11151 N TAMARACK AVE 91331
Certificate Information: 11151 N TAMARACK AVE 91331
- Application / Permit
- 16014-20000-04503
- Plan Check / Job No.
- B16VN13109
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADD 2ND STORY RECREATION ROOM W/ 1/2 BATH AND EXTERIOR ACCESS STAIR TO (E) DETACHED GARAGE
- Permit Issued
- Issued on 1/10/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2016 | SAM CHANG |
| Corrections Issued | 10/18/2016 | SAM CHANG |
| Quality Review Completed | 10/18/2016 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/19/2016 | APPLICANT |
| Green Plans Picked Up | 10/19/2016 | APPLICANT |
| Applicant returned to address corrections | 12/2/2016 | SAM CHANG |
| Plan Check Approved | 1/10/2017 | SAM CHANG |
| Issued | 1/10/2017 | LADBS |
| CofO in Progress | 12/23/2021 | MICHEL ABAJAN |
| Permit Finaled | 1/19/2022 | MICHAEL SMITH |
| CofO Issued | 1/19/2022 | MICHAEL SMITH |
| Permit Finaled | 1/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2016 | IRENE CHIA |
| Green Code | Cleared | 12/2/2016 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 12/2/2016 | IRENE CHIA |
| Construction near power lines | Cleared | 1/9/2017 | LUCIO FERRER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2017 | Approved | JEFFREY PARD |
| METHANE-Barrier | 1/27/2017 | Approved | JEFFREY PARD |
| METHANE-Subgrade | 1/27/2017 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2017 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 6/27/2017 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/24/2019 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 6/24/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 6/24/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/13/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/23/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/23/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/23/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/23/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/23/2021 | Approved | MICHEL ABAJAN |
| Insulation | 3/8/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/8/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/15/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 3/26/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/7/2021 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 6/7/2021 | Approved | MICHEL ABAJAN |
| Final | 10/20/2021 | Conditional Approval | MICHEL ABAJAN |
| Green Building Final | 10/20/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/20/2021 | Approved | MICHEL ABAJAN |
| Final | 10/26/2021 | OK to Issue CofO | MICHEL ABAJAN |