636 N ERSKINE DR 90272

Certificate Information: 636 N ERSKINE DR 90272

Application / Permit
16014-30000-02439
Plan Check / Job No.
B16WL02762
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel of entire house, to increase ceiling heights and make 250sf addition at family room, dining room, master bath.
Permit Issued
Issued on 7/10/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2016 APPLICANT
Assigned to Plan Check Engineer 6/16/2016 RICARDO RAMIREZ
Corrections Issued 6/23/2016 RICARDO RAMIREZ
Quality Review Completed 6/23/2016 GUANG MIN TUNG
Building Plans Picked Up 6/27/2016 APPLICANT
Green Plans Picked Up 8/9/2016 APPLICANT
Applicant returned to address corrections 2/7/2017 RICARDO RAMIREZ
Applicant returned to address corrections 4/20/2017 RICARDO RAMIREZ
Plan Check Approved 6/2/2017 RICARDO RAMIREZ
Issued 7/10/2017 LADBS
CofO in Progress 5/13/2020 ANDREW NAVE
Permit Finaled 6/25/2020 VINCENT COTTON
Permit Finaled 6/25/2020 VINCENT COTTON
CofO Issued 6/25/2020 VINCENT COTTON

Permit Application Clearance Information

Coastal Zone Cleared 7/29/2016 ERIC CLAROS
Hydrant and Access approval Cleared 7/29/2016 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 8/9/2016 LUZ RABELO
Sewer availability Cleared 8/9/2016 LUZ RABELO
Green Code Cleared 9/8/2016 BRYAN MEYER
GPI Written Notices Cleared 4/20/2017 RICARDO RAMIREZ
Grading Pre-Inspection Cleared 4/20/2017 RICARDO RAMIREZ
Low Impact Development Cleared 6/1/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 6/2/2017 HISASHI KOBAYAKAWA

Contact Information

Architect , ; Lic. No.: C26598       ,
Contractor Owner-Builder       ,
Engineer Lobana, Singh Maninder Pa; Lic. No.: C50989 4930 READ RD      MOORPARK, CA 93021

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/25/2017 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 9/26/2017 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 10/16/2017 Approved KENNETH NAGLE
Underground Mechanical 10/24/2017 Not Ready for Inspection KENNETH NAGLE
Deputy Drilled-In Anchors 11/29/2017 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 12/19/2017 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 2/12/2018 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 2/13/2018 Corrections Issued RICHARD STEINBACH
HVAC-Rough 2/13/2018 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 3/8/2018 Corrections Issued RICHARD STEINBACH
ELECTRICAL-Rough 3/8/2018 Approved RICHARD STEINBACH
Green Building Rough 3/8/2018 Corrections Issued RICHARD STEINBACH
HVAC-Rough 3/8/2018 Corrections Issued RICHARD STEINBACH
BUILDING-Rough-Frame 3/15/2018 Corrections Issued RICHARD STEINBACH
Green Building Rough 3/15/2018 Not Ready for Inspection RICHARD STEINBACH
HVAC-Rough 3/15/2018 Not Ready for Inspection RICHARD STEINBACH
BUILDING-Rough-Frame 4/4/2018 Approved JOHN LUMB
Green Building Rough 4/4/2018 Approved JOHN LUMB
HVAC-Rough 4/4/2018 Approved JOHN LUMB
Insulation 4/6/2018 Approved RICHARD STEINBACH
Drywall Nailing 4/17/2018 Approved RYAN MCGILL
Interior/Exterior Lathing 4/23/2018 Corrections Issued RICHARD STEINBACH
Interior/Exterior Lathing 4/30/2018 Partial Approval RICHARD STEINBACH
Shower Pan 4/30/2018 Not Ready for Inspection RICHARD STEINBACH
Interior/Exterior Lathing 5/21/2018 Approved RICHARD STEINBACH
Shower Pan 5/21/2018 Approved RICHARD STEINBACH
ELECTRICAL-Final 6/21/2019 Corrections Issued ANDREW NAVE
Service/Power Release 6/21/2019 Approved ANDREW NAVE
Service/Power Release 7/30/2019 Approved ANDREW NAVE
Final 1/8/2020 Corrections Issued ANDREW NAVE
Green Building Final 1/8/2020 Not Ready for Inspection ANDREW NAVE
HVAC-Final 1/8/2020 Corrections Issued ANDREW NAVE
PLUMBING-Final 1/8/2020 Not Ready for Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 1/8/2020 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 1/8/2020 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 1/30/2020 Approved ANDREW NAVE
Final 1/30/2020 Corrections Issued ANDREW NAVE
Green Building Final 1/30/2020 Not Ready for Inspection ANDREW NAVE
HVAC-Final 1/30/2020 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 1/30/2020 SGSOV Approved ANDREW NAVE
Smoke Detectors 1/30/2020 Approved ANDREW NAVE
Final 4/6/2020 Corrections Issued ANDREW NAVE
Green Building Final 4/6/2020 Approved ANDREW NAVE
Final 5/13/2020 Conditional Approval ANDREW NAVE