444 N GREENCRAIG ROAD 90049
Certificate Information: 444 N GREENCRAIG ROAD 90049
- Application / Permit
- 16014-30000-00606
- Plan Check / Job No.
- B16WL00674
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story ground floor addition to (e) s.f.d.
- Permit Issued
- Issued on 8/8/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2016 | TARIK SAOUD |
| Corrections Issued | 3/10/2016 | TARIK SAOUD |
| Quality Review Completed | 3/11/2016 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 3/14/2016 | APPLICANT |
| Green Plans Picked Up | 3/14/2016 | APPLICANT |
| Applicant returned to address corrections | 7/14/2016 | TARIK SAOUD |
| Plan Check Approved | 8/8/2017 | TARIK SAOUD |
| Issued | 8/8/2017 | LADBS |
| CofO in Progress | 10/31/2025 | KEVIN SARGSYAN |
| Permit Finaled | 12/4/2025 | RICHARD STEINBACH |
| CofO Issued | 12/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/10/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/10/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 5/10/2016 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/10/2016 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/10/2016 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 6/16/2016 | MARTIN FRAGOSO |
| BHO/Hillside ordinance | Cleared | 6/23/2016 | HUGO RICO |
| Green Code | Cleared | 6/23/2016 | TARIK SAOUD |
| Grading Pre-Inspection | Cleared | 7/14/2016 | TARIK SAOUD |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2017 | LUZ RABELO |
Contact Information
| Architect | Raider, David H; Lic. No.: C6106 | 24311 CLIPSTONE STREET WOODLAND HILLS, CA 91367 |
| Contractor | B W C Associates Inc; Lic. No.: 949248-B | 5805 WHITE OAK AVE #19183 ENCINO, CA 91316 |
| Engineer | Rahbar, Farzin S; Lic. No.: S2833 | 24372 VANOWEN STREET STE 104 WEST HILLS, CA 91307 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 8/30/2017 | Approved | JOHN LUMB |
| Footing/Foundation/Slab | 8/30/2017 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 9/19/2017 | Approved | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 12/13/2017 | Partial Approval | JOHN LUMB |
| PLUMBING-Rough | 2/27/2018 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 10/25/2018 | Partial Approval | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 11/12/2019 | SGSOV Approved | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 2/5/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/10/2021 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 3/15/2021 | Corrections Issued | ROBERT SHELLY |
| BUILDING-Rough-Frame | 3/16/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 3/16/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 3/30/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 3/30/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/21/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 10/21/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/9/2021 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/23/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 5/23/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 5/23/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 6/22/2023 | Corrections Issued | KENNETH NAGLE |
| HVAC-Rough | 7/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| Special/Order Compliance | 7/26/2023 | Partial Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 8/2/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 8/2/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 8/15/2023 | Partial Inspection | ARAM AVEDISIAN |
| Drywall Nailing | 9/20/2023 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 1/25/2024 | Approved | KATHRYN BUTTERWORTH |
| Final | 10/31/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 10/31/2025 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 10/31/2025 | Approved | KEVIN SARGSYAN |