1678 N CLEAR VIEW DR 90210
Certificate Information: 1678 N CLEAR VIEW DR 90210
- Application / Permit
- 16014-20000-03637
- Plan Check / Job No.
- B16VN10329
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Construct 15'-3"x 42'-0" odd shaped groundfloor addition and 59'-9"x 38'-6" 2nd floor addition to existing 2 story SFD.
- Permit Issued
- Issued on 11/22/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2016 | APPLICANT |
| Green Plans Picked Up | 9/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2016 | VU NGUYEN |
| Corrections Issued | 9/22/2016 | VU NGUYEN |
| Quality Review Completed | 9/22/2016 | GUANG MIN TUNG |
| Building Plans Picked Up | 9/22/2016 | APPLICANT |
| Plan Check Approved | 11/18/2016 | VU NGUYEN |
| Issued | 11/22/2016 | LADBS |
| CofO in Progress | 11/18/2021 | CHRISTOPHER WILSON |
| Permit Finaled | 12/1/2021 | DANIEL ORRANTE |
| CofO Issued | 12/1/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/1/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/4/2016 | IRENE CHIA |
| BHO/Hillside ordinance | Cleared | 11/4/2016 | IRENE CHIA |
| BHO/Hillside ordinance | Cleared | 11/4/2016 | IRENE CHIA |
| Highway dedication | Cleared | 11/4/2016 | IRENE CHIA |
| Hydrant and Access approval | Cleared | 11/7/2016 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/15/2016 | RYAN HUDSON |
| Green Code | Cleared | 11/17/2016 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2016 | IRENE CHIA |
| Grading Pre-Inspection | Cleared | 11/18/2016 | VU NGUYEN |
| Roof/Waste drainage to street | Cleared | 11/18/2016 | IRENE CHIA |
Contact Information
| Architect | Huddy, Robert Francis; Lic. No.: C20474 | 3648 GOODLAND DR STUDIO CITY, CA 91604 |
| Contractor | Gotham Developments Llc; Lic. No.: 1011034-B | 8306 WILSHIRE BLVD #602 BEVERLY HILLS, CA 90211 |
| Engineer | Shagirian, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/30/2017 | Corrections Issued | JOEL LAUNCHBAUGH |
| PLUMBING-Rough | 4/5/2017 | Partial Approval | JOEL LAUNCHBAUGH |
| Excavation/Setback/Form/Re-Bar | 4/12/2017 | Approved | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 4/12/2017 | Corrections Issued | JOEL LAUNCHBAUGH |
| Excavation/Setback/Form/Re-Bar | 4/13/2017 | Approved | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2017 | Approved | JOEL LAUNCHBAUGH |
| Green Building Rough | 6/9/2017 | Partial Inspection | JOEL LAUNCHBAUGH |
| Verify Sprinkler Sign Off | 6/9/2017 | Partial Inspection | JOEL LAUNCHBAUGH |
| Wood Frame | 6/9/2017 | Partial Inspection | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2017 | Corrections Issued | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2017 | Approved | JOEL LAUNCHBAUGH |
| ELECTRICAL-Rough | 10/20/2017 | Partial Approval | JOEL LAUNCHBAUGH |
| PLUMBING-Rough | 10/20/2017 | Partial Approval | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2018 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 1/25/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| HVAC-Rough | 1/25/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| PLUMBING-Rough | 1/25/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2018 | Corrections Issued | JOEL LAUNCHBAUGH |
| Green Building Rough | 2/6/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| HVAC-Rough | 2/6/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| PLUMBING-Rough | 2/6/2018 | Corrections Issued | JOEL LAUNCHBAUGH |
| Verify Sprinkler Sign Off | 2/6/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2018 | Partial Approval | JOEL LAUNCHBAUGH |
| Green Building Rough | 2/8/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| HVAC-Rough | 2/8/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Verify Sprinkler Sign Off | 2/8/2018 | Corrections Issued | JOEL LAUNCHBAUGH |
| PLUMBING-Rough | 2/13/2018 | Approved | JOEL LAUNCHBAUGH |
| ELECTRICAL-Rough | 2/16/2018 | Approved | JOEL LAUNCHBAUGH |
| HVAC-Rough | 2/16/2018 | Corrections Issued | JOEL LAUNCHBAUGH |
| PLUMBING-Rough | 2/16/2018 | Approved | JOEL LAUNCHBAUGH |
| Special/Order Compliance | 2/21/2018 | Corrections Issued | JOEL LAUNCHBAUGH |
| HVAC-Rough | 2/26/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| BUILDING-Rough-Frame | 2/28/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Green Building Rough | 2/28/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Verify Sprinkler Sign Off | 2/28/2018 | Approved | JOEL LAUNCHBAUGH |
| BUILDING-Rough-Frame | 3/5/2018 | Approved | JOEL LAUNCHBAUGH |
| Green Building Rough | 3/5/2018 | Approved | JOEL LAUNCHBAUGH |
| HVAC-Rough | 3/5/2018 | Approved | JOEL LAUNCHBAUGH |
| Insulation | 3/9/2018 | Partial Approval | JONATHAN HOM |
| Insulation | 3/14/2018 | Corrections Issued | RYAN MCGILL |
| Interior/Exterior Lathing | 3/14/2018 | Partial Approval | RYAN MCGILL |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2018 | Approved | JOEL LAUNCHBAUGH |
| Shower Pan | 3/20/2018 | Approved | JOEL LAUNCHBAUGH |
| Drywall Nailing | 3/29/2018 | Approved | RYAN MCGILL |
| Insulation | 3/29/2018 | Approved | RYAN MCGILL |
| Interior/Exterior Lathing | 3/29/2018 | Approved | RYAN MCGILL |
| Special/Order Compliance | 12/29/2018 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 1/5/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 3/5/2019 | Not Required | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Partial Approval | ANTHONY MCDOWALL |
| Sewer | 10/19/2020 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 12/9/2020 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 1/21/2021 | Approved | ANTHONY MCDOWALL |
| Final | 9/15/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/15/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 9/15/2021 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 9/15/2021 | Approved | CHRISTOPHER WILSON |
| Final | 11/2/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 11/3/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 11/12/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 11/16/2021 | Conditional Approval | CHRISTOPHER WILSON |