810 N ORLANDO AVE 90069

Certificate Information: 810 N ORLANDO AVE 90069

Application / Permit
16014-20000-04942
Plan Check / Job No.
B16VN14432
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION OF (N) IRR 50' X 136' HABITABLE BASEMENT WITH 4-CAR GARAGE, IRR. ADDITIONS @ 1ST AND 2ND FLOOR, & PATIO ADDITION AT GRADE TO (E) 2-STORY SFD.
Permit Issued
Issued on 2/16/2017
Issuing Office
Valley
Current Status
CofO Issued on 6/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2016 APPLICANT
Green Plans Picked Up 11/3/2016 APPLICANT
Assigned to Plan Check Engineer 11/10/2016 ALEXANDER SBARDELLATI
Corrections Issued 11/14/2016 ALEXANDER SBARDELLATI
Quality Review Completed 11/15/2016 ARMEN SARKISIAN
Building Plans Picked Up 11/15/2016 APPLICANT
Applicant returned to address corrections 11/30/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/10/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/23/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/25/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/2/2017 ALEXANDER SBARDELLATI
Plan Check Approved 2/16/2017 ALEXANDER SBARDELLATI
Issued 2/16/2017 LADBS
CofO in Progress 6/12/2025 JOSE MACIAS
Permit Finaled 6/22/2025 DEROLD HAUFF
CofO Issued 6/22/2025 DEROLD HAUFF
Permit Finaled 6/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 11/15/2016 LEE GUILBEAUX
Sewer availability Cleared 11/15/2016 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 11/15/2016 LEE GUILBEAUX
CPC Cleared 1/31/2017 RICK TORRES
Green Code Cleared 2/3/2017 RICHARD DOCKUS
Excavation more than 5-ft deep Cleared 2/6/2017 CALOSHA APPROVED
Eng Process Fee Ord 176,300 Cleared 2/14/2017 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 2/14/2017 JOHN DALLAS
Low Impact Development Cleared 2/14/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/14/2017 MARKOS PEREZ-BRAN

Contact Information

Architect Hersey, John P; Lic. No.: C25560 8067 WILLOW GLEN ROAD      LOS ANGELES, CA 90046
Contractor Helpful Hands Services Inc; Lic. No.: 865843-B 32915 LISTIE AVENUE      ACTON, CA 93510
Engineer Zhuang, Wenbin; Lic. No.: S5236 184 S ALTADENA DRIVE      PASADENA, CA 91107

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2017 Not Ready for Inspection RONALD COWAN
Footing/Foundation/Slab 4/27/2017 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 4/27/2017 Partial Inspection RONALD COWAN
Footing/Foundation/Slab 7/7/2017 No Access for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/10/2017 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/27/2017 Not Ready for Inspection RONALD COWAN
Footing/Foundation/Slab 7/28/2017 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/9/2017 Partial Approval RONALD COWAN
Green Building Rough 8/9/2017 Partial Inspection RONALD COWAN
Deputy Steel/Welding 11/27/2017 Approved RAUL BARAJAS
Green Building Rough 11/27/2017 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 11/27/2017 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/14/2017 Approved RAUL BARAJAS
Green Building Rough 12/14/2017 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/18/2018 Partial Approval CRAIG VAUGHAN
Green Building Rough 1/18/2018 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/2/2018 Approved RONALD COWAN
PLUMBING-Rough 3/8/2018 Approved RONALD COWAN
HVAC-Rough 3/9/2018 Not Ready for Inspection LUIS BARRALES
ELECTRICAL-Rough 4/3/2018 Approved RONALD COWAN
HVAC-Rough 4/4/2018 Approved RONALD COWAN
PLUMBING-Rough 4/4/2018 Approved RONALD COWAN
BUILDING-Rough-Frame 4/6/2018 Approved RONALD COWAN
Green Building Rough 4/6/2018 Approved RONALD COWAN
Drywall Nailing 5/3/2018 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 5/3/2018 Approved CRAIG VAUGHAN
Green Building Final 9/18/2018 Approved RONALD COWAN
Drywall Nailing 10/25/2018 Approved RONALD COWAN
Final 10/25/2018 Not Ready for Inspection RONALD COWAN
Reinforced Concrete Frame 10/25/2018 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 10/25/2018 SGSOV Not Ready RONALD COWAN
Smoke Detectors 10/25/2018 Approved RONALD COWAN
Special/Order Compliance 12/11/2019 Corrections Issued JOSEPH MCGARRY
Final 12/17/2019 Corrections Issued JOSEPH MCGARRY
HVAC-Final 12/17/2019 Approved JOSEPH MCGARRY
PLUMBING-Final 12/17/2019 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/17/2019 SGSOV Approved JOSEPH MCGARRY
Special/Order Compliance 6/20/2023 Corrections Issued LILIANA PORTILLO
Final 4/12/2024 Corrections Issued AMIR NAZARIAN
Final 10/7/2024 Corrections Issued JOSE MACIAS
Non Compliance 2/12/2025 Not Required JOSE MACIAS
Final 4/29/2025 Corrections Issued JOSE MACIAS
Final 6/6/2025 Conditional Approval JOSE MACIAS
Final 6/11/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 6/18/2025 Approved JOSE MACIAS