549 N MUSKINGUM AVE 90272

Certificate Information: 549 N MUSKINGUM AVE 90272

Application / Permit
16014-30000-03976
Plan Check / Job No.
B16WL04272
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add ground floor 800 sq ft.Convert 400 sq ft garage to family room.Add attached 400 sq ft garage.
Permit Issued
Issued on 2/14/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2016 APPLICANT
Assigned to Plan Check Engineer 8/19/2016 HARLEN CARRAHER
Corrections Issued 8/19/2016 HARLEN CARRAHER
Plan Check Approved 2/14/2017 HARLEN CARRAHER
Issued 2/14/2017 LADBS
Permit Withdrawn-Status Void 1/18/2019 CORA JOHNSON
Re-Activate Permit 1/23/2019 ALFREDO JARA
CofO in Progress 3/25/2021 ANDREW NAVE
Permit Finaled 4/22/2021 KENNETH NAGLE
CofO Issued 4/22/2021 KENNETH NAGLE
Permit Finaled 4/22/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/19/2016 HARLEN CARRAHER
BHO/Hillside ordinance Cleared 11/3/2016 IRENE CHIA
BHO/Hillside ordinance Cleared 11/3/2016 IRENE CHIA
BHO/Hillside ordinance Cleared 11/3/2016 IRENE CHIA
BHO/Hillside ordinance Cleared 11/3/2016 IRENE CHIA
Coastal Zone Cleared 11/3/2016 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 11/3/2016 IRENE CHIA
Sewer availability Cleared 11/3/2016 IRENE CHIA
Low Impact Development Cleared 1/27/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/1/2017 ERIK MUNOZ
Permit Cleared 2/13/2017 BRIAN KELLY
BHO/Hillside ordinance Cleared 2/14/2017 IRENE CHIA

Contact Information

Architect Gemigniani, Richard Louis; Lic. No.: C18783 11739 CANTON PL      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/21/2017 Corrections Issued KENNETH NAGLE
Pre-Inspection 4/6/2017 Partial Inspection KENNETH NAGLE
Special/Order Compliance 4/7/2017 Corrections Issued KENNETH NAGLE
Pre-Inspection 5/1/2017 Partial Inspection KENNETH NAGLE
Pre-Inspection 5/2/2017 Corrections Issued KENNETH NAGLE
Pre-Inspection 5/24/2017 Partial Inspection KENNETH NAGLE
Pre-Inspection 6/9/2017 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 8/23/2017 Not Ready for Inspection KENNETH NAGLE
Pre-Inspection 11/16/2018 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 3/5/2019 Not Ready for Inspection RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 4/27/2019 Conditional Approval CARLOS MATAMOROS
Deputy Wood Construction 9/20/2019 Approved ANDREW NAVE
Deputy Wood Construction 9/26/2019 Approved ANDREW NAVE
Special/Order Compliance 7/15/2020 Approved ANDREW NAVE
Excavation/Setback/Form/Re-Bar 8/27/2020 Corrections Issued ANDREW NAVE
PLUMBING-Final 2/25/2021 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 3/8/2021 Approved ANDREW NAVE
Final 3/8/2021 Not Ready for Inspection ANDREW NAVE
Footing/Foundation/Slab 3/8/2021 Approved ANDREW NAVE
Green Building Final 3/8/2021 Corrections Issued ANDREW NAVE
Green Building Rough 3/8/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 3/8/2021 SGSOV Approved ANDREW NAVE
Service/Power Release 3/8/2021 Approved ANDREW NAVE
Smoke Detectors 3/8/2021 Approved ANDREW NAVE
Final 3/18/2021 Corrections Issued ANDREW NAVE
Green Building Final 3/18/2021 Approved ANDREW NAVE
Final 3/25/2021 OK to Issue CofO ANDREW NAVE