17075 W DEVONSHIRE ST 91325
Certificate Information: 17075 W DEVONSHIRE ST 91325
- Application / Permit
- 16014-30000-00089
- Plan Check / Job No.
- B16WL00115
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Parking Building
- Work Description
- New elevator and walkway to connect two existing structures. restripe some stalls to provide additional disabled access parking.
- Permit Issued
- Issued on 6/15/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2016 | CHRISTINE MAALOUF |
| Corrections Issued | 1/20/2016 | CHRISTINE MAALOUF |
| Quality Review Completed | 1/26/2016 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 1/27/2016 | APPLICANT |
| Green Plans Picked Up | 2/2/2016 | APPLICANT |
| Disabled Access Plans Picked Up | 2/25/2016 | APPLICANT |
| Applicant returned to address corrections | 6/14/2016 | TARIK SAOUD |
| Plan Check Approved | 8/8/2016 | TARIK SAOUD |
| Plan Check Approved | 10/11/2016 | TARIK SAOUD |
| Issued | 6/15/2017 | LADBS |
| CofO in Progress | 12/17/2020 | JEFFREY FULTON |
| CofO Issued | 12/18/2020 | JEFFREY DURAN |
| Permit Finaled | 12/18/2020 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/15/2016 | MAIDEL LUEVANO |
| CPC | Cleared | 3/15/2016 | MAIDEL LUEVANO |
| Miscellaneous | Cleared | 3/15/2016 | MAIDEL LUEVANO |
| Specific Plan | Cleared | 3/15/2016 | MAIDEL LUEVANO |
| ZA Case | Cleared | 3/15/2016 | MAIDEL LUEVANO |
| ZA Case | Cleared | 3/15/2016 | MAIDEL LUEVANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2016 | ADRIAN HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 3/16/2016 | ADRIAN HERNANDEZ |
| Green Code | Cleared | 3/22/2016 | RICHARD GARCIA |
| DAS Clearance | Cleared | 3/24/2016 | SHINE LIN |
| Excavation more than 5-ft deep | Cleared | 8/8/2016 | CALOSHA APPROVED |
Contact Information
| Contractor | West - Tech Construction Inc; Lic. No.: 803311-B | 10801 KURT ST SYLMAR, CA 91342 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2017 | Corrections Issued | TROY CHRISTIAN |
| Excavation/Setback/Form/Re-Bar | 8/11/2017 | No Access for Inspection | TROY CHRISTIAN |
| Excavation/Setback/Form/Re-Bar | 8/28/2017 | Partial Approval | TROY CHRISTIAN |
| Deputy Reinf. Concrete | 8/30/2017 | Conditional Approval | TROY CHRISTIAN |
| Masonry Wall/Backfill | 10/12/2017 | Partial Approval | TROY CHRISTIAN |
| Wood Frame | 10/17/2017 | Partial Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 10/18/2017 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 10/19/2017 | Partial Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 10/20/2017 | Partial Approval | DANIEL VARNUM |
| Masonry Wall/Backfill | 10/23/2017 | Partial Approval | TROY CHRISTIAN |
| Deputy Reinf. Masonry | 10/24/2017 | Conditional Approval | TROY CHRISTIAN |
| Masonry Wall/Backfill | 10/25/2017 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 10/26/2017 | Conditional Approval | TROY CHRISTIAN |
| Masonry Wall/Backfill | 10/27/2017 | Partial Approval | TROY CHRISTIAN |
| Deputy Reinf. Masonry | 11/1/2017 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 11/1/2017 | Approved | JEFFREY DURAN |
| Deputy Reinf. Masonry | 11/2/2017 | Conditional Approval | JAMES STEPHENS |
| Deputy Reinf. Concrete | 12/1/2017 | Conditional Approval | CAMERON CHABAN |
| Final | 10/3/2018 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 10/3/2018 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Final | 10/3/2018 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 10/3/2018 | Not Ready for Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 10/3/2018 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 10/3/2018 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 10/3/2018 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 12/11/2019 | Not Ready for Inspection | MILLARD ARDOIN |
| Reinforced Masonry Frame | 12/11/2019 | Corrections Issued | MILLARD ARDOIN |
| Structural Steel Frame | 1/3/2020 | Corrections Issued | JEFFREY FULTON |
| Structural Steel Frame | 2/26/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 7/7/2020 | Partial Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 7/16/2020 | Approved | JEFFREY FULTON |
| Final | 8/4/2020 | OK to Issue CofO | JEFFREY FULTON |
| Footing/Foundation/Slab | 8/4/2020 | Approved | JEFFREY FULTON |
| Green Building Final | 8/4/2020 | Approved | JEFFREY FULTON |
| Green Building Rough | 8/4/2020 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 8/4/2020 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 8/4/2020 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 8/4/2020 | Approved | JEFFREY FULTON |