11460 W THURSTON CIR 90049
Certificate Information: 11460 W THURSTON CIR 90049
- Application / Permit
- 16014-30000-06211
- Plan Check / Job No.
- B16WL06896
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and major remodel of existing single family dwelling from 1-story to 2-story. NFPA-13D fire sprinkler required thru out. Slope band analysis maximum allowable RFA = 4,316 sq-ft + 863 sq-ft (20% bonus) = 5,179 sq-ft.
- Permit Issued
- Issued on 6/15/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2017 | ERWIN PASCUA |
| Corrections Issued | 2/8/2017 | ERWIN PASCUA |
| Green Plans Picked Up | 2/8/2017 | APPLICANT |
| Quality Review Completed | 2/9/2017 | STEVEN KIM |
| Building Plans Picked Up | 3/2/2017 | APPLICANT |
| Applicant returned to address corrections | 4/18/2017 | ERWIN PASCUA |
| Plan Check Approved | 6/13/2018 | ERWIN PASCUA |
| Issued | 6/15/2018 | LADBS |
| CofO in Progress | 9/25/2025 | CARLOS MATAMOROS |
| Permit Finaled | 9/29/2025 | RICHARD STEINBACH |
| CofO Issued | 9/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/18/2018 | STEVEN JIN |
| BHO/Hillside ordinance | Cleared | 5/18/2018 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2018 | STEVEN JIN |
| Hydrant and Access approval | Cleared | 5/21/2018 | GILBERT URREA |
| Low Impact Development | Cleared | 6/8/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/8/2018 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/12/2018 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 6/13/2018 | ERWIN PASCUA |
| Grading Pre-Inspection | Cleared | 6/13/2018 | ERWIN PASCUA |
| Green Code | Cleared | 6/13/2018 | RICHARD GARCIA |
Contact Information
| Contractor | Ralley Capital & Development Co; Lic. No.: 788438-B | 865 COMSTOCK AVE STE 5B LOS ANGELES, CA 90024 |
| Engineer | Azizisefat, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2018 | Approved | JOEL LAUNCHBAUGH |
| Pre-Inspection | 4/26/2019 | Partial Approval | ANTHONY MCDOWALL |
| Pre-Inspection | 9/17/2019 | Partial Inspection | ANTHONY MCDOWALL |
| Pre-Inspection | 10/16/2019 | Partial Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 12/18/2019 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/31/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/18/2020 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/30/2020 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Steel/Welding | 9/2/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/9/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/21/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 9/6/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 10/17/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 10/21/2022 | Corrections Issued | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 10/25/2022 | Partial Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 11/3/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/28/2022 | Partial Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 12/8/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/3/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/13/2023 | Corrections Issued | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 2/15/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/22/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/9/2023 | No Access for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/23/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/31/2023 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/2/2023 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/27/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/26/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/26/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 12/20/2023 | No Access for Inspection | CARLOS MATAMOROS |
| Wood Frame | 12/22/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 1/4/2024 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 2/22/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/26/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/22/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 4/24/2024 | Conditional Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/24/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/29/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 4/29/2024 | Corrections Issued | CHRISTOPHER WILSON |
| MERV13>=Rough | 4/29/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 4/29/2024 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/30/2024 | Corrections Issued | CARLOS MATAMOROS |
| Wood Frame | 4/30/2024 | Conditional Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 5/2/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 5/2/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 5/3/2024 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 5/15/2024 | Corrections Issued | MICHAEL PELHAM |
| Drywall Nailing | 5/28/2024 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 5/28/2024 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/12/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 6/12/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 6/12/2024 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 6/12/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 6/25/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 10/1/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/5/2024 | Corrections Issued | BOBBY KEY |
| Gas Test | 12/5/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 12/12/2024 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 12/12/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 12/12/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 12/13/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 12/13/2024 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 12/16/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 12/16/2024 | Corrections Issued | CARLOS MATAMOROS |
| Sewer | 12/16/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/29/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | CARLOS MATAMOROS |
| Structural Steel Frame | 1/29/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/19/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/17/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 4/18/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 4/21/2025 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 4/22/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 8/19/2025 | Approved | CARLOS MATAMOROS |
| Final | 9/24/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 9/24/2025 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 9/24/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/24/2025 | Approved | CARLOS MATAMOROS |