549 N MUSKINGUM AVE 90272
Certificate Information: 549 N MUSKINGUM AVE 90272
- Application / Permit
- 16014-30009-03976
- Plan Check / Job No.
- B18WL07050
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO PCIS # 16014-30000-03976 TO REVISE DESIGN PER CDP, ADD ROOF DECK, 3 RD FLOOR ELEVATOR & INCREASE ADDITION
- Permit Issued
- Issued on 1/23/2019
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 3/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2018 | APPLICANT |
| Green Plans Picked Up | 11/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2018 | ALFREDO JARA |
| Corrections Issued | 11/28/2018 | ALFREDO JARA |
| Quality Review Completed | 12/7/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/15/2019 | ALFREDO JARA |
| Issued | 1/23/2019 | LADBS |
| Permit Finaled | 3/18/2021 | ANDREW NAVE |
Permit Application Clearance Information
| Green Code | Cleared | 11/29/2018 | DONALD CRICHLOW |
| BHO/Hillside ordinance | Cleared | 12/13/2018 | TAO YANG |
| BHO/Hillside ordinance | Cleared | 12/13/2018 | TAO YANG |
| BHO/Hillside ordinance | Cleared | 12/13/2018 | TAO YANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2018 | TAO YANG |
| Permit | Cleared | 12/13/2018 | TAO YANG |
| Roof/Waste drainage to street | Cleared | 12/13/2018 | TAO YANG |
| Hydrant and Access approval | Cleared | 12/28/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/28/2018 | MARTIN FRAGOSO |
| Coastal Zone | Cleared | 1/2/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 1/2/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 1/2/2019 | TREVOR MARTIN |
| Trees in Parkway | Cleared | 1/7/2019 | JOHN KIM |
| GPI Written Notices | Cleared | 1/15/2019 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 1/15/2019 | ALFREDO JARA |
Contact Information
| Architect | Gemigniani, Richard Louis; Lic. No.: C18783 | 11739 CANTON PL STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/5/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 3/14/2019 | Partial Approval | RICHARD STEINBACH |
| Masonry Wall/Backfill | 4/5/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/22/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/22/2019 | Partial Approval | ANDREW NAVE |
| Masonry Wall/Backfill | 5/31/2019 | Partial Approval | ANDREW NAVE |
| Masonry Wall/Backfill | 6/10/2019 | Corrections Issued | ANDREW NAVE |
| Masonry Wall/Backfill | 6/11/2019 | Partial Approval | ANDREW NAVE |
| Masonry Wall/Backfill | 6/14/2019 | Not Ready for Inspection | ANDREW NAVE |
| Masonry Wall/Backfill | 6/18/2019 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 7/15/2019 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2019 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2019 | Partial Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 10/31/2019 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 10/31/2019 | Not Ready for Inspection | ANDREW NAVE |
| Wood Frame | 10/31/2019 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 11/18/2019 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 12/16/2019 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 1/14/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 1/15/2020 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 1/15/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 1/16/2020 | Approved | ANDREW NAVE |
| Wood Frame | 1/17/2020 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/31/2020 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 1/31/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 2/13/2020 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 2/24/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 2/24/2020 | Approved | ANDREW NAVE |
| Insulation | 2/24/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/4/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 3/4/2020 | Approved | ANDREW NAVE |
| Sewer | 3/9/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/20/2020 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 4/17/2020 | Approved | ANDREW NAVE |
| Underground Mechanical | 10/6/2020 | Approved | ANDREW NAVE |
| Final | 2/25/2021 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 2/25/2021 | Approved | ANDREW NAVE |
| Green Building Final | 2/25/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 2/25/2021 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 2/25/2021 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 2/26/2021 | Corrections Issued | ANDREW NAVE |
| Gas Test | 3/2/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 3/2/2021 | Approved | ANDREW NAVE |
| PLUMBING-Final | 3/2/2021 | Approved | ANDREW NAVE |
| Special/Order Compliance | 3/2/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 3/3/2021 | Corrections Issued | ANDREW NAVE |
| Service/Power Release | 3/3/2021 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 3/8/2021 | Approved | ANDREW NAVE |
| Green Building Final | 3/8/2021 | Approved | ANDREW NAVE |
| Final | 3/18/2021 | Permit Finaled | ANDREW NAVE |
| Smoke Detectors | 3/18/2021 | Approved | ANDREW NAVE |