4213 N VAN NUYS BLVD 91403

Certificate Information: 4213 N VAN NUYS BLVD 91403

Application / Permit
16014-20000-03621
Plan Check / Job No.
B16VN10295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Construct 3,126.3sf addition (1st floor and new 2nd floor) to existing 1,550sf 1 story SFD. Demo existing detached garage. Major interior remodel with new attached garage.
Permit Issued
Issued on 11/1/2016
Issuing Office
Valley
Current Status
CofO Issued on 6/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2016 APPLICANT
Green Plans Picked Up 9/2/2016 APPLICANT
Assigned to Plan Check Engineer 9/15/2016 VU NGUYEN
Corrections Issued 9/21/2016 VU NGUYEN
Quality Review Completed 9/21/2016 GUANG MIN TUNG
Building Plans Picked Up 9/22/2016 APPLICANT
Plan Check Approved 11/1/2016 VU NGUYEN
Issued 11/1/2016 LADBS
CofO in Progress 3/10/2022 JACK KARGODORIAN
Permit Finaled 6/4/2022 MICHAEL SMITH
CofO Issued 6/4/2022 MICHAEL SMITH
Permit Finaled 6/4/2022 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/23/2016 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 9/23/2016 RICHARD SOUTHERLAND
Eng Process Fee Ord 176,300 Cleared 9/23/2016 RICHARD SOUTHERLAND
Permit Cleared 9/23/2016 RICHARD SOUTHERLAND
Sewer availability Cleared 9/23/2016 RICHARD SOUTHERLAND
ZI Cleared 9/23/2016 TRACY WILLIAMS
Low Impact Development Cleared 10/21/2016 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/27/2016 ROBERT SAMONTE
Green Code Cleared 10/28/2016 RICHARD DOCKUS
Grading Pre-Inspection Cleared 11/1/2016 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/22/2017 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/22/2017 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 3/28/2017 Partial Approval JOHN KIDWELL
Deputy Steel/Welding 4/10/2017 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/20/2017 Approved JOHN KIDWELL
Deputy Reinf. Concrete 4/24/2017 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/26/2017 Conditional Approval JOHN KIDWELL
Underground Mechanical 4/26/2017 Conditional Approval JOHN KIDWELL
Deputy Steel/Welding 5/9/2017 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/20/2017 Conditional Approval JOHN KIDWELL
ELECTRICAL-Rough 10/12/2017 Approved JOHN KIDWELL
PLUMBING-Rough 10/12/2017 Approved JOHN KIDWELL
HVAC-Rough 11/28/2017 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 11/30/2017 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/28/2017 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 1/17/2018 Approved JOHN KIDWELL
Green Building Rough 1/17/2018 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 1/17/2018 Approved JOHN KIDWELL
Drywall Nailing 1/26/2018 Approved JOHN KIDWELL
Shower Pan 4/4/2018 Approved JOHN KIDWELL
Final 9/21/2018 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 9/25/2018 Partial Approval COREY HUPP
ELECTRICAL-Rough 3/29/2019 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 10/1/2019 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 9/2/2020 Corrections Issued CHARLES POWELL
Final 3/10/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 3/10/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 3/10/2022 Approved JACK KARGODORIAN
Smoke Detectors 3/10/2022 Approved JACK KARGODORIAN