8185 W HOLLYWOOD BLVD 90069
Certificate Information: 8185 W HOLLYWOOD BLVD 90069
- Application / Permit
- 16014-20000-03819
- Plan Check / Job No.
- B16VN10906
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 43'-0" X 19'-0" IRREG SHAPED TWO STORY ADDITION AND REMODEL TO EXISTING TWO STORY SINGLE FAMILY DWELLING TO ENLARGE MASTER BATHROOM AND CLOSET, RELOCATE TWO BEDROOMS AND TWO BATHROOMS, AND CONVERT STORAGE ROOM TO DEN.
- Permit Issued
- Issued on 10/27/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2016 | APPLICANT |
| Green Plans Picked Up | 8/25/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2016 | JEROME MAGAT PALMA |
| Corrections Issued | 9/7/2016 | JEROME MAGAT PALMA |
| Quality Review Completed | 9/7/2016 | MOURAD AZIZ |
| Building Plans Picked Up | 9/9/2016 | APPLICANT |
| Plan Check Approved | 5/30/2017 | JEROME MAGAT PALMA |
| Issued | 10/27/2017 | LADBS |
| CofO in Progress | 7/28/2025 | ROY SPAULDING |
| Permit Finaled | 7/29/2025 | DEROLD HAUFF |
| CofO Issued | 7/29/2025 | DEROLD HAUFF |
| Permit Finaled | 7/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2016 | YESENIA DIAZ |
| Hydrant and Access approval | Cleared | 9/30/2016 | OSCAR SALGADO JR |
| Sewer availability | Cleared | 9/30/2016 | YESENIA DIAZ |
| Low Impact Development | Cleared | 5/5/2017 | SAM NAVID |
| Green Code | Cleared | 5/11/2017 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 5/11/2017 | KENNETH PHAM |
| GPI Written Notices | Cleared | 5/30/2017 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 5/30/2017 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Dixie Builders Inc; Lic. No.: 899179-B | 20058 VENTURA BLVD #240 WOODLAND HILLS, CA 91364 |
| Engineer | Adams, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
| Engineer | Su, Yu-Ting; Lic. No.: C76714 | PO BOX 1290 TUSTIN, CA 92781 |
| Geologist | Carrle, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/17/2018 | Approved | DONALD GALLAGHER |
| Pre-Inspection | 10/12/2022 | Partial Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 2/15/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 2/16/2023 | Conditional Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 2/21/2023 | Partial Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/5/2023 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 4/5/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 4/5/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 5/23/2023 | Approved | STUART CHAPMAN |
| Sewer | 5/23/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/8/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 6/8/2023 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/8/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 6/20/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 6/20/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 6/26/2023 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 6/30/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | RAUL BARAJAS |
| Green Building Rough | 7/17/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 7/17/2023 | Partial Approval | RAUL BARAJAS |
| Insulation | 7/24/2023 | Approved | RAUL BARAJAS |
| Shower Pan | 7/24/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 8/15/2023 | Approved | STUART CHAPMAN |
| Final | 4/24/2024 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/24/2024 | Approved | RAUL BARAJAS |
| Green Building Final | 4/24/2024 | Partial Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 4/24/2024 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 7/18/2024 | Approved | RAUL BARAJAS |
| Gas Test | 7/24/2024 | Approved | RAUL BARAJAS |
| HVAC-Final | 7/24/2024 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 8/16/2024 | Approved | RAUL BARAJAS |
| Reinforced Concrete Frame | 5/14/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 7/1/2025 | Conditional Approval | ROY SPAULDING |
| Green Building Final | 7/1/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 7/1/2025 | Approved | ROY SPAULDING |
| Final | 7/10/2025 | Conditional Approval | ROY SPAULDING |
| Final | 7/21/2025 | Conditional Approval | ROY SPAULDING |
| Final | 7/23/2025 | OK to Issue CofO | ROY SPAULDING |