632 S ARDEN BLVD 90005

Certificate Information: 632 S ARDEN BLVD 90005

Application / Permit
16014-20000-06145
Plan Check / Job No.
B16VN17966
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLR (IRR 22'-9" X 27'-4") & 2ND FLR (IRR 32'-9" X 51'-3") ADDITION TO (E) 1-STORY SFD; INTERIOR REMODEL
Permit Issued
Issued on 2/15/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2016 APPLICANT
Assigned to Plan Check Engineer 1/12/2017 NILOOFAR MEHRAIN
Corrections Issued 1/17/2017 NILOOFAR MEHRAIN
Quality Review Completed 1/19/2017 GUANG MIN TUNG
Building Plans Picked Up 1/30/2017 APPLICANT
Green Plans Picked Up 1/30/2017 APPLICANT
Applicant returned to address corrections 10/27/2017 NILOOFAR MEHRAIN
Plan Check Approved 11/6/2017 NILOOFAR MEHRAIN
Issued 2/15/2018 LADBS
CofO in Progress 7/25/2025 RAUL BARAJAS
Permit Finaled 7/27/2025 DEROLD HAUFF
CofO Issued 7/27/2025 DEROLD HAUFF
Permit Finaled 7/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/1/2017 JOHN LIN
Sewer availability Cleared 9/1/2017 JOHN LIN
CPC Cleared 9/7/2017 KIMBERLY HENRY
CPC Cleared 9/7/2017 KIMBERLY HENRY
HPOZ Cleared 9/7/2017 KIMBERLY HENRY
Miscellaneous Cleared 9/7/2017 KIMBERLY HENRY
ZI Cleared 9/7/2017 KIMBERLY HENRY
ZI Cleared 9/7/2017 KIMBERLY HENRY
Low Impact Development Cleared 9/27/2017 SAM NAVID
Specific Plan Cleared 9/28/2017 JOE LUCKEY
Green Code Cleared 10/27/2017 ROLLIN GETTLE III
Roof/Waste drainage to street Cleared 11/6/2017 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Phan, Phillip Trung Tri; Lic. No.: C76425 19221 E NORTHAM      WEST COVINA, CA 91792

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/27/2018 Approved DANNY TOLENTINO
METHANE-Barrier 8/27/2018 Approved DANNY TOLENTINO
METHANE-Subgrade 8/27/2018 Approved DANNY TOLENTINO
Deputy Reinf. Concrete 8/28/2018 Conditional Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 9/13/2018 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 9/18/2018 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 10/10/2018 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 11/21/2018 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 12/12/2018 Corrections Issued DANNY TOLENTINO
PLUMBING-Rough 12/20/2018 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 1/28/2019 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 2/27/2019 Approved DANIEL GONZALEZ
ELECTRICAL-Rough 3/1/2019 Approved JOSEPH MCGARRY
HVAC-Rough 3/20/2019 No Access for Inspection LUIS BARRALES
HVAC-Rough 3/26/2019 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 4/1/2019 Partial Approval DANIEL GONZALEZ
Green Building Rough 4/1/2019 Approved DANIEL GONZALEZ
METHANE-Rough 4/1/2019 Approved DANIEL GONZALEZ
Insulation 4/4/2019 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 4/4/2019 Partial Approval DANIEL GONZALEZ
Drywall Nailing 4/12/2019 Approved LUIS BARRALES
Shower Pan 4/17/2019 Not Ready for Inspection DANIEL GONZALEZ
BUILDING-Rough-Frame 4/19/2019 Corrections Issued DANIEL GONZALEZ
Shower Pan 4/19/2019 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 3/12/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 12/14/2021 No Access for Inspection ARTHUR SARGSYAN
Final 12/14/2021 No Access for Inspection ARTHUR SARGSYAN
Green Building Final 12/14/2021 No Access for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Not Ready ARTHUR SARGSYAN
Smoke Detectors 12/14/2021 No Access for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 4/24/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 4/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 4/24/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/27/2025 Approved RAUL BARAJAS
Final 6/27/2025 Not Ready for Inspection RAUL BARAJAS
Green Building Final 6/27/2025 Approved RAUL BARAJAS
Final 7/11/2025 Corrections Issued RAUL BARAJAS
Final 7/25/2025 OK to Issue CofO RAUL BARAJAS