8185 W HOLLYWOOD BLVD 90069

Certificate Information: 8185 W HOLLYWOOD BLVD 90069

Application / Permit
16014-20000-03819
Plan Check / Job No.
B16VN10906
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
43'-0" X 19'-0" IRREG SHAPED TWO STORY ADDITION AND REMODEL TO EXISTING TWO STORY SINGLE FAMILY DWELLING TO ENLARGE MASTER BATHROOM AND CLOSET, RELOCATE TWO BEDROOMS AND TWO BATHROOMS, AND CONVERT STORAGE ROOM TO DEN.
Permit Issued
Issued on 10/27/2017
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2016 APPLICANT
Green Plans Picked Up 8/25/2016 APPLICANT
Assigned to Plan Check Engineer 9/1/2016 JEROME MAGAT PALMA
Corrections Issued 9/7/2016 JEROME MAGAT PALMA
Quality Review Completed 9/7/2016 MOURAD AZIZ
Building Plans Picked Up 9/9/2016 APPLICANT
Plan Check Approved 5/30/2017 JEROME MAGAT PALMA
Issued 10/27/2017 LADBS
CofO in Progress 7/28/2025 ROY SPAULDING
Permit Finaled 7/29/2025 DEROLD HAUFF
CofO Issued 7/29/2025 DEROLD HAUFF
Permit Finaled 7/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/30/2016 YESENIA DIAZ
Hydrant and Access approval Cleared 9/30/2016 OSCAR SALGADO JR
Sewer availability Cleared 9/30/2016 YESENIA DIAZ
Low Impact Development Cleared 5/5/2017 SAM NAVID
Green Code Cleared 5/11/2017 MICHAEL AYERS
Roof/Waste drainage to street Cleared 5/11/2017 KENNETH PHAM
GPI Written Notices Cleared 5/30/2017 JEROME MAGAT PALMA
Grading Pre-Inspection Cleared 5/30/2017 JEROME MAGAT PALMA

Contact Information

Contractor Dixie Builders Inc; Lic. No.: 899179-B 20058 VENTURA BLVD #240      WOODLAND HILLS, CA 91364
Engineer Adams, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304
Engineer Su, Yu-Ting; Lic. No.: C76714 PO BOX 1290      TUSTIN, CA 92781
Geologist Carrle, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/17/2018 Approved DONALD GALLAGHER
Pre-Inspection 10/12/2022 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 2/15/2023 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 2/16/2023 Conditional Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 2/21/2023 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 4/5/2023 Partial Approval STUART CHAPMAN
Green Building Rough 4/5/2023 Not Ready for Inspection STUART CHAPMAN
Wood Frame 4/5/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 5/23/2023 Approved STUART CHAPMAN
Sewer 5/23/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 6/8/2023 Approved RAUL BARAJAS
HVAC-Rough 6/8/2023 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/8/2023 Approved RAUL BARAJAS
HVAC-Rough 6/20/2023 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 6/20/2023 Approved STUART CHAPMAN
HVAC-Rough 6/26/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 6/30/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/17/2023 Approved RAUL BARAJAS
Green Building Rough 7/17/2023 Approved RAUL BARAJAS
HVAC-Rough 7/17/2023 Partial Approval RAUL BARAJAS
Insulation 7/24/2023 Approved RAUL BARAJAS
Shower Pan 7/24/2023 Approved RAUL BARAJAS
Drywall Nailing 8/15/2023 Approved STUART CHAPMAN
Final 4/24/2024 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/24/2024 Approved RAUL BARAJAS
Green Building Final 4/24/2024 Partial Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 4/24/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 7/18/2024 Approved RAUL BARAJAS
Gas Test 7/24/2024 Approved RAUL BARAJAS
HVAC-Final 7/24/2024 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 8/16/2024 Approved RAUL BARAJAS
Reinforced Concrete Frame 5/14/2025 Not Ready for Inspection ROY SPAULDING
Final 7/1/2025 Conditional Approval ROY SPAULDING
Green Building Final 7/1/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved ROY SPAULDING
Smoke Detectors 7/1/2025 Approved ROY SPAULDING
Final 7/10/2025 Conditional Approval ROY SPAULDING
Final 7/21/2025 Conditional Approval ROY SPAULDING
Final 7/23/2025 OK to Issue CofO ROY SPAULDING