1415 W 220TH ST 90501

Certificate Information: 1415 W 220TH ST 90501

Application / Permit
16014-20000-04707
Plan Check / Job No.
B16VN13697
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
26'-5" X 34'-2" IRREG SHAPED ADDITION & REMODEL TO (E) ONE STORY SFD W/ ATTACHED GARAGE TO CONVERT GARAGE TO BEDROOM, BATHROOM, & FAMILY ROOM; ADD TWO BEDROOMS & FULL BATHROOM; CONVERT BEDROOM TO DEN; & ADD 20'-0" X 18'-0" ATTACHED CARPORT. ALL WORK PER WFPP.
Permit Issued
Issued on 1/3/2017
Issuing Office
Valley
Current Status
CofO Issued on 10/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2016 APPLICANT
Assigned to Plan Check Engineer 10/3/2016 JOSE RODRIGUEZ
Corrections Issued 10/3/2016 JOSE RODRIGUEZ
Plan Check Approved 1/3/2017 JEROME MAGAT PALMA
Issued 1/3/2017 LADBS
CofO in Progress 10/11/2023 EUGENE CASSIDY
Permit Finaled 10/20/2023 ANSON MAGLASANG
CofO Issued 10/20/2023 ANSON MAGLASANG
Permit Finaled 10/20/2023 ANSON MAGLASANG

Permit Application Clearance Information

Low Impact Development Cleared 11/28/2016 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 12/23/2016 ROBERT SAMONTE
Roof/Waste drainage to street Cleared 12/23/2016 ROBERT SAMONTE
Sewer availability Cleared 12/23/2016 ROBERT SAMONTE

Contact Information

Contractor Titan Builders & Remodeling Inc; Lic. No.: 1002561-B 4872 TOPANGA CANYON #402      WOODLAND HILLS, CA 91364

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2017 Corrections Issued DAVID FEILER
Underground Mechanical 2/15/2017 Partial Approval DAVID FEILER
Footing/Foundation/Slab 2/24/2017 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 4/4/2017 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 4/4/2017 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/4/2017 Partial Approval DAVID FEILER
Green Building Rough 4/4/2017 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/4/2017 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 4/7/2017 Not Ready for Inspection DAVID FEILER
Green Building Rough 4/7/2017 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/7/2017 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/3/2017 Partial Approval DAVID FEILER
ELECTRICAL-Rough 5/3/2017 Approved DAVID FEILER
PLUMBING-Rough 5/3/2017 Approved DAVID FEILER
HVAC-Rough 5/18/2017 Approved DAVID FEILER
BUILDING-Rough-Frame 6/1/2017 Approved DAVID FEILER
Green Building Rough 6/1/2017 Approved DAVID FEILER
Interior/Exterior Lathing 6/1/2017 Corrections Issued DAVID FEILER
Insulation 7/6/2017 Approved DAVID FEILER
Drywall Nailing 7/12/2017 Approved DAVID FEILER
Interior/Exterior Lathing 7/12/2017 Partial Approval DAVID FEILER
Interior/Exterior Lathing 8/9/2017 Approved DAVID FEILER
Final 9/26/2017 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 9/26/2017 Approved DAVID FEILER
Green Building Final 9/26/2017 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/26/2017 SGSOV Not Ready DAVID FEILER
Smoke Detectors 9/26/2017 Corrections Issued DAVID FEILER
Special/Order Compliance 7/17/2018 Corrections Issued DAVID FEILER
Final 7/28/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 7/28/2020 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 7/28/2020 Partial Approval JOHN KLARIN
Final 2/16/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 2/16/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/16/2022 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 4/13/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 10/25/2022 Approved EUGENE CASSIDY
Final 1/31/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 1/31/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 1/31/2023 Approved JAMES CHAVEZ
Final 2/7/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 2/7/2023 Approved EUGENE CASSIDY
Final 10/10/2023 OK to Issue CofO EUGENE CASSIDY