7413 W 91ST ST 90045

Certificate Information: 7413 W 91ST ST 90045

Application / Permit
16014-20000-02855
Plan Check / Job No.
B16VN08120
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AT FIRST FLOOR AND ADDITION OF (N) SECOND FLOOR ON TOP. FULLY SPRINKLER - NFPA-13D. SEE COMMENTS.
Permit Issued
Issued on 12/15/2017
Issuing Office
West Los Angeles
Current Status
Issued on 12/15/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2016 APPLICANT
Assigned to Plan Check Engineer 7/28/2016 MENA WASSEF
Corrections Issued 9/1/2016 MENA WASSEF
Quality Review Completed 9/2/2016 GUANG MIN TUNG
Building Plans Picked Up 9/7/2016 APPLICANT
Green Plans Picked Up 9/7/2016 APPLICANT
Applicant returned to address corrections 4/26/2017 MENA WASSEF
Plan Check Approved 5/16/2017 MENA WASSEF
Issued 12/15/2017 LADBS

Permit Application Clearance Information

Address approval Cleared 3/28/2017 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 3/28/2017 MENA WASSEF
Hydrant and Access approval Cleared 3/28/2017 OSCAR SALGADO JR
Sewer availability Cleared 3/28/2017 MENA WASSEF
Green Code Cleared 4/4/2017 ROLLIN GETTLE III
Low Impact Development Cleared 4/14/2017 RYAN HUDSON
Permit Cleared 4/14/2017 ROCHELLE DUNGCA
Roof/Waste drainage to street Cleared 4/14/2017 ROCHELLE DUNGCA
Grading Pre-Inspection Cleared 5/16/2017 MENA WASSEF

Contact Information

Architect Richards, Mark D; Lic. No.: C27531 559 AZURE HILLS DRIVE      SIMI VALLEY, CA 93065
Contractor Owner-Builder       ,
Engineer Warling, Jeffrey Paul; Lic. No.: C43743 2828 COCHRAN STREET 321      SIMI VALLEY, CA 93065

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/25/2018 No Access for Inspection DAVID HEINE
Pre-Inspection 12/28/2018 Partial Inspection RONALD WEBER
Piling/Pier/Caisson 1/8/2019 Partial Approval RONALD WEBER
Deputy Drilled-In Anchors 1/29/2019 Conditional Approval RONALD WEBER
Footing/Foundation/Slab 1/29/2019 Approved RONALD WEBER
Deputy Reinf. Concrete 1/31/2019 Conditional Approval RONALD WEBER
BUILDING-Rough-Frame 2/13/2019 Partial Approval RONALD WEBER
PLUMBING-Rough 2/13/2019 Partial Approval RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 3/21/2019 Partial Approval JUAN VALENZUELA
Deputy Steel/Welding 3/22/2019 Conditional Approval JUAN VALENZUELA
Underground Mechanical 5/10/2019 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/30/2019 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 7/8/2019 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/7/2019 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/26/2019 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 11/15/2019 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/10/2019 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/17/2019 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 12/17/2019 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/6/2020 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 4/6/2020 Approved JUAN VALENZUELA
Gas Test 4/6/2020 Corrections Issued JUAN VALENZUELA
Green Building Rough 4/6/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 4/6/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 4/6/2020 Partial Approval JUAN VALENZUELA
Shower Pan 4/6/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/6/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 4/24/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 4/24/2020 Approved JUAN VALENZUELA
HVAC-Rough 4/24/2020 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 4/24/2020 Partial Approval JUAN VALENZUELA
Insulation 5/18/2020 Approved ANTHONY MCDOWALL
Drywall Nailing 6/2/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/27/2020 Partial Approval JUAN VALENZUELA
Underground Mechanical 8/18/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 9/11/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 9/11/2020 Corrections Issued JUAN VALENZUELA