1101 N STRADELLA ROAD 90077

Certificate Information: 1101 N STRADELLA ROAD 90077

Application / Permit
16014-20004-05008
Plan Check / Job No.
B18VN11745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*** TO REVISE TO ADD ADDITIONAL 1790 SQ FT & DECK EXTENSION ALSO REMOVE 68 SF FROM PREVIOUSLY PERMIT & CHANGE ENGINEER/ ARCHITECT OF RECORD & COMPLIANCE FOR NEW BHO***
Permit Issued
Issued on 12/12/2018
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2018 APPLICANT
Green Plans Picked Up 7/24/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 CHON CHIO KUO
Corrections Issued 8/21/2018 CHON CHIO KUO
Quality Review Completed 8/24/2018 STEVEN KIM
Building Plans Picked Up 8/27/2018 APPLICANT
Applicant returned to address corrections 9/20/2018 CHON CHIO KUO
Applicant returned to address corrections 10/3/2018 CHON CHIO KUO
Applicant returned to address corrections 10/11/2018 CHON CHIO KUO
Applicant returned to address corrections 12/11/2018 CHON CHIO KUO
Plan Check Approved 12/12/2018 CHON CHIO KUO
Issued 12/12/2018 LADBS
Permit Finaled 9/9/2022 CHRISTOPHER WILSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/20/2018 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 9/20/2018 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 9/20/2018 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 9/20/2018 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 9/20/2018 JOHN CONNEALLY
Permit Cleared 9/20/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 9/20/2018 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 10/11/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/11/2018 STEVE MELGAR
Green Code Cleared 10/19/2018 MICHAEL AYERS
Work Adjacent to Public Way Cleared 12/5/2018 BOK GOH
GPI Written Notices Cleared 12/11/2018 CHON CHIO KUO
Grading Pre-Inspection Cleared 12/11/2018 CHON CHIO KUO

Contact Information

Architect Pali, Zoltan Emery; Lic. No.: C19741 8609 WASHINGTON BLVD      CULVER CITY, CA 90232
Contractor J D Group Inc; Lic. No.: 675485-B 1537 PONTIUS AVENUE SUITE B      LOS ANGELES, CA 90025
Engineer Paniagua, Cristobal; Lic. No.: C72894 1538 W 92ND ST      LOS ANGELES, CA 90047
Engineer Parker, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025
Engineer Peck, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/18/2018 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/5/2019 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 2/7/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/5/2019 Partial Approval ROBERT SHELLY
Footing/Foundation/Slab 3/13/2019 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/20/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/21/2019 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 3/22/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/29/2019 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 4/1/2019 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/2/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/3/2019 Conditional Approval CHRISTOPHER WILSON
Underground Mechanical 4/17/2019 Partial Approval ROBERT SHELLY
Footing/Foundation/Slab 4/18/2019 No Access for Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 4/19/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/7/2019 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 5/10/2019 Partial Inspection CHRISTOPHER WILSON
Masonry Wall/Backfill 5/16/2019 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/18/2019 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 9/20/2019 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/30/2019 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/3/2019 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Approved CARLOS MATAMOROS
Pre-Inspection 1/9/2020 Corrections Issued CHRISTOPHER WILSON
Structural Steel Frame 4/8/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 4/15/2020 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 5/13/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/13/2020 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 5/21/2020 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/26/2020 Partial Approval CHRISTOPHER WILSON
Insulation 5/26/2020 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 6/2/2020 Corrections Issued ANTHONY MCDOWALL
Interior/Exterior Lathing 6/4/2020 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/22/2020 Corrections Issued CHRISTOPHER WILSON
Final 6/22/2020 Corrections Issued CHRISTOPHER WILSON
Wood Frame 6/24/2020 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/7/2020 Approved CHRISTOPHER WILSON
Green Building Rough 7/7/2020 Approved CHRISTOPHER WILSON
Insulation 7/16/2020 Approved CHRISTOPHER WILSON
Drywall Nailing 8/10/2020 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/19/2020 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/16/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/19/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/20/2020 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/9/2020 Corrections Issued CHRISTOPHER WILSON
Sewer 11/13/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/24/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 12/3/2020 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/17/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 12/17/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 12/17/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 12/17/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 12/24/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 4/7/2021 Corrections Issued CHRISTOPHER WILSON
Shower Pan 4/9/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/22/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 4/26/2021 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 4/28/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/27/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/2/2021 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 2/1/2022 No Access for Inspection JOHN KIDWELL
ELECTRICAL-Rough 2/3/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 2/3/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 2/22/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/28/2022 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/3/2022 No Access for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 3/3/2022 No Access for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 3/4/2022 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/8/2022 Approved CHRISTOPHER WILSON
Service/Power Release 3/29/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 3/31/2022 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 4/15/2022 Approved CHRISTOPHER WILSON
Final 5/18/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/18/2022 Approved CHRISTOPHER WILSON
Green Building Final 5/18/2022 Not Ready for Inspection CHRISTOPHER WILSON
Smoke Detectors 5/18/2022 Not Ready for Inspection CHRISTOPHER WILSON
Grading Pre-Inspection 5/23/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Final 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 7/8/2022 Not Ready for Inspection CHRISTOPHER WILSON
Smoke Detectors 7/8/2022 Approved CHRISTOPHER WILSON
Final 8/31/2022 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 8/31/2022 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 8/31/2022 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 9/7/2022 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 9/7/2022 Partial Approval MICHAEL PELHAM
Final 9/9/2022 Permit Finaled CHRISTOPHER WILSON
Green Building Final 9/9/2022 Approved CHRISTOPHER WILSON