1101 N STRADELLA ROAD 90077

Certificate Information: 1101 N STRADELLA ROAD 90077

Application / Permit
16014-30000-05008
Plan Check / Job No.
B16WL05520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel (3237 s.f.) and addition (2605 s.f.) to (e) 2-story s.f.d.
Permit Issued
Issued on 2/9/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2016 APPLICANT
Green Plans Picked Up 11/8/2016 APPLICANT
Assigned to Plan Check Engineer 11/9/2016 CHON CHIO KUO
Corrections Issued 11/14/2016 CHON CHIO KUO
Quality Review Completed 11/17/2016 FELIX FIGUEROA
Building Plans Picked Up 11/17/2016 APPLICANT
Applicant returned to address corrections 1/11/2017 CHON CHIO KUO
Applicant returned to address corrections 1/24/2017 CHON CHIO KUO
Plan Check Approved 2/8/2017 CHON CHIO KUO
Issued 2/9/2017 LADBS
CofO in Progress 10/15/2022 CHRISTOPHER WILSON
CofO in Progress 10/22/2022 CHRISTOPHER WILSON
Permit Finaled 11/3/2022 DANIEL ORRANTE
CofO Issued 11/3/2022 DANIEL ORRANTE
Permit Finaled 11/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/14/2016 JOSEPH RHYU
BHO/Hillside ordinance Cleared 12/14/2016 JOSEPH RHYU
BHO/Hillside ordinance Cleared 12/14/2016 JOSEPH RHYU
Permit Cleared 12/14/2016 JOSEPH RHYU
Hydrant and Access approval Cleared 1/10/2017 ROBERT DUFF
Sewer availability Cleared 1/11/2017 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 1/13/2017 RAVIL MANAPOV
Low Impact Development Cleared 1/13/2017 SAM NAVID
Roof/Waste drainage to street Cleared 1/13/2017 RAVIL MANAPOV
Building over 3-story or 36-ft Cleared 1/24/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/24/2017 CALOSHA APPROVED
GPI Written Notices Cleared 1/24/2017 CHON CHIO KUO
Grading Pre-Inspection Cleared 1/24/2017 CHON CHIO KUO
Work Adjacent to Public Way Cleared 1/24/2017 ERIK MUNOZ
Green Code Cleared 1/26/2017 RICHARD GARCIA

Contact Information

Architect Williger, Paul Brant; Lic. No.: C24022 26176 FAIRSIDE ROAD      MALIBU, CA 90265
Contractor Taconic Builders Inc; Lic. No.: 930731-B 11117 WASHINGTON BLVD      CULVER CITY, CA 90232
Engineer Parker, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025
Engineer Peck, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2017 Approved ANTHONY ANDERSON
Piling/Pier/Caisson 5/1/2017 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 5/5/2017 Partial Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 6/22/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 7/13/2017 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 8/17/2017 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 8/28/2017 Conditional Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 9/5/2017 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 9/5/2017 Partial Inspection ANTHONY ANDERSON
Deputy Steel/Welding 9/14/2017 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 9/15/2017 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 9/18/2017 Conditional Approval ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/4/2017 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 10/11/2017 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 10/13/2017 Conditional Approval ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/7/2017 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 11/28/2017 Approved ANTHONY ANDERSON
HVAC-Rough 2/7/2018 Conditional Approval ANTHONY ANDERSON
HVAC-Rough 3/21/2018 Approved ANTHONY ANDERSON
Piling/Pier/Caisson 1/9/2019 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 1/26/2019 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 4/6/2019 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 4/13/2019 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 9/30/2019 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 3/10/2020 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 6/27/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 7/4/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 7/25/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/1/2020 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/9/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 9/9/2022 Approved CHRISTOPHER WILSON
Final 9/9/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 9/9/2022 Approved CHRISTOPHER WILSON
Green Building Final 9/9/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 9/9/2022 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 9/9/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/9/2022 Approved CHRISTOPHER WILSON
Final 9/13/2022 No Access for Inspection CHRISTOPHER WILSON
Green Building Final 9/13/2022 No Access for Inspection CHRISTOPHER WILSON
Smoke Detectors 9/13/2022 No Access for Inspection CHRISTOPHER WILSON
Final 9/19/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Final 9/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Smoke Detectors 9/19/2022 Approved CHRISTOPHER WILSON
Final 10/11/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 10/11/2022 Partial Inspection CHRISTOPHER WILSON
Final 10/14/2022 OK to Issue CofO CHRISTOPHER WILSON
Green Building Final 10/14/2022 Approved CHRISTOPHER WILSON