GPI Written Notices Cleared 1/15/2019 ALFREDO JARA
Grading Pre-Inspection Cleared 1/15/2019 ALFREDO JARA

Contact Information

Architect Gemigniani, Richard Louis; Lic. No.: C18783 11739 CANTON PL      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/5/2019 Not Ready for Inspection RICHARD STEINBACH
Footing/Foundation/Slab 3/14/2019 Partial Approval RICHARD STEINBACH
Masonry Wall/Backfill 4/5/2019 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/22/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 5/22/2019 Partial Approval ANDREW NAVE
Masonry Wall/Backfill 5/31/2019 Partial Approval ANDREW NAVE
Masonry Wall/Backfill 6/10/2019 Corrections Issued ANDREW NAVE
Masonry Wall/Backfill 6/11/2019 Partial Approval ANDREW NAVE
Masonry Wall/Backfill 6/14/2019 Not Ready for Inspection ANDREW NAVE
Masonry Wall/Backfill 6/18/2019 Partial Approval ANDREW NAVE
PLUMBING-Rough 7/15/2019 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Partial Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 10/31/2019 Not Ready for Inspection ANDREW NAVE
Green Building Rough 10/31/2019 Not Ready for Inspection ANDREW NAVE
Wood Frame 10/31/2019 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 11/18/2019 Corrections Issued ANDREW NAVE
HVAC-Rough 12/16/2019 Corrections Issued ANDREW NAVE
HVAC-Rough 1/14/2020 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 1/15/2020 Approved ANDREW NAVE
PLUMBING-Rough 1/15/2020 Approved ANDREW NAVE
ELECTRICAL-Rough 1/16/2020 Approved ANDREW NAVE
Wood Frame 1/17/2020 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 1/31/2020 Partial Approval ANDREW NAVE
Green Building Rough 1/31/2020 Approved ANDREW NAVE
BUILDING-Rough-Frame 2/13/2020 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 2/24/2020 Approved ANDREW NAVE
Green Building Rough 2/24/2020 Approved ANDREW NAVE
Insulation 2/24/2020 Approved ANDREW NAVE
BUILDING-Rough-Frame 3/4/2020 Approved ANDREW NAVE
Drywall Nailing 3/4/2020 Approved ANDREW NAVE
Sewer 3/9/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 3/20/2020 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 4/17/2020 Approved ANDREW NAVE
Underground Mechanical 10/6/2020 Approved ANDREW NAVE
Final 2/25/2021 Not Ready for Inspection ANDREW NAVE
Footing/Foundation/Slab 2/25/2021 Approved ANDREW NAVE
Green Building Final 2/25/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Final 2/25/2021 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 2/25/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Final 2/26/2021 Corrections Issued ANDREW NAVE
Gas Test 3/2/2021 Approved ANDREW NAVE
HVAC-Final 3/2/2021 Approved ANDREW NAVE
PLUMBING-Final 3/2/2021 Approved ANDREW NAVE
Special/Order Compliance 3/2/2021 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 3/3/2021 Corrections Issued ANDREW NAVE
Service/Power Release 3/3/2021 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 3/8/2021 Approved ANDREW NAVE
Green Building Final 3/8/2021 Approved ANDREW NAVE
Final 3/18/2021 Permit Finaled ANDREW NAVE
Smoke Detectors 3/18/2021 Approved ANDREW NAVE