2334 S FREY AVE 90291

Certificate Information: 2334 S FREY AVE 90291

Application / Permit
16014-30000-01142
Plan Check / Job No.
B16WL01295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd floor addition and major remodel to (e) 1-story s.f.d.
Permit Issued
Issued on 9/12/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2016 APPLICANT
Assigned to Plan Check Engineer 4/1/2016 VLADIMIR ARUTYUNYAN
Corrections Issued 4/5/2016 VLADIMIR ARUTYUNYAN
Quality Review Completed 4/6/2016 GUANG MIN TUNG
Building Plans Picked Up 4/8/2016 APPLICANT
Green Plans Picked Up 4/20/2016 APPLICANT
Plan Check Approved 9/6/2019 VLADIMIR ARUTYUNYAN
Issued 9/12/2019 LADBS
CofO in Progress 8/6/2021 PIERRE VEGA
CofO in Progress 8/6/2021 PIERRE VEGA
CofO Issued 8/9/2021 VINCENT COTTON
Permit Finaled 8/9/2021 VINCENT COTTON

Permit Application Clearance Information

Specific Plan Cleared 5/16/2016 SOCORRO YUMUL
ZA Case Cleared 4/30/2019 TREVOR MARTIN
ZA Case Cleared 4/30/2019 TREVOR MARTIN
Green Code Cleared 8/8/2019 RICHARD GARCIA
Coastal Zone Cleared 8/19/2019 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 8/19/2019 JAMES MORALEZ
Low Impact Development Cleared 8/19/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 8/19/2019 JAMES MORALEZ
Sewer availability Cleared 8/19/2019 JAMES MORALEZ

Contact Information

Architect Winters, Patrick Charles; Lic. No.: C22032 11410 BIONA DRIVE      LOS ANGELES, CA 90066
Contractor Westside Construction; Lic. No.: 852976-B 1531 15TH STREET APT 6      SANTA MONICA, CA 90404
Engineer Brah, Kulwant Singh; Lic. No.: S2752 20540 CALIFA ST      WOODLAND HILLS, CA 91367

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 2/5/2020 Conditional Approval DAVID HEINE
METHANE-Barrier 2/5/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 2/5/2020 Not Ready for Inspection DAVID HEINE
Deputy Drilled-In Anchors 2/26/2020 Partial Approval DAVID HEINE
Wood Frame 3/4/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 3/9/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 3/9/2020 Partial Approval DAVID HEINE
METHANE-Barrier 3/9/2020 Approved DAVID HEINE
METHANE-Subgrade 3/9/2020 Approved DAVID HEINE
Wood Frame 4/7/2020 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 5/7/2020 Approved DAVID HEINE
Footing/Foundation/Slab 5/7/2020 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 5/8/2020 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 5/11/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval DAVID HEINE
Deputy Steel/Welding 5/13/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Partial Approval DAVID HEINE
Underground Mechanical 10/22/2020 Approved DAVID HEINE
ELECTRICAL-Rough 11/4/2020 Approved DAVID HEINE
HVAC-Rough 11/4/2020 Approved DAVID HEINE
PLUMBING-Rough 11/4/2020 Approved DAVID HEINE
ELECTRICAL-Rough 11/6/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 12/8/2020 Approved JUAN VALENZUELA
Green Building Rough 12/8/2020 Approved JUAN VALENZUELA
METHANE-Rough 12/8/2020 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 12/8/2020 Approved JUAN VALENZUELA
Insulation 12/14/2020 Approved DAVID HEINE
Interior/Exterior Lathing 12/14/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 12/21/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 1/6/2021 Partial Approval DAVID HEINE
ELECTRICAL-Rough 2/23/2021 Approved JOHNNY MIRANDA
Structural Steel Frame 2/23/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 6/14/2021 Approved JOHNNY MIRANDA
HVAC-Final 6/14/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 6/14/2021 Approved JOHNNY MIRANDA
Smoke Detectors 6/14/2021 Approved JOHNNY MIRANDA
Drywall Nailing 7/22/2021 Approved JOHNNY MIRANDA
Final 7/22/2021 OK to Issue CofO JOHNNY MIRANDA
Footing/Foundation/Slab 7/22/2021 Approved JOHNNY MIRANDA
Green Building Final 7/22/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/22/2021 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 7/22/2021 Approved JOHNNY MIRANDA