9487 W REMBERT LANE 90210

Certificate Information: 9487 W REMBERT LANE 90210

Application / Permit
16014-20000-03656
Plan Check / Job No.
B16VN10382
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Relocate and Add 25'-6" x 15'-0" Irr. to Kitchen, Remove 2'-6" x 8'-6" por. (E) Dining Room, and Add 2'-6" x 8'-6" Covered Entry, Convert 10' x 9' Irr. por. (E) Storage into Half Bath and Closet on First Floor.
Permit Issued
Issued on 2/28/2017
Issuing Office
Valley
Current Status
CofO Issued on 3/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2016 APPLICANT
Assigned to Plan Check Engineer 8/2/2016 JOSE RODRIGUEZ
Corrections Issued 8/2/2016 JOSE RODRIGUEZ
Plan Check Approved 8/5/2016 OMID HEDAYAT
Issued 2/28/2017 LADBS
CofO in Progress 10/7/2022 RAUL BARAJAS
Permit Finaled 3/25/2023 DANIEL ORRANTE
CofO Issued 3/25/2023 DANIEL ORRANTE
Permit Finaled 3/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/2/2016 LEE GUILBEAUX
Specific Plan Cleared 8/2/2016 HERMINIGILDO AGUSTIN
ZA Case Cleared 8/2/2016 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 8/5/2016 YESENIA DIAZ
Grading Pre-Inspection Cleared 8/5/2016 JOSE RODRIGUEZ

Contact Information

Architect Oatway, Nicholas B; Lic. No.: C9372 P O BOX 1872      OJAI, CA 93024
Contractor Owner-Builder       ,
Engineer Hornstein, Marvin A; Lic. No.: S875 4535 NOGALES DR      TARZANA, CA 91356

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2018 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 2/28/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 2/28/2019 Not Ready for Inspection DANNY TOLENTINO
PLUMBING-Rough 2/28/2019 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 4/25/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/25/2019 Approved DANNY TOLENTINO
PLUMBING-Rough 4/25/2019 Not Ready for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 10/30/2019 Approved RICHARD STEINBACH
Special/Order Compliance 9/2/2020 Corrections Issued RICHARD STEINBACH
Insulation 7/12/2021 Corrections Issued JUSTIN HAWLEY
Special/Order Compliance 7/14/2021 Partial Inspection RICHARD STEINBACH
Drywall Nailing 8/6/2021 Partial Approval RAUL BARAJAS
Green Building Rough 8/6/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 5/4/2022 Approved RAUL BARAJAS
Drywall Nailing 5/4/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 5/4/2022 Not Ready for Inspection RAUL BARAJAS
Final 5/4/2022 Corrections Issued RAUL BARAJAS
Green Building Final 5/4/2022 Conditional Approval RAUL BARAJAS
HVAC-Final 5/4/2022 Conditional Approval RAUL BARAJAS
PLUMBING-Final 5/4/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 5/4/2022 Approved RAUL BARAJAS
Final 6/15/2022 No Access for Inspection RAUL BARAJAS
Green Building Final 6/15/2022 No Access for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Not Ready RAUL BARAJAS
Final 7/18/2022 Corrections Issued RAUL BARAJAS
Green Building Final 7/18/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Not Ready RAUL BARAJAS
Final 7/21/2022 No Access for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Approved RAUL BARAJAS
Final 10/7/2022 OK to Issue CofO RAUL BARAJAS