2225 W EFFIE ST 90026

Certificate Information: 2225 W EFFIE ST 90026

Application / Permit
16014-30000-03005
Plan Check / Job No.
B16WL03327
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 12'7" x 14'3" to enlarge/remodel kitchen & add 6'7" x 12'1" bathroom/closet.Add 4'9" x 3' to enlarge bathroom.Enclose 4'4" x 36' balconies to enlarge living & bedroom.Add 5'7" x 18'2" covered balconyAdd 24 sq ft basement water heater enclosure.Remodel throughout.Foundation replacement.Reroof comp shingles.Replace doors & 7 windows.(See comments).
Permit Issued
Issued on 7/13/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2016 APPLICANT
Assigned to Plan Check Engineer 6/24/2016 HARLEN CARRAHER
Plan Check Approved 6/24/2016 HARLEN CARRAHER
Issued 7/13/2016 LADBS
CofO in Progress 2/26/2024 THOMAS LOGRASSO
CofO in Progress 2/26/2024 THOMAS LOGRASSO
CofO in Progress 4/23/2024 THOMAS LOGRASSO
CofO in Progress 6/22/2024 SCOTT FINNILA
CofO Issued 6/26/2024 DEROLD HAUFF
Permit Finaled 6/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/24/2016 HARLEN CARRAHER

Contact Information

Contractor Owner-Builder       ,
Engineer Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2016 Approved DAVID CHAN
BUILDING-Rough-Frame 12/5/2016 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 1/26/2017 Conditional Approval DAVID CHAN
ELECTRICAL-Rough 1/26/2017 Approved DAVID CHAN
PLUMBING-Rough 1/26/2017 Approved DAVID CHAN
BUILDING-Rough-Frame 2/7/2017 Approved DAVID CHAN
ELECTRICAL-Rough 2/7/2017 Approved DAVID CHAN
PLUMBING-Rough 2/7/2017 Approved DAVID CHAN
Insulation 2/10/2017 Approved DAVID CHAN
Drywall Nailing 3/17/2017 Approved DAVID CHAN
Interior/Exterior Lathing 3/17/2017 Not Ready for Inspection DAVID CHAN
Interior/Exterior Lathing 3/24/2017 Approved DAVID CHAN
ELECTRICAL-Final 8/17/2017 Corrections Issued DAVID CHAN
PLUMBING-Final 8/17/2017 Not Ready for Inspection DAVID CHAN
Service/Power Release 8/17/2017 Not Ready for Inspection DAVID CHAN
Service/Power Release 8/18/2017 Approved DAVID CHAN
Final 10/13/2017 Corrections Issued DAVID CHAN
SGSOV-Seismic Gas S/O Valve 10/13/2017 SGSOV Approved DAVID CHAN
Smoke Detectors 10/13/2017 Approved DAVID CHAN
ELECTRICAL-Final 10/18/2017 Approved DAVID CHAN
HVAC-Final 10/18/2017 Approved DAVID CHAN
PLUMBING-Final 10/18/2017 Approved DAVID CHAN
Final 12/2/2020 No Access for Inspection KATHRYN BUTTERWORTH
Final 1/20/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 7/6/2021 Corrections Issued RUBEN SALAS
Final 2/23/2024 OK to Issue CofO THOMAS LOGRASSO