1180 N PIEDRA MORADA DR 90272
Certificate Information: 1180 N PIEDRA MORADA DR 90272
- Application / Permit
- 16014-30000-02990
- Plan Check / Job No.
- B16WL03305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Major remodel of 2-story SFD.
- Permit Issued
- Issued on 2/23/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2016 | APPLICANT |
| Green Plans Picked Up | 7/18/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2016 | MANUEL GARCIA |
| Corrections Issued | 7/25/2016 | MANUEL GARCIA |
| Quality Review Completed | 7/28/2016 | GUANG MIN TUNG |
| Building Plans Picked Up | 7/28/2016 | APPLICANT |
| Applicant returned to address corrections | 10/18/2016 | MANUEL GARCIA |
| Plan Check Approved | 10/27/2016 | MANUEL GARCIA |
| Issued | 2/23/2017 | LADBS |
| CofO in Progress | 12/2/2022 | BRENDAN LOONEY |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
| CofO Issued | 2/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 7/29/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 7/29/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 7/29/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 7/29/2016 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 7/29/2016 | JOHN CONNEALLY |
| Sewer availability | Cleared | 7/29/2016 | RAVIL MANAPOV |
| Coastal Zone | Cleared | 8/22/2016 | CASSANDRA ZWEEP |
| Miscellaneous | Cleared | 8/22/2016 | CASSANDRA ZWEEP |
| ZA Case | Cleared | 8/22/2016 | CASSANDRA ZWEEP |
| Green Code | Cleared | 9/13/2016 | BRYAN MEYER |
| Low Impact Development | Cleared | 9/16/2016 | MICHAEL SCADUTO |
| Miscellaneous | Cleared | 9/16/2016 | TERRY PHAN |
| Roof/Waste drainage to street | Cleared | 9/16/2016 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 10/27/2016 | MANUEL GARCIA |
Contact Information
| Architect | Irani, Glen R; Lic. No.: C22184 | 410 SHERMAN CANAL VENICE, CA 90291 |
| Contractor | Tso Construction Inc; Lic. No.: 911570-B | P O BOX 6883 MALIBU, CA 90264 |
| Engineer | Behshid, Farshid; Lic. No.: S4585 | 4647 ENCINAS DR LA CANADA, CA 91011 |
| Engineer | Mac, Neil Daniel Paul; Lic. No.: L6961 | PO BOX 1342 TOPANGA, CA 90290 |
| Engineer | Mahn, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Obando, Gaspar Eduardo; Lic. No.: C71382 | 14000 TAHITI WY 303 MARINA DEL REY, CA 90292 |
| Geologist | Pongracz-Bartha, Ed; Lic. No.: EG2370 | 26018 PALOMITA DR VALENCIA, CA 91355 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/21/2017 | Not Ready for Inspection | VINCENT SCIPIONI |
| Green Building Rough | 7/21/2017 | Not Ready for Inspection | VINCENT SCIPIONI |
| Pre-Inspection | 7/21/2017 | Partial Inspection | VINCENT SCIPIONI |
| Verify Sprinkler Sign Off | 7/21/2017 | Not Ready for Inspection | VINCENT SCIPIONI |
| Wood Frame | 7/21/2017 | Not Ready for Inspection | VINCENT SCIPIONI |
| ELECTRICAL-Rough | 8/16/2017 | Partial Approval | VINCENT SCIPIONI |
| PLUMBING-Rough | 8/16/2017 | Partial Approval | VINCENT SCIPIONI |
| Sewer | 8/16/2017 | Not Ready for Inspection | VINCENT SCIPIONI |
| Footing/Foundation/Slab | 11/17/2017 | Partial Approval | VINCENT SCIPIONI |
| BUILDING-Rough-Frame | 1/29/2018 | Partial Inspection | VINCENT SCIPIONI |
| Green Building Rough | 1/29/2018 | Not Ready for Inspection | VINCENT SCIPIONI |
| Structural Steel Frame | 1/29/2018 | Not Ready for Inspection | VINCENT SCIPIONI |
| Verify Sprinkler Sign Off | 1/29/2018 | Not Ready for Inspection | VINCENT SCIPIONI |
| Deputy Steel/Welding | 2/13/2018 | Approved | JOHN LUMB |
| Footing/Foundation/Slab | 4/12/2018 | Not Ready for Inspection | JOHN LUMB |
| Excavation/Setback/Form/Re-Bar | 6/11/2018 | Approved | JOHN LUMB |
| ELECTRICAL-Rough | 6/13/2018 | Partial Approval | JOHN LUMB |
| HVAC-Rough | 6/15/2018 | Partial Approval | JOHN LUMB |
| PLUMBING-Rough | 6/15/2018 | Partial Approval | JOHN LUMB |
| ELECTRICAL-Rough | 7/16/2018 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 8/9/2018 | Partial Approval | JOHN LUMB |
| Excavation/Setback/Form/Re-Bar | 8/24/2018 | Partial Approval | VINCENT SCIPIONI |
| Footing/Foundation/Slab | 8/24/2018 | Partial Approval | VINCENT SCIPIONI |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2018 | Partial Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 10/16/2018 | Conditional Approval | DANIEL ORRANTE |
| ELECTRICAL-Rough | 3/11/2019 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/11/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/11/2019 | Partial Approval | ANDREW NAVE |
| Reinforced Concrete Frame | 3/11/2019 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/29/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Drilled-In Anchors | 5/31/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 5/31/2019 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/18/2019 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 6/18/2019 | Not Ready for Inspection | ANDREW NAVE |
| Verify Sprinkler Sign Off | 6/18/2019 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2019 | Partial Approval | ANDREW NAVE |
| Wood Frame | 10/15/2019 | Partial Approval | DAVID FEILER |
| Deputy Steel/Welding | 10/22/2019 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 10/23/2019 | Conditional Approval | ANDREW NAVE |
| Wood Frame | 10/24/2019 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2019 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 1/13/2020 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 3/11/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 3/11/2020 | Partial Approval | ANDREW NAVE |
| Insulation | 3/17/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 3/17/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 4/20/2020 | Partial Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 4/27/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 4/27/2020 | Corrections Issued | ANDREW NAVE |
| Verify Sprinkler Sign Off | 4/27/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 4/28/2020 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/20/2020 | Partial Inspection | ANDREW NAVE |
| Green Building Rough | 5/20/2020 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 5/20/2020 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/29/2020 | Partial Inspection | ANDREW NAVE |
| Green Building Rough | 6/29/2020 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 7/2/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/17/2020 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 9/9/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 12/9/2020 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 12/29/2020 | Partial Approval | JOHNNY MIRANDA |
| Pool Piping | 12/29/2020 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 2/17/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 3/9/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 4/13/2021 | Corrections Issued | ANDREW NAVE |
| Service/Power Release | 4/13/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 8/4/2021 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/6/2021 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 8/6/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 8/6/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Not Ready | ANDREW NAVE |
| HVAC-Final | 8/9/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 8/9/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 8/11/2021 | Approved | ANDREW NAVE |
| Final | 8/11/2021 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Final | 8/11/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 8/11/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Final | 8/11/2021 | Partial Approval | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 8/11/2021 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 8/11/2021 | Not Ready for Inspection | ANDREW NAVE |
| Final | 10/1/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 10/1/2021 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 10/1/2021 | Approved | ANDREW NAVE |
| Sewer | 10/19/2021 | Approved | ANDREW NAVE |
| Final | 10/26/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 10/26/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 10/26/2021 | Approved | ANDREW NAVE |
| PLUMBING-Final | 10/26/2021 | Approved | ANDREW NAVE |
| Final | 11/18/2021 | Corrections Issued | ANDREW NAVE |
| Final | 9/28/2022 | Conditional Approval | BRENDAN LOONEY |
| Final | 12/1/2022 | OK to Issue CofO | BRENDAN LOONEY |