9420 W READCREST DR 90210
Certificate Information: 9420 W READCREST DR 90210
- Application / Permit
- 16014-30000-03236
- Plan Check / Job No.
- B16WL03549
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (e) garage to habitable space and add a new basement.
- Permit Issued
- Issued on 1/13/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2016 | RICHARD GARCIA |
| Green Plans Picked Up | 8/4/2016 | APPLICANT |
| Corrections Issued | 8/6/2016 | RICHARD GARCIA |
| Quality Review Completed | 8/9/2016 | STEVEN KIM |
| Building Plans Picked Up | 8/10/2016 | APPLICANT |
| Applicant returned to address corrections | 11/9/2016 | RICHARD GARCIA |
| Plan Check Approved | 1/13/2017 | RICHARD GARCIA |
| Plan Check Approved | 1/13/2017 | RICHARD GARCIA |
| Issued | 1/13/2017 | LADBS |
| CofO in Progress | 11/22/2021 | RAUL BARAJAS |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/17/2016 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 8/17/2016 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 8/17/2016 | ROBERT DUFF |
| Green Code | Cleared | 9/9/2016 | BRYAN MEYER |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2016 | ALFREDO JARA |
| Low Impact Development | Cleared | 11/23/2016 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 11/23/2016 | ALFREDO JARA |
| Work Adjacent to Public Way | Cleared | 12/23/2016 | DAVID PEREZ |
| Excavation more than 5-ft deep | Cleared | 1/11/2017 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/11/2017 | RICHARD GARCIA |
| Grading Pre-Inspection | Cleared | 1/11/2017 | RICHARD GARCIA |
| BHO/Hillside ordinance | Cleared | 1/12/2017 | LUZ RABELO |
Contact Information
| Architect | Shokoufandeh, Shahram; Lic. No.: C32681 | 4628 CERRILLOS DRIVE WOODLAND HILLS, CA 91364 |
| Contractor | Omni Real Estate & Construction Group; Lic. No.: 1007716-B | P O BOX 61074 IRVINE, CA 92602 |
| Engineer | Shokoufandeh, Bahman; Lic. No.: C49709 | 13024 SKY VALLEY ROAD LOS ANGELES, CA 90049 |
| Geologist | Kruger, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/5/2017 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 6/5/2017 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 6/5/2017 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 6/6/2017 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/8/2017 | Partial Approval | RONALD COWAN |
| Piling/Pier/Caisson | 6/8/2017 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 6/9/2017 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/20/2017 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/21/2017 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 7/10/2017 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 8/1/2017 | Partial Approval | RONALD COWAN |
| Piling/Pier/Caisson | 2/22/2018 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 7/23/2018 | Partial Approval | RONALD COWAN |
| Reinforced Concrete Frame | 8/29/2018 | Partial Approval | RONALD COWAN |
| Deputy Shotcrete | 9/5/2018 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 9/13/2018 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 9/14/2018 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 9/20/2018 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 10/25/2018 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 1/11/2019 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 1/11/2019 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2019 | Partial Approval | RICHARD STEINBACH |
| Green Building Rough | 7/17/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| ELECTRICAL-Rough | 12/19/2019 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 12/23/2019 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 12/24/2019 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2020 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 1/9/2020 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 3/9/2020 | Conditional Approval | RICHARD STEINBACH |
| Green Building Rough | 3/9/2020 | Approved | RICHARD STEINBACH |
| Insulation | 3/9/2020 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 3/9/2020 | Partial Approval | RICHARD STEINBACH |
| Special/Order Compliance | 3/9/2020 | Corrections Issued | RICHARD STEINBACH |
| Drywall Nailing | 3/19/2020 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 6/29/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/7/2021 | Partial Inspection | RAUL BARAJAS |
| Gas Test | 5/7/2021 | Approved | RAUL BARAJAS |
| Gas Test | 5/28/2021 | Approved | RAUL BARAJAS |
| HVAC-Final | 6/11/2021 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Final | 8/18/2021 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 9/21/2021 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 10/26/2021 | Approved | RAUL BARAJAS |
| Final | 10/26/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/26/2021 | Approved | RAUL BARAJAS |
| Green Building Final | 10/26/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 10/26/2021 | Approved | RAUL BARAJAS |
| Final | 10/29/2021 | Partial Inspection | RAUL BARAJAS |
| Final | 11/3/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Test | 11/4/2021 | Approved | RAUL BARAJAS |
| Final | 11/22/2021 | Conditional Approval | RAUL BARAJAS |